Apollo 12 Spacecraft History
Event |
Date |
LM #6 integrated test at factory. |
31 Dec 1968 |
Individual and combined CM and SM systems test completed at factory. |
20 Jan 1969 |
Integrated CM and SM systems test completed at factory. |
03 Feb 1969 |
LM #6 final engineering evaluation acceptance test at factory. |
18 Feb 1969 |
Saturn S-IVB stage #507 delivered to KSC. |
10 Mar 1969 |
LM descent stage #6 ready to ship from factory to KSC. |
22 Mar 1969 |
LM ascent stage #6 ready to ship from factory to KSC. |
23 Mar 1969 |
LM ascent stage #6 and LM descent stage #6 delivered to KSC. |
24 Mar 1969 |
CM #108 and SM #108 ready to ship from factory to KSC. |
27 Mar 1969 |
CM #108 and SM #108 delivered to KSC. |
28 Mar 1969 |
CM #108 and SM #108 mated. |
02 Apr 1969 |
CSM #108 combined systems test completed. |
21 Apr 1969 |
Saturn S-II stage #7 delivered to KSC. |
21 Apr 1969 |
LM ascent stage #6 and descent stage #6 mated. |
28 Apr 1969 |
LM #6 combined systems test completed. |
01 May 1969 |
Saturn S-IC stage #7 delivered to KSC. |
03 May 1969 |
Spacecraft/LM adapter #15 delivered to KSC. |
06 May 1969 |
Saturn S-IC stage #7 erected on MLP #2. |
07 May 1969 |
Saturn V instrument unit #507 delivered to KSC. |
08 May 1969 |
Saturn S-II stage #7 erected. |
21 May 1969 |
Saturn S-IVB stage #507 and Saturn V instrument unit #107 erected. |
22 May 1969 |
CSM #108 altitude test with prime crew completed. |
07 Jun 1969 |
CSM #108 altitude tests completed. |
09 Jun 1969 |
CSM #108 altitude test with backup crew completed. |
10 Jun 1969 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
12 Jun 1969 |
LM #6 altitude test with backup crew completed. |
13 Jun 1969 |
LM #6 altitude test with prime crew completed. |
16 Jun 1969 |
Spacecraft moved to VAB. |
20 Jun 1969 |
LM #6 landing gear installed. |
22 Jun 1969 |
LM #6 mated to spacecraft/LM adapter #15. |
23 Jun 1969 |
CSM #108 mated to spacecraft/LM adapter #15. |
27 Jun 1969 |
CSM #108 moved to VAB |
30 Jun 1969 |
Spacecraft erected. |
01 Jul 1969 |
LM #6 combined systems test completed. |
05 Jul 1969 |
CSM #108 integrated systems test completed. |
07 Jul 1969 |
CSM #108 electrically mated to launch vehicle. |
16 Jul 1969 |
Space vehicle overall test completed. |
17 Jul 1969 |
Space vehicle electrically mated. |
17 Aug 1969 |
Space vehicle overall test #1 (plugs in) completed. |
21 Aug 1969 |
Space vehicle and MLP #2 transferred to launch complex 39A. |
08 Sep 1969 |
Mobile service structure transferred to launch complex 39A. |
10 Sep 1969 |
LM #5 flight readiness test completed. |
18 Sep 1969 |
Space vehicle flight readiness test completed. |
30 Sep 1969 |
Saturn S-IC stage #7 RP-1 fuel loading completed. |
20 Oct 1969 |
Space vehicle countdown demonstration test (wet) completed. |
28 Oct 1969 |
Space vehicle countdown demonstration test (dry) completed. |
29 Oct 1969 |