Apollo 10 Spacecraft History

Apollo 10 Spacecraft History

 

Event

Date

LM #4 integrated test at factory.

25 May 1968

Individual and combined CM and SM systems test completed at factory.

08 Sep 1968

LM #4 final engineering evaluation acceptance test at factory.

02 Oct 1968

LM descent stage #4 ready to ship from factory to KSC.

09 Oct 1968

LM descent stage #4 delivered to KSC.

11 Oct 1968

LM ascent stage #4 ready to ship from factory to KSC.

12 Oct 1968

LM ascent stage #4 delivered to KSC.

16 Oct 1968

Integrated CM and SM systems test completed at factory.

19 Oct 1968

LM ascent stage #4 and descent stage #4 mated.

02 Nov 1968

LM #4 combined systems test completed.

06 Nov 1968

CM #106 and SM #106 delivered to KSC.

23 Nov 1968

CM #106 and SM #106 ready to ship from factory to KSC.

24 Nov 1968

CM #106 and SM #106 mated.

26 Nov 1968

Saturn S-IC stage #5 delivered to KSC.

27 Nov 1968

Saturn S-II stage #5 delivered to KSC.

03 Dec 1968

Saturn S-IVB stage #505 delivered to KSC.

03 Dec 1968

LM #4 altitude tests completed.

06 Dec 1968

Saturn V instrument unit #505 delivered to KSC.

15 Dec 1968

CSM #106 combined systems test completed.

16 Dec 1968

Launch vehicle erected.

30 Dec 1968

CSM #106 altitude tests completed.

17 Jan 1969

Launch vehicle propellant dispersion/malfunction overall test completed.

03 Feb 1969

CSM #106 moved to VAB

06 Feb 1969

Spacecraft erected.

06 Feb 1969

LM #4 combined systems test completed.

10 Feb 1969

CSM #106 integrated systems test completed.

13 Feb 1969

CSM #106 electrically mated to launch vehicle.

27 Feb 1969

Space vehicle overall test completed.

03 Mar 1969

Space vehicle overall test #1 (plugs in) completed.

05 Apr 1969

Space vehicle and MLP #3 transferred to launch complex 39B.

11 May 1969

LM #4 flight readiness test completed.

27 Jun 1969

Emergency egress test completed.

28 Jul 1969

Space vehicle flight readiness test completed.

19 Apr 1969

Space vehicle hypergolic fuel loading completed.

25 Apr 1969

Saturn S-IC stage #5 RP-1 fuel loading completed.

02 May 1969

Space vehicle countdown demonstration test (wet) completed.

05 May 1969

Space vehicle countdown demonstration test (dry) completed.

06 May 1969

 