Apollo 14 Spacecraft History
Event |
Date |
Individual and combined CM and SM systems test completed at factory. |
02 Apr 1969 |
Integrated CM and SM systems test completed at factory. |
07 May 1969 |
LM #8 final engineering evaluation acceptance test at factory. |
25 Aug 1969 |
LM #8 integrated test at factory. |
25 Aug 1969 |
LM ascent stage #8 ready to ship from factory to KSC. |
08 Nov 1969 |
LM descent stage #8 ready to ship from factory to KSC. |
13 Nov 1969 |
CM #110 and SM #110 ready to ship from factory to KSC. |
17 Nov 1969 |
CM #110 and SM #110 delivered to KSC. |
19 Nov 1969 |
CM #110 and SM #110 mated. |
24 Nov 1969 |
LM ascent stage #8 delivered to KSC. |
24 Nov 1969 |
LM descent stage #8 delivered to KSC. |
24 Nov 1969 |
Saturn S-IC stage #9 delivered to KSC. |
11 Jan 1970 |
Saturn S-IC stage #9 erected on MLP #2 |
14 Jan 1970 |
LM ascent stage #8 and descent stage #8 mated. |
20 Jan 1970 |
Saturn S-IVB stage #509 delivered to KSC. |
20 Jan 1970 |
Saturn S-II stage #9 delivered to KSC. |
21 Jan 1970 |
LM #8 combined systems test completed. |
22 Jan 1970 |
CSM #110 combined systems test completed. |
02 Feb 1970 |
Spacecraft/LM adapter #17 delivered to KSC. |
31 Mar 1970 |
Saturn V instrument unit #509 delivered to KSC. |
06 May 1970 |
Saturn S-II stage #9 erected. |
12 May 1970 |
Saturn S-IVB stage #509 erected. |
13 May 1970 |
Saturn V instrument unit #509 erected. |
14 May 1970 |
Launch vehicle electrical systems test completed. |
04 Jun 1970 |
LM #8 altitude tests completed. |
22 Jun 1970 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
07 Jul 1970 |
CSM #110 altitude tests completed. |
01 Sep 1970 |
Launch vehicle service arm overall test completed. |
21 Oct 1970 |
CSM #110 moved to VAB |
04 Nov 1970 |
Spacecraft erected. |
04 Nov 1970 |
Space vehicle and MLP #2 transferred to launch complex 39A. |
09 Nov 1970 |
LM #8 combined systems test completed. |
16 Nov 1970 |
CSM #110 integrated systems test completed. |
18 Nov 1970 |
CSM #110 electrically mated to launch vehicle. |
13 Dec 1970 |
LM #7 flight readiness test completed. |
14 Dec 1970 |
Space vehicle overall test #1 (plugs in) completed. |
14 Dec 1970 |
Space vehicle flight readiness test completed. |
19 Dec 1970 |
Saturn S-IC stage #9 RP-1 fuel loading completed. |
08 Jan 1971 |
Space vehicle countdown demonstration test (wet) completed. |
18 Jan 1971 |
Space vehicle countdown demonstration test (dry) completed. |
19 Jan 1971 |