Advanced Design, Fabrication, and Testing
August 1965
1965
August 2
NASA announced plans to install Apollo Unified S-Band System 
equipment at its Corpus Christi, Tex., tracking station. The Unified S-Band 
equipment included a 9-m (30-ft) diameter parabolic antenna and would enable 
handling of seven different types of communications with two different vehicles, 
the CM and the LEM. The communications would: track the spacecraft; command its 
operations and confirm that the command had been executed; provide two-way voice 
conversation with three astronauts; keep a continuous check on the astronauts' 
health; make continuous checks on the spacecraft and its functions; supply a 
continuous flow of information from the Apollo onboard experiments; and transmit 
television of the astronauts and the exploration of the moon.
NASA News Release 65-250, "NASA to Install Apollo Unified S-Band Tracking at 
Corpus Christi Station," August 2, 1965; Space Business Daily, 
August 3, 1965, p. 156.
August 2
NASA's office at Downey, Calif., approved the contract with the 
Marquardt Corporation for the procurement of Block II SM reaction control system 
engines. Estimated cost of the fixed price contract would be $6.5 million. 
Marquardt was supplying the Block I SM engines.
TWX, Henry S. Smith, NASA-Downey, to NASA Headquarters, Attn: Director of 
Procurement and Supply Division, August 2, 1965.
August 2
Hamilton Standard shipped the first prototype portable life 
support system to Houston, where it would undergo testing by the Crew Systems 
Division.
MSC News Release 65-68, August 2, 1965; Space Business Daily, 
August 5, 1965, p. 172.
August 2
MSC informed Grumman of package dimensions and weight 
restrictions for the scientific equipment and packages to be stored in the LEM.
TWXs, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, August 2, 1965.
August 3
NASA named three firms, Bendix Systems Division, TRW Systems 
Group, and Space-General Corporation to design prototypes of the Apollo Lunar 
Surface Experiments Package (ALSEP). Each company received a $500,000, six-month 
contract. After delivery of the prototypes, MSC would select one of the three to 
develop the ALSEP flight hardware.
NASA Headquarters Release No. 65-260, "Three Firms Selected to Design Apollo 
Lunar Surface Package," August 4, 1965; letter, Samuel C. Phillips, NASA, to 
Robert O. Piland, MSC, "Selection of Contractors for Apollo Lunar Surface 
Experiments Package," September 10, 1965.
August 3
Grumman reported the status of its effort to lighten the LEM. 
Despite some relief afforded by recent program changes (e.g., revised velocity 
budgets and the replacing of fuel cells with batteries), the contractor admitted 
that significant increases resulted as the design of the spacecraft matured. 
Grumman recommended, and MSC approved, a Super Weight Improvement Program (SWIP) 
similar to the one that the company had used in its F-111 aircraft program. By 
the end of the month, the company reported that SWIP had trimmed about 45 kg 
(100 lbs) from the ascent and about 25 kg (55 lbs) from the descent stages of 
the spacecraft. Grumman assured MSC that the SWIP team's attack on the complete 
vehicle, including its equipment, would be completed prior to the series of LEM 
design reviews scheduled for late in the year.
ASPO, "Minutes, NASA/GAEC Program Management Meeting, August 3, 1965"; GAEC, 
"Monthly Progress Report No. 31," LPR-10-47, September 10, 1965, p. 1.
August 4
During the next 10 months, 200 employees of MSFC would be 
transferred to MSC to augment the Houston staff for the operational phase of the 
Apollo program. Completion of the first phase of the Saturn program (with the 
successful launch of SA-10) made it possible for Marshall to release qualified 
personnel to satisfy MSC's needs.
Space Business Daily, August 9, 1965, p. 187; memorandum, 
Wernher von Braun, MSFC, to Distr., "Marshall's Changing Role in the Space 
Program," August 13, 1965.
August 5
During tests of the Apollo earth landing system (ELS) at El 
Centro, Calif., boilerplate (BP) 6A sustained considerable damage in a drop that 
was to have demonstrated ELS performance during a simulated apex-forward pad 
abort. Oscillating severely at the time the auxiliary brake parachute was 
opened, the spacecraft severed two of the electrical lines that were to have 
released that device. Although the ELS sequence took place as planned, the 
still-attached brake prevented proper operation of the drogues and full 
inflation of the mains. As a result, BP-6A landed at a speed of about 50 fps.
"ASPO Weekly Management Report, August 5-12, 1965."
August 5
 
 
The S-IC stage during static firing at MSFC. 
The Saturn V's booster, the S-IC stage, made a "perfect" full-duration static 
firing by burning for the programmed 2.5 minutes at its full 33,360-kilonewton 
(7.5-million-lbs) thrust in a test conducted at MSFC. The test model 
demonstrated its steering capability on command from the blockhouse after 100 
sec had elapsed; the firing consumed 2.133-million liters (537,000 gallons) of 
kerosene and liquid oxygen.
Space Business Daily, August 9, 1965, p. 185.
August 5-12 
North American developed a plan to process NASA- and 
contractor-initiated design changes through a Change Control Board (CCB). 
Indications were that the contractor's Apollo Program Manager would implement 
the plan on August 19. Elevating the level of management on the CCB, together 
with a standard approach to processing changes, was expected to improve the 
technical definition and documentation of design changes. In addition, program 
baselines were being established to permit a more informed control of technical 
requirements.
"ASPO Weekly Management Report, August 5-12, 1965."
August 6
North American and MSC attended a design review at 
Ling-Temco-Vought on the environmental control system radiator for the Block II 
CSM. After reviewing design and performance analyses, the review team approved 
changes in testing and fabrication of test hardware.
Memorandum, Richard J. Gillen, MSC, to Chief, Crew Systems Division, "Trip to 
Ling-Temco-Vought, Dallas, Texas, on August 6, 1965, Block II ECS radiator," 
August 20, 1965; MSC, "ASPO Weekly Management Report, August 26-September 2, 
1965."
August 6
Crew Systems Division (CSD) reported that changing the method 
for storing oxygen in the LEM (from cryogenic to gaseous) had complicated the 
interface between the spacecraft's environmental control system (ECS) and the 
portable life support system (PLSS). Very early, the maximum temperature for 
oxygen at the PLSS recharge station had been placed at 80 degrees. Recent 
analyses by Grumman disclosed that, in fact, the gas temperature might be double 
that figure. Oxygen supplied at 160 degrees, CSD said, would limit to 2½ hours 
the PLSS operating period. Modifying the PLSS, however, would revive the issue 
of its storage aboard both spacecraft.
Seeking some answer to this problem, CSD engineers began in-house studies of 
temperature changes in the spacecraft's oxygen. There was some optimism that 
Grumman's estimates would be proved much too high, and MSC thus far had made no 
changes either to the ECS or to the PLSS.
Memorandum, Richard E. Mayo, MSC, to Chief, Systems Engineering Division, 
"ECS thermal control configuration for 'battery' LEM," August 9, 1965; "ASPO 
Weekly Management Report, August 5-12, 1965."
August 9
Two Saturn milestones occurred on the same day. At Santa 
Susana, Calif., North American conducted the first full-duration captive firing 
of an S-II, second stage of the Saturn V. And at Sacramento, Douglas 
static-tested the first flight-model S-IVB, second stage for the Saturn IB. This 
latter marked the first time that a complete static test (encompassing vehicle 
checkout, loading, and firing) had been controlled entirely by computers.
TWX, Wernher von Braun, MSFC, to NASA Headquarters, Attn: George Mueller, 
August 11, 1965; Space Business Daily, August 12, 1965, p. 207.
August 10
MSC notified North American that, should one of the CM's 
postlanding batteries fail, the crew could lower the power requirements of the 
spacecraft during recovery and thus stay within the capabilities of the two 
remaining batteries.
TWX, C. L. Taylor, MSC, to NAA, Space and Information Systems Division, Attn: 
J. C. Cozad, August 10, 1965.
August 10
ASPO forwarded to Grumman the following schedule dates which 
should be used for submission of detailed vehicle test plans:
  
  
    | AS Mission | Vehicle Test Plan | Schedule Date | 
  
    | 206 | LEM-1 | 9-1-65 | 
  
    | 207 | LEM-2 | 12-1-65 | 
  
    | 503 | LEM-3 | 2-1-66 | 
  
    | 504 | LEM-4 | 5-1-66 | 
  
    | 505 | LEM-5 | 7-1-66 | 
  
    | 506 | LEM-6 | 11-1-66 | 
When determination of LEM test articles to 
be used on Missions 501 and 502 had been finalized, test plan dates would be 
forwarded. Current dates for 501 and 502 detailed vehicle test plans were 
8-15-65 and 11-1-65, respectively.
TWX, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, "Vehicle Test Plan 
Schedule Dates," August 10, 1965.
August 12
Resident ASPO quality assurance officers at North American 
began investigating recent failures of titanium tanks at Bell Aerosystems. 
Concern about this problem had been expressed by the Apollo Test Directorate at 
NASA Hq in July and MSC started an investigation at that time. The eventual 
solution (a change in the nitrogen tetroxide specification) was contributed to 
by North American, Bell Aero Systems, the Boeing Company, MSFC, MSC, Langley 
Research Center, and a committee chaired by John Scheller of NASA Hq. The 
penstripe method to find cracks on the interior of the vessels was used to solve 
the problem. The quality assurance people viewed the failures as quite serious 
since Bell had already fabricated about 180 such tanks.
MSC, "Minutes of Senior Staff Meeting, August 6, 1965," John B. Lee, 
Recorder, p. 3; memorandum, L. E. Day, NASA to Melvyn Savage, "Apollo N2O4 Tank 
Problems," August 18, 1965; "ASPO Weekly Management Report, August 5-12, 1965"; 
memorandum, Director, Apollo Soyuz Test Project Engineering, NASA Hq, to Acting 
Director, NASA Historical Office, "Volume III of The Apollo Spacecraft: A 
Chronology," sgd. Charles H. King, Jr., May 7, 1973.
August 12
Samuel C. Phillips, Apollo Program Director, listed the six 
key checkpoints in the development of Apollo hardware:
  - Preliminary Design Review (PDR) - a review of the basic design 
  conducted before or during the detailed design phase. 
  
- Critical Design Review (CDR) - a review of specifications and 
  engineering drawings preceding, if possible, their release for manufacture. 
  
- Flight Article Configuration Inspection (FACI) - a comparison of 
  hardware with specifications and drawings and the validation of acceptance 
  testing. FACIs could be repeated to ensure that deficiencies had been 
  corrected. Also, this inspection would be conducted on every configuration 
  that departed significantly from the basic design. Items successfully passing 
  the FACI were accepted, provided they met requirements in the Apollo 
  Configuration Management Manual. 
  
- Certification of Flight Worthiness (COFR) - to certify that each 
  vehicle stage or spacecraft module was a complete and qualified piece of 
  hardware. 
  
- Design Certification Review (DCR) - to certify that the entire 
  space vehicle was airworthy and safe for manned flight. DCRs would formally 
  review the development and qualification of all stages, modules, and 
  subsystems. 
  
- Flight Readiness Review (FRR) - a two-part review, scheduled for 
  each flight, to determine that both hardware and facilities were ready. 
  Following a satisfactory ERR, and when decided upon by the mission director, 
  the mission period would begin (which would commit deployment of support 
  forces around the world).
NASA OMSF, Apollo Program Directive No. 6, 
"Sequence and Flow of Hardware Development and Key Inspection, Review, and 
Certification Checkpoints," August 12, 1965.
August 12
Grumman received approval from Houston for an all-gaseous 
oxygen supply system in the LEM. While not suggesting any design changes, MSC 
desired that portable life support systems (PLSS) be recharged with the cabin 
pressurized. And because the oxygen pressure in the descent stage tanks might be 
insufficient for the final recharge, the PLSSs could be "topped off" with oxygen 
from one of the tanks in the vehicle's ascent stage if necessary.
Letter, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS 
9-1100, Gaseous Oxygen Supply Configuration," August 12, 1965.
August 12-13
MSC rejected North American's second design concept for a 
panel retention system in the LEM adapter. (The contractor's first proposal had 
drawn an unsatisfactory verdict early in June.) These successive rejections, 
largely on the basis of weight and vibration factors, illustrated the company's 
continuing difficulties with the system. MSC "suggested" to North American that 
it circumvent these problems by attaching the retention cable directly to the 
skin of the adapter.
"Critical Design Review for the Block II Spacecraft/LEM Adapter, 12-13 August 
1965."
August 18
At a third status meeting on LEM-1, Grumman put into effect 
"Operation Scrape," an effort to lighten that spacecraft by about 57 kg (125 
lbs). "Scrape" involved an exchange of parts between LEM-1 and LTA-3. The former 
vehicle thus would be heavier than the latter; LTA-3, on the other hand, would 
have the same structural weight as LEMs 2 and forthcoming.
MSC, "ASPO Weekly Management Report, August 12-19, 1965"; letter, R. Wayne 
Young, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS 9-1100, LEM I Status 
Meeting Number Three," August 30, 1965; "Monthly Progress Report No. 31," 
LPR10-47, pp. 28-29.
August 18
Owen E. Maynard, Chief of the Systems Engineering Division, 
asked that part of the LEM Mission Programmer, the Program Reader Assembly, be 
deleted. The assembly was no longer needed, Maynard said, to meet Apollo mission 
requirements.
Memorandum, Owen E. Maynard, MSC, to Subsystem Manager, LEM SCS, "LEM Mission 
Programmer," August 18, 1965.
August 18-24
The preliminary Design Engineering Inspection (DEI) for CSM 
011, Mission AS-202, was held. This was a major program milestone for the 
mission. The review board met on August 24 and the formal DEI was conducted 
August 30, 31, and September 1 (see entry for those dates).
Memorandum, Carl R. Huss, JSC, to JSC Historical Office, "Comments on Volume 
III of The Apollo Spacecraft: A Chronology," June 6, 1973.
August 19
The Apollo Resident Office at KSC was notified that it was 
ASPO Manager Joseph F. Shea's desire that a Configuration Control Panel be 
established and chaired at KSC to consider and process engineering changes to 
Apollo spacecraft and associated hardware undergoing checkout and test at KSC.
The ASPO Configuration Management Plan was being revised to reflect the 
action. The newly formed CCP's authority would be restricted to review of end 
item hardware (including ground support equipment configuration changes) to 
determine if the change was mandatory in the conduct of tests at KSC, and the 
approval of the contractor's plan for making the mandatory change to specific 
Apollo hardware end items at KSC.
Memorandum, William M. Bland, Jr., MSC, to Assistant Head of MSC Apollo 
Resident Office, KSC, "Apollo Spacecraft Configuration Control Panel at KSC," 
August 19, 1965.
August 19-26
MSC assigned two LEM test articles (numbers 10 and 2, 
respectively) to the SA-501 and SA-502 missions. Prior to flight, the spacecraft 
would be refurbished by Grumman, which would require four to five months' work 
on each vehicle.
MSC, "ASPO Weekly Management Report, August 19-26, 1965"; "Monthly Progress 
Report No. 31," LPR- 10-47, p. 38; memorandum, C. H. Perrine, MSC, to H. Davis, 
"Use of LTA-10 for Facilities Verification Vehicle," August 31, 1965.
August 20
Douglas Aircraft Company static-fired the S-IVB in a test at 
Sacramento, Calif., simulating the workload of a lunar mission. The stage was 
run for three minutes, shut down for half an hour, then reignited for almost six 
minutes.
Astronautics and Aeronautics, 1965, p. 386.
August 21
Gemini V, piloted by L. Gordon Cooper, Jr., and 
Charles Conrad, Jr., roared into space from Cape Kennedy. During their eight-day 
flight the astronauts performed a number of orbital and simulated rendezvous 
maneuvers to evaluate the spacecraft's rendezvous guidance and navigation 
equipment. A second principal objective of the mission was to evaluate the 
effects on the crew of prolonged exposure in space. Gemini V was 
significant as well for another reason: although the hardware experienced some 
troubles during the early part of the flight (which threatened to terminate the 
mission prematurely), Gemini V was the first spacecraft to use fuel 
cells as its primary source of electrical power. The operational feasibility of 
fuel cells would be essential for the success of long-distance (i.e., lunar) 
manned space flight.
Grimwood, et al., Project Gemini: A Chronology, pp. 
209-211.
August 23
MSC and Apollo spacecraft contractors were in process of 
planning and implementing an extensive ground- based test program to certify the 
spacecraft for flight. All possible efforts were being made to benefit from the 
experience of related spacecraft programs in planning the Apollo test program. 
In view of the similarities of the Surveyor mission and the LEM mission, Jet 
Propulsion Laboratory was asked to cooperate by providing: (1) background 
information concerning the manner in which their qualification test program had 
been performed, (2) the major complete vehicle and partial vehicles used in the 
ground test programs, and (3) significant results obtained from such programs.
Letter, Joseph F. Shea, MSC, to NASA Resident Office, JPL, "Surveyor ground 
test programs," August 23, 1965.
August 23
Joseph F. Shea, ASPO Manager, summarized ground rules on the 
schedules for qualifying and delivering equipment for Block II spacecraft:
  - All components installed on the Block II test vehicle (2TV-1) and on Block 
  II flight vehicles must be production hardware. (Prototype units were 
  unacceptable.) 
  
- Any changes from the configuration of CSM 103 in 2TV-1, 101, or 102 must 
  be essential to the specific mission requirements of those vehicles. 
  
- Delivery schedules must be compatible with North American's needs. (North 
  American was allowed some leeway in installing components, provided that such 
  reordering was feasible and did not affect overall checkout and delivery 
  schedules for the vehicle.) 
  
- Qualification testing must be scheduled so that all equipment was 
  qualified before February 15, 1967. 
  
- Launch-constraining ground tests must be scheduled for completion at least 
  six weeks before that launch.
Shea alone had authority to waive these 
schedule rules.Memorandum, Shea, MSC, to Distr., "Subsystem qualification and delivery 
schedules for Block II," August 23, 1965.
August 24
MSC requested that Grumman review the current LEM landing and 
docking dynamic environments to assure: (1) no loss of the abort guidance system 
attitude reference due to angular motion exceeding its design limit of 25 
degrees per second during indicated mission phases; and (2) a mission angular 
acceleration environment, exceeding the gyro structural tolerances, would not be 
realized.
TWX, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, August 24, 1965.
August 26-September 2
Grumman advised that prelaunch heat loads on LEM-1 
exceeded the capability of the spacecraft's prelaunch Freon boiler. That boiler 
had originally been designed for loads anticipated from fuel-celled LEMs. When 
batteries replaced fuel cells, MSC had recommended deleting the boiler; Grumman 
had urged that the item be retained on LEM-1, however, because that spacecraft 
would have optional equipment onboard at launch. "It appears," Crew Systems 
Division (CSD) reported, "that the number of items of equipment required to be 
on [LEM-1] at earth launch has snowballed": the boiler's maximum capability was 
about 900 Btus per hour; the spacecraft's heat load was estimated at something 
like 6,000. "GAEC is presently investigating what can be done to reduce these 
loads," CSD said.
"ASPO Weekly Management Report, August 26-September 2, 1965."
August 26-September 2
Qualification testing was completed on the LEM's 
helium storage tank.
Ibid.; memorandum, Joseph G. Thibodaux, Jr., "Quantity gaging for the 
Descent Propulsion Supercritical Helium Pressurization System," August 19, 1965, 
with enclosure.
August 27
Owen E. Maynard, Chief of the Systems Engineering Division 
(SED), drafted a set of guidelines for Apollo developmental missions. While 
these guidelines pertained mostly to Block II development, and were so labeled, 
to some extent they dealt with Block I flights as well. These Development 
Mission Guidelines covered the overall mission, as well as specific phases, with 
one section devoted solely to the LEM. (Maynard was careful to distinguish these 
guidelines from "ground rules" in that, rather than being mandatory 
requirements, their intent was "to afford test planning a guide and somewhat of 
an envelope . . . and not hard and fast rules.")
SED was considering including these guidelines in the Apollo Spacecraft 
Master Test Plan when that document was next revised.
Memorandum, Maynard, MSC, to Distr., "Block II Development Mission 
Guidelines," August 27, 1965.
August 27
North American reported that ground testing of the service 
propulsion engine had been concluded. Also, changing the propellant ratio of the 
service propulsion system had improved the engine's performance and gimbal 
angles and had reduced the weight of the Block II SM. (See July 23.)
Memorandum, Owen E. Maynard, MSC, to Asst. Manager, ASPO, "SPS engine 
gimballing in stack," August 25, 1965; TWX, M. L. Raines, WSTF, to MSC, Attn: R. 
R. Gilruth and others, August 30, 1965; NAA, "Apollo Monthly Progress Report," 
SID 62-300-41, October 1, 1965, pp. 8, 10.
August 29-September 4
Several important activities were noted during the 
reporting period: (1) Qualification of the new reefing line cutters was 
progressing satisfactorily and scheduled for completion in October 1965. (The 
cutter had been used successfully on the last two earth landing system tests 
conducted at El Centro); (2) the helium storage tank for the LEM reaction 
control subsystem successfully passed qualification tests; and (3) the Aero 
Spacelines' new aircraft, "Super Guppy," made its maiden flight from Van Nuys, 
Calif., to Mojave Airfield, Calif. The new aircraft had the capability of 
airlifting the spacecraft-LEM-adapter as well as providing vital backup for the 
"Pregnant Guppy" aircraft.
"Weekly Activity Report, August 29-September 4, 1965," Joseph F. Shea.
August 30
NASA's Associate Administrator for Manned Space Flight, George 
E. Mueller, informed MSC's Director Robert R. Gilruth that an official emblem 
had been adopted for the Apollo Program, a composite based on the best proposals 
submitted by NASA and contractor personnel.
Letter, Mueller to Gilruth, August 30, 1965.
August 30-September 1
Spacecraft 011's design engineering inspection was 
held at North American. The review combined structures, mission (SA-202), and 
ground support. The Review Board approved 55 changes (53 of which were assigned 
to North American).
"Apollo Monthly Progress Report," SID 62-300-41, p. 4; memorandum, C. H. 
Bolender, NASA, to E. E. Christensen and S. C. Phillips, "Trip Report on Visit 
to NAA Downey," September 7, 1965.
August 31-September 1
At an implementation meeting at MSC on the LEM's 
guidance and control system, Grumman again made a pitch for its concept for the 
landing point designator (i.e., scale markings on the vehicle's window). On 
September 13, the company received MSC's go-ahead. Grumman was told to 
coordinate closely with both MSC and MIT on the designator's design to ensure 
that the scale markings would be compatible with the spacecraft's computer.
TWX, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, subject: "Action 
Item L52, Requirements for Landing Point Designator (LPD)," September 13, 1965.
During the Month
An explosion damaged a LEM reaction control system 
thruster being fired in an up attitude in altitude tests at MSC.
"Monthly Progress Report No. 31," LPR-10-47, p. 1.
During the Month
Grumman completed an analysis of radiation levels that 
would be encountered by the LEM-3 crew during their earth orbital mission. 
Grumman advised that doses would not be harmful. To lessen these levels even 
further, the contractor recommended that during some parts of the mission the 
two astronauts climb back into the CM; also, the planned orbit for the LEM (556 
by 2,500 km [300 by 1,350 nm]) could be changed to avoid the worst part of the 
Van Allen Belt.
Ibid., p. 40. 
 
  
 