Part 2 (B)
Recovery, Spacecraft Redefinition, and First Manned Apollo Flight
May 1967
1967
May 1
MSC estimated the effect of the Apollo 204 fire on program costs
for FY 1967 and 1968, in reply to April 26 instructions from NASA Apollo
Program.
Manager Samuel C. Phillips. Estimates were:
Command and service modules |
$25 million |
Lunar module |
$21 million |
Other |
$35 million |
|
|
Total |
$81 million |
Further, the program extension resulting from the accident would require an
additional budget allocation during FY 1969 and continuing through program
runout. A May 4 message from MSC confirmed the information telephoned to
Headquarters May 1.
The following ground rules had been used in estimating the cost impact:
- All changes planned as of May 1 for the command and service modules and
the lunar module were included.
- Vehicle delivery dates were as of April 29. Guidance and navigation
schedules were adjusted to support revised CSM and LM need dates.
TWXs,
NASA Hq. to MSC, "Cost Impact of 204 Accident," April 26, 1967; MSC to NASA Hq.,
"Cost Impact of the 204 Accident," May 4, 1967.
May 1
The Space and Information Systems Division of North American
Aviation, Inc., was renamed Space Division, effective May 1.
TWX, North American Aviation Space Div., Downey, Calif., to NASA Hq., MSFC,
MSC, and KSC, "Redesignation of S&ID as Space Division," May 9, 1967.
May 1
George C. White, Jr., NASA OMSF Director of Apollo Reliability and
Quality, told Apollo Program Director Samuel C. Phillips that an MSC
presentation on April 29 had restored confidence in Apollo's future, but three
areas caused him concern as possible compromises with crew safety and mission
success in the interest of near-term schedule and cost considerations. They
were:
- Soldered joints in coolant system plumbing. Design of the joints was
basically wrong; the insertion of the tubing into the sleeve was less than the
tube diameter. Shear strength of the solder had to be depended upon for
mechanical integrity against bending and vibration as well as for sealing.
Insertion should be two to three times the diameter so that bending could be
carried by the bearing of the tube in the sleeve, and the solder would only
have to seal.
- Wiring harnesses. Wiring in the Block II spacecraft had a number of
problems, the real significance of which was difficult to evaluate. Numerous
instances of damaged insulation (bare conductor) had been found and the
repairs had, in turn, resulted in more damage. At least once, split insulation
(bare conductor) had been found inside a wire bundle; it could have been in
the wire as received or could have resulted from cold flow.
- Modification procedure. MSC planned to make the changes in the Block II
spacecraft by working directly from mockup to the spacecraft, using sketches
and a minimum of paper work. While this kind of an operation could get a job
done in a hurry, it required a strong leader, thoroughly experienced in
working with engineering and factory people and procedures, and rigorous
adherence to a minimal streamlined paper system. All "engineering" must be on
drawings and all fabrication work must be inspected at least as rigorously as
in a normal manufacturing process.
White urged close management
attention to ensure quality. Memo, White to Phillips, "MSC plan presented on
April 29, 1967," May 1, 1967.
May 2
The Air Force Manned Orbiting Laboratory Systems Program Office
requested that MSC present a briefing to selected office and contractor
personnel on NASA's progress in safety studies and tests associated with fire
hazards aboard manned space vehicles. Information was requested for the MOL
program to help formulate studies and activities that would not duplicate MSC
efforts. The briefing was given at MSC May 10.
TWXs, MOL Systems Program Office, Los Angeles, to MSC, "Request for Briefing
on Safety Studies and Associated Tests," May 2, 1967; MSC to Space Systems Div.,
USAF, May 3, 1967.
May 2
ASPO Manager George M. Low asked the Chairman of the Apollo 204
Review Board to consider releasing CM 014 for use in the Apollo program. If the
Review Board had a continuing need for the CM, Low requested that consideration
be given to release of certain individual items needed for the Apollo Mission
Simulator program. Board Chairman Floyd L. Thompson notified Low on June 22 that
the CM mockup and CM 014 were no longer required by the Review Board and that
their disposition might be determined by the ASPO Manager.
Memo, Low to Chairman, Apollo 204 Review Board, "Release of Command Module
014," May 2, 1967; TWX, Thompson to MSC, Attn: George M. Low, June 22, 1967.
May 2-4
NASA Block II Redefinition Task Team group leaders and CSM
Program Manager Kenneth S. Kleinknecht arrived at North American Aviation Space
Division at Downey May 2, followed by Task Team Manager Frank Borman the next
day. Borman met with North American management May 4 to ensure understanding of
the team plan and objectives. An afternoon meeting with NASA and North American
Task Managers and group leaders reviewed the status of the Block II Redefinition
task.
Following is a summation of the technical status at the time:
- Ninety-five percent of the wires and break points had been defined,
including additional wires for changes (approximately 200) plus the existing
open items on spacecraft 101. Schematics for manufacturing and preparation of
integrated schematics were to be available May 30.
- AiResearch environmental control system components had been reviewed by
North American and direction transmitted for materials changes.
- North American was planning no compartment closeouts behind the front
panels. This was unacceptable to NASA and closeouts would be required.
- North American definition and review of all spacecraft materials
applications were in progress, but Borman reported the progress was too slow
to date and that a plan for expediting was under consideration.
- Fire extinguisher interfaces had not yet been identified. A meeting was
planned during the next week to resolve the problem.
- NASA reaffirmed to North American the intention that DITMCO (an inspection
process) of the completed installed harness be performed as late as possible
and that harness protection be reinstalled immediately after DITMCO.
Connectors which could not be DITMCOed must be reviewed with NASA, connector
by connector.
- NASA reaffirmed that a crew compartment fit and function test was required
on each spacecraft at Downey.
- Two meetings had been held on the Downey spacecraft 101 test and checkout.
Definition of requirements was progressing rapidly and was expected to be
completed and signed off by May 5. A schedule would be prepared for
distribution on May 9, for the preparation, review and final approval of the
operational checkout procedures necessary for the approved test requirement.
The launch site test plan for spacecraft 101 would be discussed in a meeting
at Downey May 9, and this meeting would be followed by a discussion of
spacecraft 2TV-1 Downey test requirements as related to the Houston tests for
the spacecraft 101 mission.
- The Test Group of the Task Team planned to work closely with the Checkout
Working Group and would be represented in its next meeting in Downey on May
11.
- Rework resulting from the wiring inspection of spacecraft 101 was not
proceeding as rapidly as desired; however, Borman reported that more efficient
procedures were being prepared and would be carried out as soon as possible.
- The Apollo spacecraft quality requirements were being reviewed and the
North American Quality Plan would be checked against these requirements in
detail.
Borman reported on plans and schedules:
- A documentation center was being established to provide configuration
documentation to the North American and NASA teams. A master change status
board would be maintained in the NASA Task Team Office, and Block II
specifications would be updated to provide the predesign baseline.
- North American had released Master Development Schedule-10 ahead of its
May 12 schedule, and detailed engineering, manufacturing, and Apollo test
operation schedules were being prepared.
Critical open items were:
- TV monitor requirements and interfaces,
- flashing beacon mechanization and requirements,
- material for the lithium hydroxide canister,
- emergency oxygen mask mechanization,
- water chlorination mechanization,
- rapid repressurization-mechanization or surge tank, and
- cabin recirculation valve requirement.
TWX, RASPO at Downey, Calif., to distr., "Block II Redefinition Daily Report
No. 1, dated May 4, 1967," May 5, 1967.
May 3
NASA's Space Science Steering Committee approved establishment of
a facility on the moon consisting of arrays of solid corner reflectors. The
first array was to be established by the earliest possible lunar landing
mission, with other arrays to be carried on subsequent missions. Until the
Committee and Manned Space Flight Experiment Board agreed on assignment of
priorities among the various lunar science experiments, this experiment was to
be considered a contingency experiment to be carried on a "space available"
basis. The facility on the moon would be available to the principal investigator
- C. O. Alley, University of Maryland - as well as to other scientists.
TWX, NASA Hq. to MSC, Attn: Robert Piland, May 3, 1967.
May 4
Directions had been prepared to designate mission AS-501 formally
as Apollo 4, AS-204/LM-1 as Apollo 5, and AS-502 as Apollo 6, NASA Apollo
Program Director Samuel C. Phillips informed Associate Administrator for Manned
Space Flight George E. Mueller. Phillips said he thought it was the right time
to start using the designations in official releases and appropriate internal
documentation. Mueller concurred.
Note, Phillips to Mueller, May 4, 1967.
May 5
Circuit breakers being used in both CSM and LM were flammable, MSC
ASPO Manager George Low told Engineering and Development Director Maxime A.
Faget. Low said that although Structures and Mechanics Division was developing a
coating to be applied to the circuit breakers, such a solution was not the best
for the long run. He requested that the Instrumentation and Electronics Systems
Division find replacement circuit breakers for Apollo - ideally, circuit
breakers that would not bum and that would fit within the same volume as the
existing ones, permitting replacement in panels already built. On July 12 Low
wrote Faget again: "In light of the work that has gone on since my May 5, 1967,
memo, are you now prepared to propose the use of metal-jacketed circuit breakers
for Apollo spacecraft? If the answer is affirmative, then we should get specific
direction to our contractors immediately. Also, have you surveyed the industry
to see whether a replacement circuit breaker is available or will be available
in the future?" Low requested an early reply.
Memos, Low to Faget, "Apollo circuit breakers," May 5, 1967; "Apollo circuit
breakers, continued," July 12, 1967.
May 5
After review of operational considerations for a minimum restart
capability in the Saturn launch vehicle's S IVB stage, MSC's Director of Flight
Operations reported to NASA Hq. that an 80-minute restart capability was
believed the best compromise for the early lunar missions, "for the primary
reason of providing sufficient time for ground support in verifying navigation,
and flight crew checkout of CSM and S-IVB systems prior to TLI [translunar
injection], while providing for two injection opportunities in both the Atlantic
and Pacific Oceans (second and third revolutions). For later missions,
consideration should be given to the hardware implications of providing a
restart capability with minimum (zero) restrictions, so that advantage may be
taken of confidence in onboard systems to gain additional payload."
Ltr., Christopher C. Kraft, Jr., MSC, to NASA Hq., "S-IVB Restart
Capability," May 5, 1967.
May 9-10
NASA reported to Congress on actions taken on the Apollo 204
Review Board's findings and recommendations concerning the January 27 spacecraft
fire. Administrator James E. Webb, Deputy Administrator Robert C. Seamans, Jr.,
and Associate Administrator for Manned Space Flight George E. Mueller testified
before the Senate Committee on Aeronautical and Space Sciences May 9 and before
the House Committee on Science and Astronautics' Subcommittee on NASA Oversight
May 10. (See also September 21 and Appendix 8.)
Senate Committee on Aeronautical and Space Sciences, Apollo Accident:
Hearings, 90th Cong., 1st sess., pts. 6-7, May 9, 1967; House Committee
on Science and Astronautics, Subcommittee on NASA Oversight, , 90th Cong.,
1st sess, vol. 3, May 10, 1967; Astronautics and Aeronautics, 1967
(NASA SP-4008, 1968), pp. 144-148.).
May 10MSC responded to a March 29 letter from NASA Hq.
concerning two arrays of Apollo Lunar Surface Experiments Package (ALSEP)
experiments. MSC said it had reviewed schedules, cost, and integration aspects
of the requested configurations and that four areas of the project apparently
should be modified to allow proper inclusion of the configurations:
- extension of mission support efforts by Bendix Aerospace Systems Division
(BxA) for the fourth ALSEP mission;
- extension of KSC's support efforts by BxA for the fourth ALSEP mission;
- extension of the ALSEP prototype test program to encompass three distinct
system configurations rather than the two in the original plans; and
- extension of the ALSEP qualification test program to encompass three
distinct configurations rather than the original two.
The cost impact
was estimated at $670,000, and completion of the ALSEP contract was expected to
be extended three months to allow for mission support for the fourth flight.
Ltr., Robert R. Gilruth, Director, MSC, to NASA Hq., Attn: Samuel C.
Phillips, "Selection of Apollo Lunar Surface Experiments Package System
Configurations," May 10, 1967.
May 11
NASA Administrator James E. Webb issued a statement on selection
of the Apollo spacecraft contractor: "In the 1961 NASA decision to negotiate
with North American Aviation for the Apollo command and service modules, there
were no better qualified experts in or out of NASA on whom I could rely than Dr.
Robert Gilruth, Dr. Robert C. Seamans, and Dr. Hugh L. Dryden. These three were
unanimous in their judgment that of the five companies submitting proposals, and
of the two companies that were rated highest by the Source Evaluation Board,
North American Aviation offered the greatest experience in developing
high-performance manned flight systems and the lowest cost.
"In the selection of North American Aviation, the work of the Source
Evaluation Board was not rejected or discarded. It was used as the basis for a
more extensive and detailed examination of all pertinent factors than the Board
had performed at the time its report was presented to Dr. Gilruth, Dr. Seamans,
Dr. Dryden and to me.
"At that point it became the responsibility of NASA's Associate
Administrator, Dr. Seamans; its Deputy Administrator, Dr. Dryden; and its
Administrator, myself, to take all steps necessary to determine whether the
facts then available formed an adequate basis for our selection of a contractor.
We decided in the affirmative and then proceeded to select the contractor the
facts indicated offered the most to the government."
NASA News Release 67-122, May 11, 1967.
May 12
George M. Low, Manager of the Apollo Spacecraft Program, notified
NASA Hq. that Grumman was committed to a June 28 delivery for lunar module 1
(LM-1). This date included provisions for replacement of the development flight
instrumentation harness with a new one. Low's assessment was that the date would
be difficult to meet.
TWX, Low, MSC, to NASA Hq., Attn: Lee James, "LM-1 delivery schedule," May
12, 1967.
May 12
Anthony W. Wardell of the MSC Flight Safety Analysis Office wrote
Apollo Manager Low that "the May 10 inspection further substantiates my previous
recommendation to replace, rather than rework, the [spacecraft 101 wiring]
harness. In addition to the visual evidence of wire damage noted, a book
containing about 100 outstanding wire damage MRB (Material Review Board) actions
was noted on a work table near the spacecraft." He did, however, list seven
recommended suggestions to be followed in the event the harnesses were reworked
rather than replaced. The suggestions were passed on to CSM Manager Kenneth S.
Kleinknecht by Low in a memorandum on May 13. Low requested that the suggestions
be passed to North American Aviation as soon as possible, with additional
suggestions from MSC Quality Control Chief Jack A. Jones, who had also inspected
the harness.
Memos, Jones to Low, "Inspection of SC-101 Wire Harness Assemblies," May 10,
1967; Wardell to Low, "Inspection of Spacecraft 101 Wiring Harnesses," May 12,
1967; Low to Kleinknecht, "Spacecraft 101 wiring," May 13, 1967
May 12
Apollo 204 Review Board Chairman Floyd L. Thompson appointed a
subcommittee to examine the final report of Panel 18 and prepare recommendations
regarding its acceptability for inclusion in the Board's Report. Thompson named
Maxime A. Faget, MSC, to chair the subcommittee and Frank Borman, MSC, George C.
White, NASA Hq., and E. Barton Geer, LaRC, as members. Thompson asked that the
subcommittee forward its recommendations at the earliest possible date and that
it also review the comments of North American Aviation on the validity of the
findings of the Board and its Panels.
TWX, Thompson to addressees, May 12, 1967.
May 15
The NASA Block II CSM Redefinition Task Team was augmented by the
assignment of Gordon J. Stoops as Group Leader-Program Control, with the
following functions:
- Liaison with North American Aviation Program Control and Contracts to
expedite updating of the contract change authorizations and the issuance of
timely program technical direction.
- Liaison with the ASPO CSM project Engineering and Checkout Division and
CSM Contract Engineering Branch at MSC to expedite contract change
authorizations and ensure timely program technical direction.
Memo,
Manager, CSM, ASPO, to distr., "Block II redefinition, command and service
modules," May 15, 1967.
May 18
Prime and backup crews for Apollo 7 (spacecraft 101) were named,
with the assignments effective immediately. The prime crew for the
engineering-test-flight mission was to consist of Walter M. Schirra, Jr.,
commander; Donn F. Eisele, CM pilot; and R. Walter Cunningham, LM pilot. The
backup crew was Thomas P. Stafford, commander; John W. Young, CM pilot; and
Eugene A. Cernan, LM pilot. Names had been reported to the Senate Committee on
Aeronautical and Space Sciences on 9 May.
Memo, Astronaut Office to distr., "Astronaut Technical Assignments," May 18,
1967; Senate committee on Aeronautical and Space Sciences, Apollo
Accident: Hearings, 90th Cong., 1st sess., pt. 6, May 9, 1967.
May 19
A Block II spacecraft vibration program was begun to provide
confidence in CSM integrity and qualify the hardware interconnecting the
subsystems within the spacecraft. A test at MSC was to simulate the vibration
environment of max-q flight conditions. The test article was to be a Block II
CSM. A spacecraft-LM adapter, an instrumentation unit, and an S-IVB stage
forward area simulation would also be used.
Memo, Chief, Systems Engineering Div. (MS), to Manager, ASPO, "Block II
spacecraft vibration program," with encl., "Block II Spacecraft Vibration
Program," May 19, 1967.
May 20
MSC notified NASA Hq. that - with the changes defined for the
Block II spacecraft following the January 27 Apollo 204 fire and with CSM
delivery schedules now reestablished - it was necessary to complete a contract
for three additional CSMs requested in 1966. North American Aviation had
responded September 15, 1966, to MSC's February 28 request for a proposal, but
action on a contract had been suspended because of the AS-204 accident. NASA Hq.
on June 27, 1967, authorized MSC to proceed.
TWXs, Manager, ASPO, to NASA Hq., Attn: Samuel C. Phillips, "Authorization
for procurement of three additional Block II CSM's," May 20, 1967; NASA Hq.,
Associate Administrator for Manned Space Flight to MSC, Attn: George Low, June
27, 1967.
May 22
MSC ASPO Manager George Low informed Grumman Senior Vice
President George Titterton that he had asked North American Aviation assistance
in improving access to the LM when placed inside the spacecraft-lunar module
adapter (SLA). He also ordered a change request, in response to Grumman's April
18 request that MSC consider an SLA design change. Low had visited the pad at
KSC Launch Complex 37, agreed action was necessary, and on May 19 asked North
American's Apollo Program Manager Dale D. Myers for recommendations. Low said
improved access to the LM was needed "both for rapid emergency egress and for
normal servicing."
An emergency method of cutting through the SLA structure in premarked
locations with a "cookie cutter" portable handsaw device was adopted - primarily
for exit in an emergency occurring after hypergolics were loaded into the LM.
Ltrs., Titterton to MSC, Apr. 18, 1967; Low to Myers, May 19, 1967; Low to
Titterton, May 22. 1967; memo, ASPO Manager to R. W. Williams, "Preparation of
change request," May 22. 1967; Myers to Low, Aug. 11, 1967.
May 25
MSC submitted requirements to KSC that TV signals from cameras
inside the LM and CM be monitored and recorded during manned hazardous tests,
with hatch open or closed, and tests in the Vehicle Assembly Building, launch
pads, and altitude chambers. A facility camera was to monitor the
propellant-utilization gauging system during propellant loading. MSC specified
that the field of view of the TV camera should encompass the shoulder and torso
and portions of the legs of personnel at the normal flight stations in both the
CM and the LM.
Ltr., Owen G. Morris, MSC, to KSC, "Continuous Television Recording in
Support of Manned Apollo Tests at KSC," May 25, 1967.
May 26
ASPO Manager George Low told Charles A. Berry, MSC Director of
Medical Research and Operations, that it had been determined there was no
suitable substitute for water glycol as a coolant and it would continue to be
used in the Apollo spacecraft. Low recognized that it was "essential that the
effects of any possible glycol spill be well defined and that procedures be
established to avoid any hazardous conditions." He asked Berry's office to
define the limits of exposure for glycol spills of varying quantities and for
recommendations concerning cabin purge in the event of a spill. Low also
wondered, assuming development of a smelling agent, if it would be possible to
determine the concentration of water glycol by the strength of the smell in the
spacecraft. Berry's office replied June 22 that it was working with Crew Systems
Division to identify an odor additive for leak detection. They would begin a
program to establish a safe upper limit for human exposure to ethylene glycol
and had asked the National Academy of Sciences Committee on Toxicity for
information. Animal exposure tests probably would be necessary; if they were
needed, a test plan would be submitted before July 1.
Memos, Manager, ASPO, to Berry, "Water glycol toxicity," May 26, 1967; Berry
to Low, June 22, 1967.
May 26
NASA Headquarters and MSC officials attended a review of the CSM
at North American Aviation in Downey. Following the North American briefing, the
group visited the wire-harness layout and assembly areas. NASA Associate
Administrator for Manned Space Flight George E. Mueller, with Anthony W. Wardell
and Jack A. Jones of MSC, inspected the wiring in spacecraft 101 and 2TV-1 in
detail.
Mueller stressed the importance of improving spacecraft delivery schedules,
with particular emphasis on spacecraft 020 and the second and third manned
spacecraft, working up to two-month delivery intervals. He was concerned about
the five- to six-week spacecraft 020 hatch delay and stated that Apollo Program
Director Samuel C. Phillips must approve the proposed change. North American
pointed out that it was using the resources of the corporation toward the
two-month delivery schedule, and that a modification task-team approach would be
used as long as it was effective in improving schedules. Tiger teams of
engineering, quality, manufacturing, and materials personnel were working on
wiring and plumbing in spacecraft 101. CSM Manager Kenneth S. Kleinknecht
reviewed the Block II Redefinition Task Team effort for Mueller and he indicated
that Phillips had considered an industry tiger team to assist in the overall
spacecraft effort.
Memo, Kleinknecht to ASPO Manager, "Review of command and service modules,"
May 26, 1967.
May 26
Apollo 204 Review Board Chairman Floyd L. Thompson wrote NASA
Deputy Administrator Robert C. Seamans, Jr., "The Apollo 204 Review Board
respectfully submits that it has fulfilled all of its duties and
responsibilities as prescribed by the Deputy Administrator's memorandum of
February 3, 1967. Accordingly, it is requested that the Apollo 204 Review Board
be dissolved."
Ltr., Thompson to Seamans, "Report of Completion of Apollo 204 Review Board
Activities," May 26, 1967.
May 29
W. R. Downs, Special Assistant for Advanced Systems, MSC
Structures and Mechanics Division, discovered that bare or defectively insulated
silver-covered copper wires exposed to glycol/water solutions would ignite
spontaneously and burn in oxygen. Copper wire or nickel-covered copper wire
under identical conditions did not ignite. The laboratory results were confirmed
in work at the Illinois Institute of Technology. In a June 13 memorandum, the
Chief of the Structures and Mechanics Division recommended that if additional
testing verified that nickel-coated wires were free of the hazard, consideration
should be given to an in-line substitution of nickel-coated wires for
silver-coated wires in the LM. It was understood that the Block II CSM already
had nickel-coated wires. In a June 20 memo to the ASPO Manager, the Director of
Engineering and Development pointed out that silver-plated pins and sockets in
connectors would offer the same hazards. He added that Downs had also identified
a chelating agent that would capture the silver ion and apparently prevent the
reaction chain. In a July 24 memorandum, ASPO Manager George Low said that, in
view of recent spills of ethylene glycol and water mixtures, spacecraft
contractors North American Aviation and Grumman Aircraft Engineering had been
directed to begin actions immediately to ensure that a fire hazard did not exist
for the next manned spacecraft. Actions were to include identification of the
location of silver or silver-covered wires and pins and of glycol spills.
Memos, Special Assistant for Advanced Systems to Chief, Structures and
Mechanics Div., "Chemical reactivity of silver covered copper wires with
glycol/water solutions compared to copper or nickel covered copper wires," May
29, 1967 (rev. June 12, 1967); Chief, Structures and Mechanics Div., to Director
of Engineering and Development, "Silver-covered copper wires as a fire producing
hazard in spacecraft," June 13, 1967; Director of Engineering and Development to
Manager, ASPO, "Silver-covered copper wires as a fire producing hazard in
spacecraft," June 20, 1967; Manager, ASPO, to distr., "Silver-covered copper
wires as a fire producing hazard in spacecraft," July 24, 1967.
May 31
Grumman Aircraft Engineering Corp.'s method of building wiring
harness for the lunar module was acceptable, George Low, MSC Apollo Spacecraft
Program Office Manager, wrote Apollo Program Manager Samuel C. Phillips at NASA
Hq. Low had noted on a visit to Grumman on May 9 that many of the harnesses were
being built on two-dimensional boards. In view of recent discussions of the
command module wiring, Low requested Grumman to reexamine their practice and to
reaffirm their position on two-versus three-dimensional wiring harnesses.
In his May 31 letter to Phillips, Low enclosed Grumman's reply and said that,
in his opinion, Grumman's practice was acceptable because
- most wire bundles on the LM were much thinner than the CSM wiring bundles
and were much more flexible;
- portions of the LM harness were often fabricated on a three dimensional
segment of the harness board; and
- connectors were usually mounted on metal brackets with the proper
direction and clocking.
Ltrs., Low to Phillips, May 31, 1967; J. G.
Gavin to Low, "Use of Two and Three Dimensional Harness Boards in Fabrication of
LM Wiring," May 24, 1967; Grumman LM Manufacturing Memo, W. B. Atchison to C. W.
Rathke, "Harness Board Design - 2D vs. 3D," 17 May 1967.
May 31
George M. Low told Joseph N. Kotanchik, Chief of MSC's Structures
and Mechanics Division, that actions were pending on Pratt & Whitney
pressure vessel failures. The pressure vessels were used in the Apollo fuel cell
system. Kotanchik had spelled out a list of problem areas in connection with
both the vessels and management interface between MSC and principal contractor
North American Aviation, and between North American and its subcontractor Pratt
& Whitney.
Memos, Chief, Structures and Mechanics Div., to Manager, ASPO, "Conduct of
Pratt and Whitney Aircraft (PWA) on pressure vessel failure analysis," May 18,
1967; Low to Kotanchik, "Pratt & Whitney pressure vessel failures," May 31,
1967.