Apollo 13 Spacecraft History
Event |
Date |
Individual and combined CM and SM systems test completed at factory. |
16 Mar 1969 |
Integrated CM and SM systems test completed at factory. |
08 Apr 1969 |
LM #7 final engineering evaluation acceptance test at factory. |
18 May 1969 |
LM #7 integrated test at factory. |
18 May 1969 |
Saturn S-IVB stage #508 delivered to KSC. |
13 Jun 1969 |
Saturn S-IC stage #8 delivered to KSC. |
16 Jun 1969 |
Saturn S-IC stage #8 erected on MLP #3. |
18 Jun 1969 |
LM ascent stage #7 ready to ship from factory to KSC. |
24 Jun 1969 |
CM #109 and SM #109 ready to ship from factory to KSC. |
25 Jun 1969 |
LM descent stage #7 ready to ship from factory to KSC. |
25 Jun 1969 |
CM #109 and SM #109 delivered to KSC. |
26 Jun 1969 |
LM ascent stage #7 delivered to KSC. |
27 Jun 1969 |
LM descent stage #7 delivered to KSC. |
28 Jun 1969 |
Saturn S-II stage #8 delivered to KSC. |
29 Jun 1969 |
CM #109 and SM #109 mated. |
30 Jun 1969 |
CSM #109 combined systems test completed. |
07 Jul 1969 |
Saturn V instrument unit #508 delivered to KSC. |
07 Jul 1969 |
LM ascent stage #7 and descent stage #7 mated. |
15 Jul 1969 |
Saturn S-II stage #8 erected. |
17 Jul 1969 |
Spacecraft/LM adapter #16 delivered to KSC. |
18 Jul 1969 |
LM #7 combined systems test completed. |
22 Jul 1969 |
Saturn S-IVB stage #508 erected. |
31 Jul 1969 |
Saturn V instrument unit #508 erected. |
01 Aug 1969 |
Launch vehicle electrical systems test completed. |
29 Aug 1969 |
CSM #109 altitude tests completed. |
12 Sep 1969 |
LM #7 altitude tests completed. |
20 Sep 1969 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
21 Oct 1969 |
Launch vehicle service arm overall test completed. |
04 Dec 1969 |
CSM #109 moved to VAB |
09 Dec 1969 |
Spacecraft erected. |
10 Dec 1969 |
Space vehicle and MLP #3 transferred to launch complex 39A. |
15 Dec 1969 |
CSM #109 integrated systems test completed. |
05 Jan 1970 |
LM #7 combined systems test completed. |
05 Jan 1970 |
CSM #109 electrically mated to launch vehicle. |
18 Jan 1970 |
Space vehicle overall test #1 (plugs in) completed. |
20 Jan 1970 |
LM #6 flight readiness test completed. |
24 Feb 1970 |
Space vehicle flight readiness test completed. |
26 Feb 1970 |
Saturn S-IC stage #8 RP-1 fuel loading completed. |
16 Mar 1970 |
Space vehicle countdown demonstration test (wet) completed. |
25 Mar 1970 |
Space vehicle countdown demonstration test (dry) completed. |
26 Mar 1970 |