Part 1 (H)
Preparation for Flight, the Accident, and Investigation
March 16 through April 5, 1967
1967
March 16
The Apollo 204 Review Board accepted the final report of its
Administrative Procedures Panel (No. 15). The panel had been established
February 7 to establish and document such activities as control of spacecraft
work, logging and filing exhibits, logging Board activities, scheduling
meetings, preparing agendas, and arranging for secretarial services and
reproduction. During the investigation into the January 27 spacecraft fire, the
panel had:
- Issued 25 Board administrative procedures.
- Established the administrative and Secretarial Support Office, which had
provided support in two shifts seven days a week, unless otherwise required,
with some additional third-shift support.
- Established the Photographic Data Control Center to correlate and
distribute photographs and maintain a film library.
- Processed letters, telegrams, and telephone messages received offering
assistance, recommendations, and comments.
- Periodically issued approved schedules of work.
- Established the Audio Magnetic Tape Library to control 0.64centimeter
voice-transmission tape recordings about spacecraft 012 during the Space
Vehicle Plugs-Out Integrated Test.
"Board Proceedings" and Append. D.
"Panels 12 thru 17," Report of Apollo 204 Review Board, pp. 3-29
and D-15-3 through D-15-5.
March 18
The Apollo 204 Review Board accepted the final report of the
Fracture Areas Panel (No. 10). The panel had been charged with inspecting
spacecraft 012 for structural failures in the January 27 fire and analyzing them
from the standpoint of local pressure, temperature levels, direction of gas
flow, etc.
The panel inspected the spacecraft structures while they were still at Launch
Complex 34 and continued through removal of the CM heatshield. Structural damage
reports were made coinciding with spacecraft disassembly phases. As major
subsystems were removed from the spacecraft they were visually inspected.
Buckles, fractures, cracks, melted areas, localized arcing or pitting in metal
components, and obvious direct wire shorts were noted and documented.
Panel findings and determinations included:
- Finding
- Spacecraft data during the Plugs-Out Test gave indications from which a
spacecraft pressure history could be estimated.
- Determination
-
- The CM cabin structure had ruptured at 6:31:19.4 (±0.1) p.m. EST January
27 at an estimated minimum cabin pressure of 20 newtons per sq cm (29 psia).
- The CM cabin structure had sustained cabin pressure in excess of its
designed ultimate pressure of 8.9 newtons-per-sq-cm (12.9-psi) differential
(19 newtons per sq cm; 27.6 psia). Cabin pressure at rupture probably
reached 20 to 26 newtons per sq cm (29 to 37.7 psia).
- The estimated average gas temperature at rupture exceeded 644 kelvins
(700 degrees F).
- Finding
- The CM cabin ruptured in the aft bulkhead adjacent to its juncture with
the aft sidewall.
- Determination
- The failure occurred because of excessive meridional tensile stress in the
inner face sheet at the junction of the weld land to the thinner face sheet.
The fracture originated on the right-hand side of the command module.
- Finding
- The CM cabin structure was penetrated in the aft bulkhead beneath the
environmental control unit and the aft sidewall.
- Determination
-
- The loss of structural integrity at these penetrations occurred after
the primary rupture.
- Failure of the water glycol and oxygen lines near the environmental
control unit resulted in local burning and melting of the adjacent
structure.
- Finding
- The aft heatshield stainless-steel face sheets were melted and eroded.
- Determination
- The temperature of the flame and gas exiting from the fracture origin
exceeded 1640 K (2500 degrees F).
"Board Proceedings" and Append. D,
"Panels 6 thru 10," Report of Apollo Review Board, pp. 3-30 and
D-10-3 through D-10-7.
March 18-19
The final report of the Spacecraft and Ground Support
Equipment Configuration Panel (No. 1) was accepted by the Apollo 204 Review
Board. The panel had been assigned the task of documenting the physical
configuration of the spacecraft and ground support equipment immediately before
and during the January 27 fire, including equipment, switch position, and
nonflight items in the cockpit. The panel was also to document differences from
the expected launch configuration and configurations used in previous testing
(such as altitude-chamber testing).
During the investigation the panel had discovered a number of items which
might have had relevance to flame propagation:
- An engineering order, released at North American Aviation's Downey
facility on January 20, provided direction to inspect the polyurethane foam in
specified areas and coat the silicone rubber to meet flammability
requirements. The direction was not recorded in the configuration verification
record as of the start of the Space Vehicle Plugs-Out Integrated Test and was
not accomplished on spacecraft 012. This item was considered as possibly
significant in terms of fuel for the fire and a medium for flame propagation.
- Polyethylene bags covered the hose fitting for the drinking water
dispenser and the battery-instrumentation cable and connectors and transducer,
which were placed on the aft bulkhead near the batteries. The bags were made
of nonflight materials.
- Two polyurethane pads, covered with Velostat, were stowed over couch
struts. The pads were placed in the spacecraft to protect the struts, wiring,
and aft bulkhead during the planned emergency egress at the end of the test.
These items were of nonflight material and were not documented by quality
inspection records.
- Three packages of switching checklists from the Operational Checkout
Procedure and one package of system malfunction procedures, in a manila
folder, were stowed on the crew couches and on a shelf. These items were on
unqualified paper and, while required for the test, they were not documented
by quality inspection records.
- Nylon protective sleeves were covering all three crewmen's oxygen
umbilicals. These sleeves were nonflight items.
- Three ground-support-equipment window covers had been temporarily
installed to protect the windows and were nonflight items in the spacecraft at
the time of the accident. Another such cover for the side hatch window was
removed by the crew and stowed inside the command module. These covers were of
nylon fabric; flight covers were made of aluminized Mylar.
- Velcro pile had been installed to protect the Velcro hood on the command
module floor. It would have been removed before the flight.
- "Remove before flight" streamers installed in the command module interior
were additional nonflight items.
- Polyethylene zipper tubing, installed to protect hand controller cables,
was a nonflight item and was additional material in the command
module.
The panel's summary of findings and determinations included:
- Finding
- Eighty engineering orders effective for spacecraft 012 had not been
carried out at the time of the accident. Of these, twenty were specified to be
completed after the test; four did not affect configuration.
- Determination
- Test requirements had no defined relationships with the open status of 56
engineering orders. The reason not all work items and engineering orders were
closed was late receipt of changes or further work scheduled to be completed
before launch.
- Finding
- Items not documented by quality inspection records had been placed on
board the spacecraft during preparation for the Space Vehicle Plugs- Out
Integrated Test.
- Determination
- Procedures for controlling entry of items into the spacecraft were not
strictly enforced.
"Board Proceedings" and Append. D, "Panels I thru
4," Report of Apollo 204 Review Board, pp. 3-30 and D-1-5 through
D-1-19.
March 18-19
The Apollo 204 Review Board accepted the final report of the
Security Operations Panel (No. 14). The panel had been assigned to review
existing security practices at KSC and supporting areas for adequacy and
recommend any needed changes. Practices included access control, personnel
sign-in requirements, buddy systems, and background investigation requirements.
The panel's report submitted six findings and determinations, which included:
- Finding
- KSC security personnel or uniformed security personnel had been assigned
to all locations requiring safeguarding measures, including launch vehicle
stages and spacecraft from the time of arrival at KSC until the time of the
January 27 accident.
- Determination
- The number of KSC and uniformed security personnel members used was
adequate.
- Finding
- The Apollo Preflight Operations Procedures - dated October 17, 1966, and
January 24, 1967 - for access control of test and work areas, required
that<
- access controls to spacecraft work areas be exercised by the contractor;
- the contractor maintain a log of all personnel permitted access during
off-shift and nonwork periods; and
- the contractor control and log command module ingress and
egress.
- Determination
- The procedures established in the Apollo Preflight Operations Procedures
were not followed for spacecraft 012 in that
- the contractor failed to exercise adequate access controls on the fifth,
sixth, and seventh spacecraft levels;
- the contractor failed to maintain an off-shift log; and
- the command module ingress-egress log was inadequately maintained.
"Board Proceedings" and Append. D,"Panels 12 thru 17,"
Report of Apollo 204 Review Board, pp. 3-30 and D-14-3 through
D-14-7.
March 18-20
The Apollo 204 Review Board accepted the final report of its
Origin and Propagation of Fire Panel (No. 5). The panel task had been to
"conduct inspections, chemical analyses [and] spectrographic analysis of
spacecraft, parts or rubble, or use any other useful techniques to establish
point of [the CM 012] fire origin, direction and rate of propagation,
temperature gradients and extremes. The nature of the fire, the type of
materials consumed, the degree of combustion shall be determined."
Following an intensive study - which considered ignition sources,
description, and course of the fire - the panel listed 10 findings and
determinations in its final report, including:
- Finding
- Severe damage to wiring was found at the bottom of the power equipment bay
along the aft bulkhead. Evidence of arcing was found and damage was less
severe in the right-hand direction of this bay.
- Determination
- Electrical arcing in the extreme lower left-hand comer of this bay could
have provided a primary ignition source.
- Finding
- Right-hand portions of the left-hand equipment bay were severely damaged.
Wiring, tubing, and components in the carbon dioxide absorber compartment and
oxygen/water panel compartment were burned and melted. Penetrations in the aft
bulkhead and pressure vessel wall were observed. The carbon dioxide absorber
compartment showed heavy fire damage; failure was due to pressure overload and
melting caused by the fire in this area.
- Determination
- Electrical arcing in the right-hand portion of this bay could have
provided a primary ignition source.
- Finding
- Evidence of electrical arcs from conductor to conductor and from conductor
to structure were found.
- Determination
- No arc could be positively identified as the unique ignition source. Three
were found that had all the elements needed to cause the disaster. Two of
these showed evidence of poor engineering and installation.
"Board
Proceedings" and Append. D, "Panel 5," Report of Apollo 204 Review
Board, pp. 3-30 and D-5-3 through D-5-15.
March 19
The final report of the Ground Emergency Provisions Panel
(Panel 13) accepted by the Apollo 204 Review Board submitted 14 findings and
determinations. The panel had been charged with reviewing the adequacy of
planned ground procedures for the January 27 spacecraft 012 manned test, as well
as determining whether emergency procedures existed for all appropriate
activities. The review was to concentrate on activity at the launch site and to
include recommendations for changes or new emergency procedures if deemed
necessary.
The panel approached its task in two phases. First, it reviewed the emergency
provisions at the time of the CM 012 accident, investigating
- the procedures in published documents,
- the emergency equipment inside and outside the spacecraft, and
- the emergency training of the flight crew and checkout test
team.
Second, the panel reviewed the methods used to identify hazards
and ensure adequate documentation of safety procedures and applicable emergency
instructions in the operational test procedures.
Findings and determinations included:
- Finding
- The applicable test documents and flight crew procedures for the AS- 204
Space Vehicle Plugs-Out Integrated Test did not include safety considerations,
emergency procedures, or emergency equipment requirements relative to the
possibility of an internal spacecraft fire during the operation.
- Determination
- The absence of any significant emergency preplanning indicated that the
test configuration (pressurized 100-percent-oxygen cabin atmosphere) was not
classified as potentially hazardous.
- Finding
- The propagation rate of the fire in the accident was extremely rapid.
Removal of the three spacecraft hatches, from either the inside or the
outside, for emergency exit required a minimum of 40 to 70 seconds,
respectively, under ideal conditions.
- Determination
- Considering the rapid propagation of the fire and the time constraints
imposed by the spacecraft hatch configuration, it is doubtful that any amount
of emergency preparation would have precluded injury to the crew before
egress.
- Finding
- Procedures for unaided egress from the spacecraft were documented and
available. The AS-204 flight crew had participated in a total of eight egress
exercises employing those procedures.
- Determination
- The 204 flight crew was familiar with and well trained in the documented
emergency crew procedures for effecting unaided egress.
- Finding
- The spacecraft pad work team on duty at the time of the accident had not
been given emergency training drills for combating fires in or around the
spacecraft or for emergency crew egress. They were trained and equipped only
for a normal hatch removal operation.
- Determination
- The spacecraft pad work team was not properly trained or equipped to
effect an efficient rescue operation under the conditions resulting from the
fire.
- Finding
- Frequent interruptions and failures had been experienced in the overall
communications system during the operations preceding the accident. At the
time the accident occurred, the status of the system was still under
assessment.
- Determination
- The status of the overall communications was marginal for the support of a
normal operation. It could not be assessed as adequate in the presence of an
emergency condition.
- Finding
- Emergency equipment provided at the spacecraft work levels consisted of
portable carbon dioxide fire extinguishers, rocket-propellant-fuel-handler's
gas masks, and 4.4-centimeter-diameter fire hoses.
- Determination
- The existing emergency equipment was not adequate to cope with the
conditions of the fire. Suitable breathing apparatus, additional portable
carbon dioxide fire extinguishers, direct personnel evacuation routes, and
smoke removal ventilation were significant items that would have improved the
reaction capability of the personnel.
- Finding
- Under the existing method of test procedure processing at KSC, the safety
offices reviewed only the procedures noted in the operational checkout
procedure outline as involving hazards. Official approval by KSC and Air Force
Eastern Test Range Safety was given after the procedure was published and
released.
- Determination
- The scope of contractor and KSC Safety Office participation in test
procedure development was loosely defined and poorly documented.
Post-procedure-release approval by the KSC Safety Office did not ensure
positive and timely coordination of all safety considerations.
"Board
Proceedings"; Append. A, "Board Minutes"; and Append. D, "Panels 12 thru 17," in
Report of Apollo 204 Review Board, pp. 3-28 through 3-30, A-1 12,
and D-13-3 through D-13-13.
March 19
The Materials Work Panel (Panel 8, also referred to as
Materials Review' Panel) in its final report accepted by the Apollo 204 Review
Board cited a number of findings on flammable materials in spacecraft 012. The
panel's task had included the following, from its detailed work statement:
- "Assemble, summarize, compare and interpret requirements and data
describing the flammability of nonmetallic materials exposed to the crew bay
environment of the spacecraft and in related applications.
- "Specify and authorize performance of tests and/or analyses to furnish
additional information as to flammability characteristics of these materials
alone, and in combination with fluids known or postulated to have been in the
spacecraft 012 cabin.
- "Panel No. 8, in support of Panel No. 5 (Origin and Propagation of Fire)
shall interpret and implement the requirements for analyses of debris removed
from the spacecraft."
Panel 8 classified its findings in six
categories: Materials Configuration; Routine Materials Test; Fire Initiation
Special Investigation; Fire Propagation Special Investigation; Materials
Installation Criteria and Controls; and Technical Data and Information
Availability. The findings and determinations included:
- Finding
- Complete documentation identifying potentially combustible nonmetallic
materials in spacecraft 012 was not available in a single readily usable
format. A total of 2,528 different potentially combustible nonmetallic
materials that were probably used on spacecraft 012 was found by a review of
available documentation.
- Determination
- The program for identifying and documenting nonmetallic materials used in
the spacecraft, including their weights and surface areas, was not adequate.
- Finding
- Raschel Knit, Velcro, Trilock, and polyurethane foams burn about twice as
fast (in the downward direction) in oxygen at a pressure of 11.4 newtons per
sq cm (16.5 psia) as at 3.5 newtons per sq cm (5 psia).
- Determination
- The primary fuels for the fire burned more than twice as fast in the early
stages of the spacecraft 012 fire in accident conditions (pressure of 11.4
newtons per sq cm) as in the space flight atmosphere for which they were
evaluated (3.5 newtons per sq cm).
- Finding
- Surface and bulk damage of materials in spacecraft 012 varied from melting
and blistering of aluminum alloys, combustion of Velcro, and burning of Teflon
wire insulation to slight surface damage and melting of nylon fabrics.
- Determination
- The fire filled the spacecraft interior. The most intense heat was in the
lower left front area around the environmental control unit. Surface
temperatures in excess of 800 kelvins (1,000 degrees F) were reached in areas
such as the front and left side of the spacecraft. Surface temperatures were
less than 500 K (400 degrees F) in isolated pockets above the right-hand
couch.
- Finding
- The rate of flame propagation, the rate of pressure increase, the maximum
pressures achieved, and the extent of conflagration in 3.5 newtons-per-sq-cm
(5-psia) oxygen boilerplate tests was much less severe than observed in the
11.4-newton (16.5-psia) oxygen boilerplate tests. Burning or charring was
limited to approximately 29 percent of the nonmetallic materials by oxygen
depletion.
- Determination
- The conflagration that occurred in spacecraft 012 at a pressure of 11.4
newtons per sq cm would be far less severe and slower in a spacecraft
operating with an oxygen environment at 3.5 newtons, if additional large
quantities of oxygen are not fed into the fire.
- Finding
- North American Aviation materials selection specification requires that a
material pass only a 500 K (400 degrees F) spark-ignition test in oxygen at
10.1 newtons per sq cm (14.7 psia).
- Determination
- NAA criteria for materials flammability control were inadequate.
- Finding
- No flammability criteria or control existed covering nonflight items
installed in CM 012 for test.
- Determination
- Lack of control of nonflight material could have contributed to the fire.
- Finding
- The NASA materials selection criteria required that a material pass a 500
K (400 degrees F) spark-ignition test and a 1.27-an-per-sec combustion rate
(measured downward in oxygen at 3.5 newtons per sq cm). Raschel Knit and
Velcro (hook) pass this test.
- Determination
- The NASA criteria for materials flammability were not sufficiently
stringent.
- Finding
- The system for control of nonmetallic materials use at MSC during the
design and development of government furnished equipment used in CM 012
depended on identification of noncompliance with criteria by the development
engineers.
- Determination
- The NASA materials control system was permissive to the extent that
installation or use of flammable materials were not adequately reviewed by a
second party.
- Finding
- Nonmetallic materials selection criteria used by North American and NASA
were not consistent. The NASA criteria, although more stringent, were not
contractually imposed on the spacecraft contractor.
- Determination
- Materials were evaluated and selected for use in CM 012 using different
criteria. Application of the NASA criteria to the command module would have
reduced the amount of the more flammable materials (Velcro and Uralane foam).
- Finding
- Alternate materials that are nonflammable or significantly less flammable
than those used on spacecraft 012 were available for many applications.
- Determination
- The amount of combustible material used in command modules can be limited.
- Finding
- Current information and displays of the potentially flammable materials
configuration of spacecraft 012 were not available before the fire.
- Determination
- Maintenance of data and displays at central locations and test sites for
management visibility and control of flammable materials is feasible and
useful.
"Board Proceedings"; Append. A, "Board Minutes"; and Append. D,
"Panels 6 thru 10," in Report of Apollo 204 Review Board, pp. 3-30,
A-112, and D-8-3 through D-8-35.
March 20
NASA announced it would use the Apollo-Saturn 204 launch
vehicle to launch the first lunar module on its unmanned test flight. Since the
204 vehicle was prepared and was not damaged in the Apollo 204 fire in January,
it would be used instead of the originally planned AS-206.
NASA News Release 67-67, March 20, 1967.
March 20
The Deputy Administrator of NASA designated Langley Research
Center custodian of all materials dealing with the investigation and review of
the January 27 Apollo 204 accident. Review Board Chairman Floyd Thompson, LaRC,
who had the responsibility of determining the materials to be included in the
final repository, determined that the following categories of materials were to
be preserved:
- Reports, files, and working materials;
- Medical reports;
- Spacecraft 012 command module, its systems, components, and related
drawings.
Category 1 materials would be stored at LaRC, Category 2 at
MSC, and Category 3 at KSC.
In other actions Robert W. Van Dolah, Chairman of the Origin and Propagation
of Fire Panel, reported on a test being conducted in CM 014 to attempt to
establish the amount of static electricity that might be generated by a suited
crewman; and members of the Board met with MSC Director Robert R. Gilruth and
members of his staff, as well as management and engineering personnel of North
American Aviation, for a presentation concerning solder joints in the CM.
"Board Proceedings," pp. 3-30, 3-31.
March 21
Final report of the Disassembly Activities Panel (No. 4) was
accepted by the Apollo 204 Review Board. Panel 4 had been assigned to develop
procedures for disassembly of spacecraft 012 for inspection and failure
analysis. Disassembly was to proceed step by step in a manner permitting maximum
information to be obtained without disturbing the evidence - in both the cockpit
and the area outside the pressure hull. Cataloging documentary information
within the spacecraft and displaying the removed items were a part of the
required procedures.
Procedures followed included the following actions:
- Immediately after the January 27 accident, NASA KSC Security placed Launch
Complex 34 under additional security. Special guards were assigned to the
service structure and to the adjustable level at the entrance of the CM.
Controls were established for personnel access to the service structure and
the CM.
- After the accident, before disturbing any items in the spacecraft, a
series of photographs was taken. A step-by-step photography method was
established as a standard operating procedure for the Disassembly Activities
Panel.
- The first step toward an orderly disassembly was to ensure safe working
conditions at the spacecraft. A meeting with KSC and Air Force Eastern Test
Range Safety personnel established procedures and safety rules.
- After the couches were removed, a special false floor was suspended from
the couch strut fittings to provide access to the entire inside of the
spacecraft without disturbing any evidence. The false floor was fabricated
from aluminum angles supporting 2-centimeter-thick, 46-centimeter plexiglass
squares.
- The Review Board appointed a Panel Coordination Committee to carry out new
procedures to ensure closely controlled and coordinated equipment
removal.
The Disassembly Activities Panel cataloged and displayed the
1,261 items removed from spacecraft 012 during the investigation. The
Pyrotechnics Installation Building (PIB) at KSC was assigned as an area in which
components removed from the command module could be placed in bonded storage yet
still be available for inspection by investigative personnel. The following
areas were established in the PIB:
- Bond room - a bonded area to receive components as they were
removed from CM 012. This area was provided with a receiving table; 10 storage
cabinets for small components; and areas for large components and items
associated with the investigation but not from the command module itself.
- Astronaut equipment room and work room - an area in which the
spacesuits and other government furnished crew equipment were investigated.
- Bonded display area - an area in which components could be
displayed under controlled conditions to permit investigators to examine CM
012 components visually.
- Command module 012 work area - The command module was placed in a
supporting ring within an existing workstand in the PIB and remained in this
area until the aft heatshield was removed. The CM was then transferred to a
standard support ring in the north end of the building. Technicians continued
the disassembly activities while the CM was in these areas.
- Spacecraft 014 CM - Spacecraft 014 CM (identical in configuration
to spacecraft 012) was shipped to KSC on February 1 to assist the Apollo 204
Review Board in the investigation. This CM was placed in the PIB and was used
for practicing difficult removals of CM 012 components.
- Mockup No. 2 - Mockup No. 2, a full-scale plywood command module,
was brought to KSC and placed in the PIB February 8. The mockup had been
configured with Velcro, debris traps, couch positioning, etc., to duplicate CM
012 configuration at the time of the fire.
- Half-scale mockup - A half-scale mockup of the CM interior was
placed in the bonded display area February 8 to display half-scale interior
surface photographs taken after the fire in CM 012.
"Board
Proceedings," and Append. D, "Panels 1 thru 4," Report of Apollo 204
Review Board, pp. 3-31 and D-4-3 through D-4-8.
March 25
The Apollo 204 Review Board accepted the final report of its
Test Environment Panel (Panel 2). Panel 2 had been assigned responsibility for
the history of all test environments encountered by spacecraft 012 that were
considered germane to system validation from a fire hazard standpoint, including
qualification testing of systems and subsystems. The panel was particularly to
emphasize qualification tests in pure oxygen with regard to pressures,
temperature, time of exposure, and simulation of equipment malfunctions. It was
also to indicate any deficiencies in the test program related to the problem;
comparison with previous tests of appropriate flight, house, or boilerplate
spacecraft; and documentation of any problems encountered which related to fire
hazard.
The panel reviewed all tests pertinent to the investigation. The
qualification tests were reviewed at MSC, covering more than 1,000 documents.
Vehicle tests were reviewed at North American Aviation's Downey, Calif.,
facility, covering more than 500 documents. Summaries of these efforts were
reviewed by the panel at KSC to determine any test program deficiencies.
The final report of the panel included six findings and determinations. Among
them were:
- Finding
- Not all crew compartment equipment had been tested as explosion proof.
- Determination
- Testing of possible ignition sources had been insufficient.
- Finding
- Some CM equipment exhibited arcing or shorting either during certification
or during spacecraft 012 testing. There was no positive way to determine from
the records reviewed whether spacecraft anomalies (possibly caused by an arc
or a short) were reviewed by system engineers and the test conductor before a
test.
- Determination
- Review of possible ignition sources before manned testing was inadequate.
- Finding
- Not all equipment installed in CM 012 at the time of the accident was
intended for flight (some components were installed for test purposes only).
- Determination
- The suitability of this equipment in the CM for this test was not
established.
"Board Proceedings" and Append. D, "Panels 1 thru 4,"
Report of the Apollo 204 Review Board, pp. 3-32 and D-2-3 through
D-2-8.
March 25 - April 24
NASA Hq. Office of Manned Space Flight informed KSC,
MSFC, and MSC of approved designations for Apollo and Apollo Applications
missions:
- all Apollo missions would be numbered sequentially in the order flown,
with the next mission to be designated Apollo 4, the following one Apollo 5,
etc., and
- the Apollo Applications missions would be designated sequentially as
AAP-1, AAP-2, etc. The number designations would not differentiate between
manned and unmanned or uprated Saturn I and Saturn V missions.
In a letter to George E. Mueller, OMSF, on March 30, MSC Deputy Director
George M. Low offered two suggestions, in keeping with the intent of the NASA
instruction yet keeping the designation Apollo 1 for spacecraft 012. NASA Hq.
had approved that designation before the January 27 fire claimed the lives of
Astronauts Virgil I. Grissom, Edward H. White II, and Roger B. Chaffee; and
their widows requested that the designation be retained. The suggestions were:
- Consider the AS-201, 202, and 203 missions part of the Saturn I (as
opposed to uprated Saturn I) series; reserve the designation Apollo 1 for
spacecraft 012; and number the following flights Apollo 2, etc., or
- Designate the next flight Apollo 4, as indicated by Headquarters, but
apply the scheme somewhat differently for missions already flown.
Specifically, put the Apollo 1 designation on spacecraft 012 and then, for
historic purposes, designate 201 as mission 1-a, 202 as mission 2 and 203 as
mission 3.
A memorandum to the NASA space flight Centers, North
American Aviation, and certain Headquarters personnel from the NASA Assistant
Administrator for Public Affairs on April 3 stated that the Project Designation
Committee had approved the Office of Manned Space Flight's recommendations and
that Mueller had begun implementation of the designations.
On April 24, OMSF further instructed the Centers that AS-204 would be
officially recorded as Apollo 1, "first manned Apollo Saturn flight - failed on
ground test." AS-201, AS-202, and AS-203 would not be renumbered in the "Apollo"
series, and the next mission would be Apollo 4.
TWX, Mueller, NASA OMSF, to KSC, MSFC, MSC, "Apollo and AAP Mission
Designation," March 25 and April 24, 1967; ltr., Low to Mueller, March 30, 1967;
memo, Julian Scheer, NASA Assistant Administrator for Public Affairs, to distr.,
April 3, 1967.
March 27
A meeting at MSC considered fire detection systems and fire
extinguishers. Participants were G. M. Low, K. S. Kleinknecht, A. C. Bond, J. N.
Kotanchik, J. W. Craig, M. W. Lippitt, and G. W. S. Abbey. Craig and Lippitt had
visited Wright Field, Ohio, and from their findings the following conclusions
were reached:
- no fire detection system was available for incorporation into the Apollo
spacecraft;
- a reliable system would be desirable, but the system must not give false
alarms when used in a closed spacecraft environment and yet must give adequate
warning of fire;
- two kinds of systems appeared to be in varying states of development -
systems using infrared or ultraviolet sensors and systems sensing ionized
particles or condensation nucleii in the atmosphere;
- a work statement should be prepared, with the help of personnel at Wright
Field, for the purpose of receiving specific proposals on available systems;
and
- the ultimate goal should be to develop a system ready for flight use
within six months.
Memo for the Record, George M. Low, "Fire
detection/extinguishment," March 27, 1967.
March 28
Apollo 204 Review Board Chairman Floyd Thompson asked for a
report on the Pyrotechnic Installation Building activity. Disassembly of
spacecraft 012 had been completed March 27. Of 1,261 items logged through the
bond room for display to Board and panel personnel, about 1,000 items were from
the CM.
The final report of the Screening Committee was distributed to the Board by
George T. Sasseen, KSC, for review. Sasseen stated that the following items
would be retained as Category A (items damaged or identified as suspect or
associated with anomalies).
- Lower equipment bay junction box cover plate
- Command pilot's torso harness
- Velcro and Raschel netting
- Static inverter 2
- Main display control panel 8
- Instrumentation data distribution panel J800/J850
- Octopus cable.
Maxime A. Faget, MSC, advised the Board that the
lithium hydroxide cartridge had been sent to MSC for analysis. Hubert D.
Calahan, OMSF, was appointed courier to handcarry the item to MSC and Richard S.
Johnston, MSC, was designated the Board's witness for the analysis. MSC's Crew
Systems Laboratory was to make the analysis and report to the Board. The
analysis was to identify contaminants to determine the quantity of carbon
dioxide in the lithium hydroxide.
William D. Mangan, Langley Research Center, joined the legal staff supporting
the Board.
"Board Proceedings," pp. 3-32, 3-33.
March 29
At the request of the Manager of the MSC Lunar Surface Programs
Office, NASA Associate Administrator for Space Science and Applications Homer E.
Newell considered alternate Array B configurations of the Apollo Lunar Surface
Experiments Package to alleviate a weight problem. Instead of a single array, he
selected two configurations for ALSEP III and ALSEP IV:
- ALSEP III Experiments:
- Passive Seismic, Heat Flow (w/Lunar Drill), Cold Cathode Gauge, and
Charged Particle Lunar Environment.
- ALSEP IV Experiments:
- Passive Seismic, Active Seismic, Suprathermal Ion Detector/Cold Cathode
Gauge, and Charged Particle Lunar Environment.
Newell requested that
both configurations be built but that, if program constraints permitted the
fabrication of only one array for ALSEP II and IV, ALSEP III should be given the
preference. The Apollo Program Director concurred in the Newell recommendation.
Ltr., Apollo Program Director, NASA Hq., to R. O. Piland, MSC, March 29,
1967.
March 29-30
The Apollo Site Selection Board meeting at NASA Hq. March 29
heard MSC presentations on lunar landing site selection constraints, results of
the Orbiter II screening, and reviews of the tasks for site
analysis. MSC made recommendations for specific sites on which to concentrate
during the next four months and recommended that the landing sites for the first
lunar landing mission be selected by August 1. The Board accepted the
recommendations. A Surveyor and Orbiter meeting the following day considered the
targeting of the Surveyor C mission and the Lunar Orbiter V mission. MSC
representatives at the two meetings were John Eggleston and Owen E. Maynard.
Memo, Chief, Mission Operations Div., MSC, to Manager, ASPO, "Trip Report -
Apollo Site Selection Board and Surveyor/Orbiter Utilization Committee
Meetings," April 20, 1967.
March 29 - April 4
H. C. Creighton, A. R. Goldenberg, and Guy N.
Witherington, all of KSC, inspected spacecraft 101 wire bundles March 29 at the
request of CSM Manager Kenneth S. Kleinknecht of MSC. Kleinknecht had asked that
they give him a recommendation as to whether the bundles should be removed or
whether they could be repaired in place. On April 4, they reported to
Kleinknecht that time had not been sufficient to determine the complete status
of the wiring. A superficial inspection about five-percent complete had
indicated some serious discrepancies, for which they made some recommendations,
but they recommended a more detailed inspection of the spacecraft 101 wire
bundles.
Memo, Creighton, Goldenberg, and Witherington to Kleinknecht, "Condition of
Spacecraft 101 Wire Bundles," April 4, 1967.
March 30
The Apollo 204 Review Board accepted the report of its Sequence
of Events Panel (No. 3), which had been charged with analyzing data from
immediately before and during the January 27 fire, including digital, analog,
voice communications, and photography. The data was required to display
significant events as they occurred with the precise time tag. Time histories of
all continuous or semicontinuous recorded parameters and correlation of
parameter variations and events were to be recorded, as well as interpretation
of the analysis results. Where pertinent, normal expected variations were to be
compared with those actually obtained.
Panel 3 had served as a separate panel from January 31 through February 23,
when it was merged with the Integration Analysis Panel (No. 18). Panel 3
reported one finding and one determination:
- Finding
- The data recorded from the spacecraft and ground instrumentation system
during the Spacecraft Plugs-Out Test were found to be valid except for three
brief dropouts after 6:31:17 EST, January 27 (13 seconds after the pilot
reported "fire in the cockpit"). All onboard data transmission ended about
6:31:22 EST.
- Determination
- The onboard instrumentation system functioned normally before and during
the initial phase of the fire. There were no indicated malfunctions in any of
the instrumentation sensors during this period.
"Board Proceedings" and
Append. D, "Panels 1 thru 4," Report of Apollo 204 Review Board,
pp. 3-33 and D-3-3 through D-3-6.
March 30
The Apollo 204 Review Board met with its Test Procedures Review
Panel (Panel No. 7) to complete acceptance of the panel's final report. The
panel had been established February 7 to document test procedures actually
employed during the day of the January 27 accident and to indicate deviations
between planned procedures and those used. The panel was to determine changes
that might alleviate fire hazard conditions or that might provide for improved
reaction or corrective conditions and review the changes for applicability to
other tests.
Among the panel's findings and determinations were:
- Finding
- 209 pages of the 275-page Operational Checkout Procedure (OCP) were
revised and released on the day before the test. However, less than 25 percent
of the line items were changed. Approximately one percent of the change was
due to errors in technical content in the original issue of the procedure. In
addition, 106 deviations were written during the test.
- Determination
- Neither the revision nor the deviations were known to have contributed
specifically to the incident. The late timing of the change release, however,
prevented test personnel from becoming adequately familiar with the test
procedure before use.
- Finding
- During the altitude chamber tests, the cabin was pressurized at pressures
greater than sea level with an oxygen environment two and a half times as long
as the cabin was pressurized with oxygen before the accident during Plugs-Out
Test.
- Determination
- The spacecraft had successfully operated with the same cabin conditions in
the chamber for a greater period of time than on the pad up to the time of the
accident.
- Finding
- Troubleshooting the communication problem was not controlled by any one
person, and was at times independently run from the spacecraft, Launch Complex
34 Blockhouse, and the Manned Spacecraft Operations Building. Communications
switching, some of which was not called out in OCP, was performed without the
control of the Test Conductor.
- Determination
- The uncontrolled troubleshooting and switching contributed to the
difficulty experienced in attempting to assess the communication problem.
- Finding
- KSC was not able to ensure that the spacecraft launch operations plans and
procedures adequately satisfied, in a timely way, the intent of MSC. Changes
in spacecraft testing by KSC could not be kept in phase with the latest
requirements of MSC. Prelaunch checkout requirements were not formally
transmitted to KSC from MSC.
- Determination
- Prelaunch-test-requirements control for the Apollo spacecraft program was
constrained by slow response to changes, lack of detailed KSC-MSC inter-Center
agreements, and lack of official NASA-approved test specifications applicable
to prelaunch checkout.
- Finding
- The decision to perform the Plugs-Out Test with the flight crew, closed
hatch, and pure oxygen cabin environment made on October 31, 1966, was a
significant change in test philosophy.
- Determination
- There was no evidence that this change in test philosophy was made so late
as to preclude timely incorporation into the test procedure.
"Board
Proceedings" and Append. D, "Panels 6 thru 10," Report of Apollo 204
Review Board, pp. 3-33 and D-7-3 through D-7-13.
March 30
The Apollo 204 Review Board was scheduled to review the final
report of its Historical Data Panel (Panel No. 6). The panel had been assigned
to assemble, summarize, and interpret historical data concerning the spacecraft
and associated systems pertinent to the January 27 fire. The data were to
include such records as the spacecraft log, failure reports, and other quality
engineering and inspection documents. In addition the panel prepared narratives
to reflect the relationship and flow of significant review and acceptance points
and substantiating documentation and presented a brief history of prelaunch
operations performed on spacecraft 012 at Kennedy Space Center.
In its final report to the Review Board the Historical Data Panel submitted
eight findings and determinations. Among them were:
- Finding
- The Ingress-Egress Log disclosed several instances where tools and
equipment were carried into the spacecraft, but the log did not indicate these
items had been removed.
- Determination
- Maintenance of the Ingress-Egress Log was inadequate.
- Finding
- Inspection personnel did not perform a prescheduled inspection with a
checklist before hatch closing.
- Determination
- Inspection personnel could not verify specific functions during that
period.
- Finding
- At the time of the spacecraft 012 shipment to KSC, the contractor
submitted an incomplete list of open items. A revision of that list
significantly and substantially enlarged the list of open items.
- Determination
- The true status of the spacecraft was not identified by the
contractor.
"Board Proceedings" and Append. D, "Panels 6 thru 10,"
Report of Apollo 204 Review Board, pp. 3-33 and D-6-3 through
D-6-7.
March 30
The Apollo 204 Review Board accepted the final report of its
Design Review Panel (No.9), whose duty had been to conduct Critical Design
Reviews of systems or subsystems that might be potential ignition sources within
the Apollo command module cockpit or that might provide a combustible condition
in either normal or failed conditions. The panel was also to consider areas such
as the glycol plumbing configuration; electrical wiring and its protection,
physical and electrical; and such potential ignition sources as motors, relays,
and corona discharge. Other areas would include egress augmentation and the
basic cabin atmosphere concept (one-gas versus two-gas).
The contemplated spacecraft configuration for the next scheduled manned
flight (spacecraft 101, Block II) was significantly different from that of
spacecraft 012 (Block I), in which the January 27 fire had occurred. Therefore,
both configurations were to be reviewed - the Block I configuration as an aid in
determining possible sources for the fire, the Block II to evaluate the system
design characteristics and potential design change requirements to prevent
recurrence of fire.
The panel's final report to the Review Board contained findings on ignition
and flammability, cabin atmosphere, review of egress process, and review of the
flight and ground voice communications. Among them were:
- Finding
- Flammable, nonmetallic materials were used throughout the spacecraft. In
the Block I and Block II spacecraft design, combustible materials were
contiguous to potential ignition sources.
- Determination
- In the Block I and Block II spacecraft design, combustible materials were
exposed in sufficient quantities to constitute a fire hazard.
- Finding
- The spacesuit contained power wiring to electronic circuits. The
astronauts could be electrically insulated.
- Determination
- Both the power wiring and potential for static discharge constituted
possible ignition sources in the presence of combustible materials. The wiring
in the suit could fail from working or bending.
- Finding
- Residues of RS89 (inhibited ethylene glycol/water solution) after drying
were both corrosive and combustible. RS89 was corrosive to wire bundles
because of its inhibitor.
- Determination
- Because of the corrosive and combustible properties of the residues, RS89
coolant could, in itself, provide all of the elements of a fire hazard if it
leaked onto electrical equipment.
- Finding
- Water/glycol was combustible, although not easily ignited.
- Determination
- Leakage of water/glycol in the cabin would increase risk of fire.
- Finding
- Deficiencies in design, manufacture, and quality control were found in the
postfire inspection of the wire installation.
- Determination
- There was an undesirable risk exposure, which should have been prevented
by both the contractor and the government.
- Finding
- The spacecraft atmosphere control system design was based on providing a
pure oxygen environment.
- Determination
- The technology was so complex that, to provide diluent gases, duplication
of the atmosphere control components as well as addition of a mechanism for
oxygen partial-pressure control would be required. These additions would
introduce additional crew-safety failure modes into the flight systems.
- Finding
- Sixty seconds were required for unaided crew egress from the CM. The hatch
could not be opened with positive cabin pressure above approximately 0.17
newtons per sq cm (0.25 psi). The vent capacity was insufficient to
accommodate the pressure buildup in the Apollo 204 spacecraft.
- Determination
- Even under optimum conditions emergency crew egress from Apollo 204
spacecraft could not have been accomplished in sufficient time.
- Finding
- During the January 27 Apollo 204 test, difficulty was experienced in
communicating from ground to spacecraft and among ground stations.
- Determination
- The ground system design was not compatible with operational
requirements.
"Board Proceedings" and Append. D, "Panels 6 thru 10,"
Report of Apollo 204 Review Board, pp. 3-33 and D-9-3 through
3-9-13.
March 31
The Integration Analysis Panel (No. 18) was rewriting its final
report to the Apollo 204 Review Board. Panel 18 had been assigned to review
information from all task groups and make the final technical integration of the
evidence. Panels 3 and 16 had been merged with Panel 18 on February 23. In its
final report to the Review Board, Panel 18 listed:
- Findings
- Several arcing indications were observed in the CM left front sector and a
voltage transient was noted in all three phases of AC Bus 2. This transient
was most closely simulated by a power interruption or short circuit on DC Bus
B. Physical evidence and witness statements indicated the progress of the fire
to be from the left side of the spacecraft. Simulations and tests indicated
that combustion initiation by electrostatic discharge or chemical action was
not probable. No physical evidence of prefire overheating of mechanical
components or heating devices was found.
- Determinations
- No single ignition source could be conclusively identified. The most
probable initiator was considered to be the electrical arcing or shorting in
the left front sector of the spacecraft. The location best fitting the total
available information was that where environmental control system
instrumentation power wiring ran into the area between the environmental
control unit and the oxygen panel.
- Finding
- All spacecraft records were reviewed by the various panels and the results
were screened by Panel 18.
- Determination
- No evidence was found to correlate previously known discrepancies,
malfunctions, qualification failures or open work items with the source of
ignition.
- Finding
- At the time of the observed fire, data including telemetry and voice
communications indicated no malfunctioning spacecraft systems (other than the
live microphone).
- Determination
- Existing spacecraft instrumentation was insufficient by itself to provide
data to identify the source of ignition.
"Board Proceedings" and
Append. D, "Panel 18," Report of Apollo 204 Review Board, pp. 3-33
and D-18-3 through D-18-51.
March 31
The final report of the Medical Analysis Panel (No. 11) to the
Apollo 204 Review Board was processed for printing. The panel had been assigned
to provide a summary of medical facts with appropriate medical analysis for
investigation of the January 27 fire. Examples were cause of death, pathological
evidence of overpressure, and any other areas of technical value in determining
the cause of accident or in establishing corrective action.
The panel report indicated that at the time of the accident two NASA
physicians were in the blockhouse monitoring data from the senior pilot. Upon
hearing the first voice transmission indicating fire, the senior NASA physician
turned from the biomedical console to look at the bank of television monitors.
When his attention returned to the console the bioinstrumentation data had
stopped. The biomedical engineer in the Acceptance Checkout Equipment (ACE)
Control Room called the senior medical officer for instructions. He was told to
make the necessary alarms and informed that the senior medical officer was
leaving his console. The two NASA physicians left the blockhouse for the base of
the umbilical tower and arrived there shortly before ambulances and a Pan
American physician arrived at 6:43 p.m. The three physicians went to the
spacecraft; time of their arrival at the White Room was estimated to be 6:45
p.m. EST.
By this time some 12 to 15 minutes had elapsed since the fire began. After a
quick evaluation it was evident that the crew had not survived the heat, smoke,
and burns and it was decided that nothing could be gained by attempting
immediate egress and resuscitation.
Panel 11's 24 findings included:
- Finding
- Biomedical data at the time of the accident were received from only the
senior pilot. The data consisted of one lead of electrocardiogram, one lead of
phonocardiogram, and impedance pneumogram (respiration). The data was received
by telemetry and from the onboard medical data acquisition system.
- Determination
- This configuration was normal for the test.
- Finding
- At 6:31:04 p.m. there was a marked change in the senior pilot's
respiratory and heart rates on the biomedical tape. There was also evidence of
muscle activity in the electrocardiogram and evidence of motion in the
phonocardiogram. The heart rate continued to climb until loss of signal.
- Determination
- This physiological response is compatible with the realization of an
emergency situation.
- Finding
- Voice contact with the crew was maintained until 6:31:22.7
- Determination
- At least one crew member was conscious until that time.
- Finding
- Hatches were opened at approximately 6:36 p.m. and no signs of life were
detected. Three physicians looked at the suited bodies at approximately 6:45
p.m. and decided that resuscitation efforts would be to no avail.
- Determination
- Time of death could not be determined from this finding.
- Finding
- "The cause of death of the Apollo 204 Crew was asphyxia due to inhalation
of toxic gases due to fire. Contributory cause of death was thermal burns."
- Determination
- It could be concluded that death occurred rapidly and that unconsciousness
preceded death by some increment of time. The fact that an equilibrium had not
been established throughout the circulatory system indicated that blood
circulation stopped rather abruptly before an equilibrium could be reached.
- Finding
- Panel 5 had estimated that significant levels (more than two percent) of
carbon monoxide were in the spacecraft atmosphere by 6:31:30 p.m. EST. By this
time at least one spacesuit had failed, introducing cabin gases to all suit
loops.
- Determination
- The crew was exposed to a lethal atmosphere when the first suit was
breached.
- Finding
- The distribution of carbon monoxide in body organs indicated that
circulation stopped rather abruptly when high levels of carboxyhemoglobin
reached the heart.
- Determination
- Loss of consciousness was caused by cerebral hypoxia due to cardiac arrest
from myocardial hypoxia. Factors of temperature, pressure, and environmental
concentrations of carbon monoxide, carbon dioxide, oxygen, and pulmonary
irritants were changing at extremely rapid rates. It was impossible from
available information to integrate these variables with the dynamic
physiological and metabolic conditions they produced, to arrive at a precise
statement of the time when consciousness was lost and when death supervened.
Loss of consciousness was estimated as at between 15 and 30 seconds after the
first suit failed. Chances of resuscitation decreased rapidly thereafter and
were irrevocably lost within 4 minutes.
- Finding
- The purge with 100-percent oxygen at above sea-level pressure contributed
to the propagation of fire in the Apollo 204 spacecraft.
- Determination
- The oxygen level was the planned cabin environment for testing and launch,
since prelaunch denitrogenation was necessary to forestall the possibility of
the astronauts' suffering the bends. A comprehensive review of operational and
physiological tradeoffs of various methods of denitrogenation was in
progress.
"Board Proceedings" and Append. D, "Panel 11," Report
of Apollo 204 Review Board, pp. 333 and D-11-3 through D-11-9.
March 31
ASPO Manager Joseph F. Shea requested that the White Sands Test
Facility be authorized to conduct the descent propulsion system series tests
starting April 3 and ending about May 1. The maximum expected test pressure
would be 174 newtons per sq cm (253 psia), normal maximum operating pressure.
The pressure could go as high as 179 newtons per sq cm (260 psia) according to
the test to be conducted.
Required leak check operations were also requested at a maximum pressure of
142 newtons per sq cm (206 psia), with a design limit of 186 newtons per sq cm
(270 psia). The test fluids would be compatible with the titanium alloy at the
test pressures. The test would be conducted in the Altitude Test Stand, where
adequate protection existed for isolating and containing a failure. MSC Director
Robert R. Gilruth approved the request the same day.
Memo, Shea to Gilruth, "Request for authorization to conduct a pressure
test," March 31, 1967.
April 1
In reply to a request from NASA Hq., CSM Manager Kenneth S.
Kleinknecht told Apollo Program Director Samuel C. Phillips that replacement of
the service module 017 oxidizer tank was based on a double repair weld of the
method 2 kind in that tank. This kind of repair, he said, resulted in a weld
chemistry similar to the weld on the S-IVB helium bottle that had failed, as had
only recently been determined by examination of the secondary-propulsion-system
tank repair weld. There was insufficient proof that titanium hydride
concentrations could not occur in the double method-2 repair weld, and
replacement of the tank would preclude any question as to the integrity of the
tank. The decision was delayed as long as possible in the hope of developing
technical justification of weld integrity. When that was not achieved and there
was little confidence that justification could be developed in the near future,
the decision was made directing the tank change. The activity would not cause
additional schedule time loss, as it was already necessary to repeat the
spacecraft integrated test because of wiring rework.
Ltr., Kleinknecht to Phillips, "Delay in Direction to Effect Service Module
Tank Change," April 1, 1967.
April 5
The mission profile for the first manned Apollo flight would be
based on that specified in Appendix AS-204 in the Apollo Flight Mission
Assignments Document dated November 1966, the three manned space flight Centers
were informed. Apollo Program Director Samuel C. Phillips said the complexity of
the mission was to be limited to that previously planned, and therefore
consideration of a rendezvous exercise would be dependent upon the degree of
complication imposed on the mission. "There will be no additions that require
major new commitments such as opening a CM hatch in space or exercising the
docking subsystem."
TWX, Phillips to MSC, MSFC, and KSC, "First Manned Mission," April 5, 1967.
April 5
The Apollo 204 Review Board transmitted its final formal report
to NASA Administrator James E. Webb, each member concurring in each of the
findings, determinations, and recommendations concerning the January 27
spacecraft fire that took the lives of three astronauts.
The Apollo 204 Review Board studied Apollo spacecraft 014 (above) in
its investigation of the January 27, 1967, fire in the similar CM 012 (below,
photographed after the fire). The interior view shows the forward section of the
left-hand equipment bay, below the environmental control unit in each
spacecraft. The DC power cable crosses over aluminum tubing and under a lithium
hydroxide access door (removed in the photo of the damaged CM 012). The board
determined this was the area of the most probable initiator of the fire.
During the review the Board had adhered to the principle that reliability of
the CM and the entire system involved in its operation was a requirement common
to both safety and mission success. Once the CM had left the earth's environment
the occupants were totally dependent on it for their safety. It followed that
protection from fire as a hazard required much more than quick egress. Egress
was useful only during test periods on earth when the CM was being readied for
its mission and not during the mission itself. The risk of fire had to be faced,
but that risk was only one factor pertaining to CM reliability that must receive
adequate consideration. Design features and operating procedures intended to
reduce the fire risk must not introduce other serious risks to mission success
and safety.
The House Committee on Science and Astronautics' Subcommittee on NASA
Oversight held hearings on the Review Board report April 10-12, 17, and 21 and
May 10. Senate Committee on Aeronautical and Space Sciences hearings were held
April 11, 13,and 17 and May 4 and 9 (see May 9-10, 1967, and Appendix 8).
Findings, determinations, and recommendations of the Apollo 204 Review Board
were:
- Finding
-
- A momentary power failure occurred at 6:30:55 p.m. EST (23:30:55 GMT).
- Evidence of several arcs was found in the postfire investigation.
- No single ignition source of the fire was conclusively
identified.
- Determination
- The most probable initiator was an electrical arc in the sector between
the -Y and +Z spacecraft axes. The exact location best fitting the total
available information was near the floor in the lower forward section of the
left-hand equipment bay where environmental control system instrumentation
power wiring led into the area between the environmental control unit and the
oxygen panel. No evidence was discovered that suggested sabotage.
- Finding
-
- The CM contained many classes of combustible material in areas
contiguous to possible ignition sources.
- The test was conducted with a 100-percent oxygen atmosphere at 11.5
newtons per sq cm (16.7 psia).
- Determination
- The test conditions were extremely hazardous.
- Recommendation
- The amount and location of combustible materials in the CM must be
severely restricted and controlled.
- Finding
-
- The rapid spread of fire increased pressure and temperature, rupturing
the CM and creating a toxic atmosphere. "Death of the crew was from asphyxia
due to inhalation of toxic gases due to fire. A contributory cause of death
was thermal burns."
- Non-uniform distribution of carboxyhemoglobin was found by
autopsy.
- Determination
- Autopsy data led to the medical opinion that unconsciousness occurred
rapidly and that death followed soon thereafter.
- Finding
- Because of internal pressure, the CM inner hatch could not be opened
before rupture of the CM.
- Determination
- The crew was never capable of effecting emergency egress because of the
pressurization before the rupture and their loss of consciousness soon after
rupture.
- Recommendation
- The time required for egress of the crew should be reduced and the
operations necessary for egress be simplified.
- Finding
- The organizations responsible for planning, conducting, and safety of this
test failed to identify it as being hazardous. Contingency preparations to
permit escape or rescue of the crew from an internal CM fire were not made.
- No procedures for this kind of emergency had been established either for
the crew or for the spacecraft pad work team.
- The emergency equipment in the White Room and on the spacecraft work
levels was not designed for the smoke condition resulting from a fire of
this nature.
- Emergency fire, rescue, and medical teams were not in attendance.
- Both the spacecraft work levels and the umbilical tower access arm
contained features such as steps, sliding doors, and sharp turns in the
egress paths which hindered emergency operations.
- Determination
- Adequate safety precautions were neither established nor observed for this
test.
- Recommendations
-
- Management should continually monitor the safety of all test operations
and ensure the adequacy of emergency procedures.
- All emergency equipment (breathing apparatus, protective clothing,
deluge systems, access arm, etc.) should be reviewed for adequacy.
- Personnel training and practice for emergency procedures should be given
regularly and reviewed before a hazardous operation.
- Service structures and umbilical towers should be modified to facilitate
emergency operations.
- Finding
- Frequent interruptions and failures had been experienced in the overall
communication system during the operations preceding the accident.
- Determination
- The overall communication system was unsatisfactory.
- Recommendation
-
- The ground communication system should be improved to ensure reliable
communications among all test elements as. soon as possible and before the
next manned flight.
- A detailed design review should be conducted on the entire spacecraft
communication system.
- Finding
-
- Revisions in the Operational Checkout Procedure for the test were issued
at 5:30 p.m. EST January 26, 1967 (209 pages), and 10:00 a.m. EST January
27, 1967 (4 pages).
- Differences existed between the ground test procedures and the inflight
checklists.
- Determination
- Neither the revision nor the differences contributed to the accident. The
late issuance of the revision, however, prevented test personnel from becoming
adequately familiar with the test procedure before use.
- Recommendations
-
- Test procedures and pilot's checklists that represent the actual CM
configuration should be published in final form and reviewed early enough to
permit adequate preparation and participation of all test organizations.
- Timely distribution of test procedures and major changes should be made
a constraint to the beginning of any test.
- Finding
- The fire in CM 012 was subsequently simulated closely by a test fire in a
full-scale mockup.
- Determination
- Full-scale mockup fire tests could be used to give a realistic appraisal
of fire risks in flight-configured spacecraft.
- Recommendation
- Full-scale mockups in flight configuration should be tested to determine
the risk of fire.
- Finding
- The CM environmental control system design provided a pure oxygen
atmosphere.
- Determination
- This atmosphere presented severe fire hazards if the mount and location of
combustibles in the CM were not restricted and controlled.
- Recommendations
-
- The fire safety of the reconfigured CM should be established by
full-scale mockup tests.
- Studies of the use of a diluent gas should be continued, with particular
reference to assessing the problems of gas detection and control and the
risk of additional operations that would be required in the use of a two-gas
atmosphere.
- Finding
- Deficiencies existed in CM design, workmanship and quality control, such
as:
- Components of the environmental control system installed in CM 012 had a
history of many removals and of technical difficulties, including regulator
failures, line failures, and environmental control unit failures. The design
and installation features of the environmental control unit made removal or
repair difficult.
- Coolant leakage at solder joints had been a chronic problem.
- The coolant was both corrosive and combustible.
- Deficiencies in design, manufacture, installation, rework, and quality
control existed in the electrical wiring.
- No vibration test was made of a complete flight-configured spacecraft.
- Spacecraft design and operating procedures required the disconnecting of
electrical connections while powered.
- No design features for fire protection were incorporated.
- Determination
- These deficiencies created an unnecessarily hazardous condition and their
continuation would imperil any future Apollo Operations.
- Recommendations
-
- All elements, components, and assemblies of the environmental control
system should be reviewed in depth to ensure its functional and structural
integrity and to minimize its contribution to fire risk.
- The design of soldered joints in the plumbing should be modified to
increase integrity or the joints should be replaced with a more structurally
reliable configuration.
- Deleterious effects of coolant leakage and spillage should be
eliminated.
- Specifications should be reviewed; three-dimensional jigs should be used
in manufacture of wire bundles; and rigid inspection at all stages of wiring
design, manufacture, and installation should be enforced.
- Flight-configured spacecraft should be vibrationtested.
- The necessity for electrical connections or disconnections with power on
within the crew compartment should be eliminated.
- The most effective means of controlling and extinguishing a spacecraft
fire should be investigated. Auxiliary breathing oxygen and crew protection
from smoke and toxic fumes should be provided.
- Finding
- An examination of operating practices showed the following examples of
problem areas:
- The number of open items at the time of shipment of the CM 012 was not
known. There were 113 significant engineering orders not accomplished at the
time CM 012 was delivered to NASA; 623 engineering orders were released
subsequent to delivery. Of these, 22 were recent releases that were not
recorded in configuration records at the time of the accident.
- Established requirements were not followed with regard to the pretest
constraints list. The list was not completed and signed by designated
contractor and NASA personnel before the test, even though oral agreement to
proceed was reached.
- Formulation of and changes in prelaunch test requirements for the Apollo
spacecraft program were responsive to changing conditions.
- Noncertified equipment items were installed in the CM at time of test.
- Discrepancies existed between NAA and NASA MSC specifications regarding
inclusion and positioning of flammable materials.
- The test specification was released August 1966 and was not updated to
include accumulated changes from release date to the January 27 test
date.
- Determination
- Problems of program management and relations between Centers and with the
contractor had led to some insufficient responses to changing program
requirements.
- Recommendation
- Every effort must be made to ensure the maximum clarification and
understanding of the responsibilities of all organizations in the program, the
objective being a fully coordinated and efficient program.
Report
of Apollo 204 Review Board to the Administrator, National Aeronautics and Space
Administration, April 5, 1967, transmittal letter and pp. 6-1 through 6-3
; House Committee on Science and Astronautics, Subcommittee on NASA Oversight,
Investigation into Apollo 204 Accident: Hearings, 90th Cong., 1st
sess., vols. 1-3, April 10, 11, 17, 21, May 10, 1967; Senate Committee on
Aeronautical and Space Sciences, Apollo Accident: Hearings, 90th
Cong., 1st sess., pts. 3-7, April 11, 13, and 17, May 4 and 9, 1967.