Apollo 8 Spacecraft History
Event |
Date |
Saturn S-II stage #3 delivered to KSC. |
26 Dec 1967 |
Saturn S-IC stage #3 delivered to KSC. |
27 Dec 1967 |
Saturn S-IC stage #3 erected on MLP #1. |
30 Dec 1967 |
Saturn S-IVB stage #503 delivered to KSC. |
30 Dec 1967 |
Saturn V instrument unit #503 delivered to KSC. |
04 Jan 1968 |
BP-30 delivered to KSC. |
06 Jan 1968 |
Lunar test article B delivered to KSC. |
09 Jan 1968 |
Lunar test article B mated to spacecraft/LM adapter. |
19 Jan 1968 |
Saturn S-II stage #3 erected. |
31 Jan 1968 |
Saturn S-IVB stage #503 erected. |
01 Feb 1968 |
Saturn V instrument unit #503 erected. |
01 Feb 1968 |
Boilerplate payload (BP-30) and summary launch escape system erected. |
05 Feb 1968 |
Launch vehicle electrically mated. |
12 Feb 1968 |
Space vehicle overall test #1 completed (for unmanned mission). |
11 Mar 1968 |
Space vehicle pull test completed (for unmanned mission). |
25 Mar 1968 |
Space vehicle overall test #2 completed (for unmanned mission). |
08 Apr 1968 |
Decision made to de-erect boilerplate payload (BP-30) for service propulsion system skirt modifications. |
10 Apr 1968 |
C mission changed to C prime mission. |
27 Apr 1968 |
Spacecraft/LM adapter #11, instrument unit #503 and Saturn S-IVB stage #503 de-erected. |
28 Apr 1968 |
Saturn S-II stage #3 de-erected. |
29 Apr 1968 |
Saturn S-II stage #3 departed for Mississippi Test Facility for man-rating tests. |
01 May 1968 |
Individual and combined CM and SM systems test completed at factory. |
02 Jun 1968 |
LM descent stage #3 delivered to KSC. |
09 Jun 1968 |
LM ascent stage #3 delivered to KSC. |
14 Jun 1968 |
Saturn S-II stage #3 delivered to KSC from Mississippi Test Facility. |
27 Jun 1968 |
Integrated CM and SM systems test completed at factory. |
21 Jul 1968 |
Saturn S-II stage #3 re-erected. |
24 Jul 1968 |
CSM #103 quads delivered to KSC. |
06 Aug 1968 |
CM #103 and SM #103 ready to ship from factory to KSC. |
11 Aug 1968 |
Service module #103 delivered to KSC. |
11 Aug 1968 |
CM #103 delivered to KSC. |
12 Aug 1968 |
Saturn S-IVB stage #503 erected. |
14 Aug 1968 |
Saturn V instrument unit #503 erected. |
15 Aug 1968 |
Facility verification vehicle erected. |
16 Aug 1968 |
AS-503 designated Apollo 8. Decision made to replace LM with spacecraft/LM adapter and lunar test article B. |
19 Aug 1968 |
CM #103 and SM #103 mated. |
22 Aug 1968 |
Launch vehicle electrical systems test completed. |
23 Aug 1968 |
CSM #103 combined systems test completed. |
05 Sep 1968 |
Facility verification vehicle de-erected. |
14 Sep 1968 |
BP-30 erected for service arm checkout. |
15 Sep 1968 |
Spacecraft/LM adapter #11 delivered to KSC. |
18 Sep 1968 |
CSM #103 altitude tests completed. |
22 Sep 1968 |
Lunar test article B mated with spacecraft/LM adapter. |
29 Sep 1968 |
Service arm overall test completed. |
02 Oct 1968 |
BP-30 de-erected. |
04 Oct 1968 |
CSM #103 moved to VAB |
07 Oct 1968 |
Space vehicle and MLP #1 transferred to launch complex 39A. |
09 Oct 1968 |
Mobile service structure transferred to launch complex 39A. |
12 Oct 1968 |
Space vehicle cutoff and malfunction test completed. |
22 Oct 1968 |
CSM #103/Mission Control Center Houston test completed. |
29 Oct 1968 |
CSM #103 integrated systems test completed. |
02 Nov 1968 |
CSM #103 electrically mated to launch vehicle. |
04 Nov 1968 |
Space vehicle electrically mated. |
05 Nov 1968 |
Space vehicle overall test completed. |
06 Nov 1968 |
Space vehicle overall test #1 (plugs in) completed. |
07 Nov 1968 |
Launch vehicle/Mission Control Center Houston test completed. |
11 Nov 1968 |
Launch umbilical tower/pad water system test completed. |
12 Nov 1968 |
Space vehicle flight readiness test completed. |
19 Nov 1968 |
Space vehicle hypergolic fuel loading completed. |
30 Nov 1968 |
Saturn S-IC stage #3 RP-1 fuel loading completed. |
02 Dec 1968 |
Space vehicle countdown demonstration test (wet) completed. |
10 Dec 1968 |
Space vehicle countdown demonstration test (dry) completed. |
11 Dec 1968 |