Fabrication of spacecraft
012 at North American Aviation, |
Aug 1964 |
|
|
Basic structure completed. |
Sept 1965 |
|
|
Installation and final assembly of subsystems completed. Critical design reviews completed. Checkout of all subsystems initiated, followed by integrated testing of all spacecraft subsystems. |
Mar 1966 |
|
|
Customer acceptance readiness review completed. NASA issued certificate of flightworthiness and authorized spacecraft to be shipped to KSC. |
Aug 1966 |
|
|
Command module received at KSC. |
|
|
|
CM-012 mated with service module in altitude chamber. Alignment, subsystems and system certification tests and functional checks performed. |
Sep 1966 |
|
|
First combined systems tests completed. |
|
|
|
Design certification document issued which certified design as flightworthy, pending satisfactory resolution of open items. |
|
|
|
First manned test at sea level pressure to verify total spacecraft system operation completed. |
|
|
|
Unmanned test at altitude pressures using oxygen to verify spacecraft system operation. |
|
|
|
Manned test with flight crew completed. |
|
|
|
Second manned altitude test with backup crew initiated, but discontinued when failure occurred in oxygen system regulator in spacecraft environmental control system. Regulator removed and found to have design deficiency. |
|
|
|
Apollo program director conducted recertification review which closed out majority of open items remaining from previous reviews. |
|
|
|
Sea level and unmanned altitude tests completed. |
|
|
|
Manned altitude test with backup flight crew completed. |
|
|
|
Command module removed from altitude chamber. |
|
|
|
Spacecraft mated to launch vehicle at Cape Kennedy Launch Complex 34. Various tests and equipment installations and replacements performed. |
|