Apollo 11 Spacecraft History
Event |
Date |
Individual and combined CM and SM systems test completed at factory. |
12 Oct 1968 |
LM #5 integrated test at factory. |
21 Oct 1968 |
Integrated CM and SM systems test completed at factory. |
06 Dec 1968 |
LM #5 final engineering evaluation acceptance test at factory. |
13 Dec 1968 |
LM ascent stage #5 ready to ship from factory to KSC. |
07 Jan 1969 |
LM ascent stage #5 delivered to KSC. |
08 Jan 1969 |
Spacecraft/LM adapter #14 delivered to KSC. |
10 Jan 1969 |
LM descent stage #5 ready to ship from factory to KSC. |
11 Jan 1969 |
LM descent stage #5 delivered to KSC. |
12 Jan 1969 |
CSM #107 quads delivered to KSC. |
15 Jan 1969 |
Saturn S-IVB stage #506 delivered to KSC. |
18 Jan 1969 |
Saturn S-IVB stage #506 delivered to KSC. |
19 Jan 1969 |
CM #107 and SM #107 ready to ship from factory to KSC. |
22 Jan 1969 |
CM #107 and SM #107 delivered to KSC. |
23 Jan 1969 |
CM #107 and SM #107 mated. |
29 Jan 1969 |
Saturn S-II stage #6 delivered to KSC. |
06 Feb 1969 |
LM ascent stage #5 and descent stage #5 mated. |
14 Feb 1969 |
CSM #107 combined systems test completed. |
17 Feb 1969 |
LM #5 combined systems test completed. |
17 Feb 1969 |
Saturn S-IC stage #6 delivered to KSC. |
20 Feb 1969 |
Saturn S-IC stage #6 erected. |
21 Feb 1969 |
Saturn V instrument unit #506 delivered to KSC. |
27 Feb 1969 |
Saturn S-II stage #6 erected. |
04 Mar 1969 |
Saturn S-IVB stage #506 erected. |
05 Mar 1969 |
Saturn V instrument unit #506 erected. |
05 Mar 1969 |
CSM #107 altitude test with prime crew completed. |
18 Mar 1969 |
LM #5 altitude test with prime crew completed. |
21 Mar 1969 |
CSM #107 altitude tests completed. |
24 Mar 1969 |
LM #5 altitude tests completed. |
25 Mar 1969 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
27 Mar 1969 |
CSM #107 moved to VAB |
14 Apr 1969 |
Spacecraft erected. |
14 Apr 1969 |
LM #5 combined systems test completed. |
18 Apr 1969 |
CSM #107 integrated systems test completed. |
22 Apr 1969 |
CSM #107 electrically mated to launch vehicle. |
05 May 1969 |
Space vehicle overall test completed. |
06 May 1969 |
Space vehicle overall test #1 (plugs in) completed. |
14 May 1969 |
Space vehicle and MLP #1 transferred to launch complex 39A. |
20 May 1969 |
Mobile service structure transferred to launch complex 39A. |
22 May 1969 |
LM #4 flight readiness test completed. |
02 Jun 1969 |
Space vehicle flight readiness test completed. |
06 Jun 1969 |
Saturn S-IC stage #6 RP-1 fuel loading completed. |
25 Jun 1969 |
Space vehicle countdown demonstration test (wet) completed. |
02 Jul 1969 |
Space vehicle countdown demonstration test (dry) completed. |
03 Jul 1969 |