Apollo 10 Spacecraft History
Event |
Date |
LM #4 integrated test at factory. |
25 May 1968 |
Individual and combined CM and SM systems test completed at factory. |
08 Sep 1968 |
LM #4 final engineering evaluation acceptance test at factory. |
02 Oct 1968 |
LM descent stage #4 ready to ship from factory to KSC. |
09 Oct 1968 |
LM descent stage #4 delivered to KSC. |
11 Oct 1968 |
LM ascent stage #4 ready to ship from factory to KSC. |
12 Oct 1968 |
LM ascent stage #4 delivered to KSC. |
16 Oct 1968 |
Integrated CM and SM systems test completed at factory. |
19 Oct 1968 |
LM ascent stage #4 and descent stage #4 mated. |
02 Nov 1968 |
LM #4 combined systems test completed. |
06 Nov 1968 |
CM #106 and SM #106 delivered to KSC. |
23 Nov 1968 |
CM #106 and SM #106 ready to ship from factory to KSC. |
24 Nov 1968 |
CM #106 and SM #106 mated. |
26 Nov 1968 |
Saturn S-IC stage #5 delivered to KSC. |
27 Nov 1968 |
Saturn S-II stage #5 delivered to KSC. |
03 Dec 1968 |
Saturn S-IVB stage #505 delivered to KSC. |
03 Dec 1968 |
LM #4 altitude tests completed. |
06 Dec 1968 |
Saturn V instrument unit #505 delivered to KSC. |
15 Dec 1968 |
CSM #106 combined systems test completed. |
16 Dec 1968 |
Launch vehicle erected. |
30 Dec 1968 |
CSM #106 altitude tests completed. |
17 Jan 1969 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
03 Feb 1969 |
CSM #106 moved to VAB |
06 Feb 1969 |
Spacecraft erected. |
06 Feb 1969 |
LM #4 combined systems test completed. |
10 Feb 1969 |
CSM #106 integrated systems test completed. |
13 Feb 1969 |
CSM #106 electrically mated to launch vehicle. |
27 Feb 1969 |
Space vehicle overall test completed. |
03 Mar 1969 |
Space vehicle overall test #1 (plugs in) completed. |
05 Apr 1969 |
Space vehicle and MLP #3 transferred to launch complex 39B. |
11 May 1969 |
LM #4 flight readiness test completed. |
27 Jun 1969 |
Emergency egress test completed. |
28 Jul 1969 |
Space vehicle flight readiness test completed. |
19 Apr 1969 |
Space vehicle hypergolic fuel loading completed. |
25 Apr 1969 |
Saturn S-IC stage #5 RP-1 fuel loading completed. |
02 May 1969 |
Space vehicle countdown demonstration test (wet) completed. |
05 May 1969 |
Space vehicle countdown demonstration test (dry) completed. |
06 May 1969 |