Apollo 11 Spacecraft History

Apollo 11 Spacecraft History

 

Event

Date

Individual and combined CM and SM systems test completed at factory.

12 Oct 1968

LM #5 integrated test at factory.

21 Oct 1968

Integrated CM and SM systems test completed at factory.

06 Dec 1968

LM #5 final engineering evaluation acceptance test at factory.

13 Dec 1968

LM ascent stage #5 ready to ship from factory to KSC.

07 Jan 1969

LM ascent stage #5 delivered to KSC.

08 Jan 1969

Spacecraft/LM adapter #14 delivered to KSC.

10 Jan 1969

LM descent stage #5 ready to ship from factory to KSC.

11 Jan 1969

LM descent stage #5 delivered to KSC.

12 Jan 1969

CSM #107 quads delivered to KSC.

15 Jan 1969

Saturn S-IVB stage #506 delivered to KSC.

18 Jan 1969

Saturn S-IVB stage #506 delivered to KSC.

19 Jan 1969

CM #107 and SM #107 ready to ship from factory to KSC.

22 Jan 1969

CM #107 and SM #107 delivered to KSC.

23 Jan 1969

CM #107 and SM #107 mated.

29 Jan 1969

Saturn S-II stage #6 delivered to KSC.

06 Feb 1969

LM ascent stage #5 and descent stage #5 mated.

14 Feb 1969

CSM #107 combined systems test completed.

17 Feb 1969

LM #5 combined systems test completed.

17 Feb 1969

Saturn S-IC stage #6 delivered to KSC.

20 Feb 1969

Saturn S-IC stage #6 erected.

21 Feb 1969

Saturn V instrument unit #506 delivered to KSC.

27 Feb 1969

Saturn S-II stage #6 erected.

04 Mar 1969

Saturn S-IVB stage #506 erected.

05 Mar 1969

Saturn V instrument unit #506 erected.

05 Mar 1969

CSM #107 altitude test with prime crew completed.

18 Mar 1969

LM #5 altitude test with prime crew completed.

21 Mar 1969

CSM #107 altitude tests completed.

24 Mar 1969

LM #5 altitude tests completed.

25 Mar 1969

Launch vehicle propellant dispersion/malfunction overall test completed.

27 Mar 1969

CSM #107 moved to VAB

14 Apr 1969

Spacecraft erected.

14 Apr 1969

LM #5 combined systems test completed.

18 Apr 1969

CSM #107 integrated systems test completed.

22 Apr 1969

CSM #107 electrically mated to launch vehicle.

05 May 1969

Space vehicle overall test completed.

06 May 1969

Space vehicle overall test #1 (plugs in) completed.

14 May 1969

Space vehicle and MLP #1 transferred to launch complex 39A.

20 May 1969

Mobile service structure transferred to launch complex 39A.

22 May 1969

LM #4 flight readiness test completed.

02 Jun 1969

Space vehicle flight readiness test completed.

06 Jun 1969

Saturn S-IC stage #6 RP-1 fuel loading completed.

25 Jun 1969

Space vehicle countdown demonstration test (wet) completed.

02 Jul 1969

Space vehicle countdown demonstration test (dry) completed.

03 Jul 1969

 