Apollo 15 Spacecraft History
Event |
Date |
Individual and combined CM and SM systems test completed at factory. |
|
Saturn S-II stage #10 delivered to KSC. |
18 May 1970 |
Saturn S-IVB stage #510 delivered to KSC. |
|
Saturn V instrument unit #510 delivered to KSC. |
|
Saturn S-IC stage #10 delivered to KSC. |
|
Saturn S-IC stage #10 erected on MLP #3. |
|
Spacecraft/LM adapter #19 delivered to KSC. |
|
Saturn S-II stage #10 erected. |
|
Saturn S-IVB stage #510 erected. |
|
Saturn V instrument unit #510 erected. |
|
LM #10 final engineering evaluation acceptance test at factory. |
|
LM #10 integrated test at factory. |
|
LM #10 delivered to KSC and launch electrical systems tests completed. |
|
Launch vehicle electrical systems tests completed. |
17 Nov 1970 |
Integrated CM and SM systems test completed at factory. |
24 Nov 1970 |
CM #112 and SM #112 ready to ship from factory to KSC. |
11 Jan 1971 |
CM #112 and SM #112 delivered to KSC. |
14 Jan 1971 |
CM #112 and SM #112 mated. |
18 Jan 1971 |
LM ascent stage #10 and descent stage #10 mated. |
09 Feb 1971 |
LM #10 combined systems test completed. |
12 Feb 1971 |
CSM #112 combined systems test completed. |
08 Mar 1971 |
LRV #1 delivered to KSC. |
15 Mar 1971 |
LM #10 altitude tests completed. |
06 Apr 1971 |
CSM #112 altitude tests completed. |
09 Apr 1971 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
15 Apr 1971 |
Launch vehicle service arm overall test completed. |
27 Apr 1971 |
LRV #1 installed. |
28 Apr 1971 |
CSM #112 moved to VAB |
08 May 1971 |
Spacecraft erected. |
08 May 1971 |
Space vehicle and MLP #3 transferred to launch complex 39A. |
11 May 1971 |
LM #10 combined systems test completed. |
17 May 1971 |
CSM #112 integrated systems test completed. |
18 May 1971 |
CSM #112 electrically mated to launch vehicle. |
07 Jun 1971 |
Space vehicle overall test #1 (plugs in) completed. |
09 Jun 1971 |
LM #8 flight readiness test completed. |
10 Jun 1971 |
Space vehicle flight readiness test completed. |
22 Jun 1971 |
Saturn S-IC stage #10 RP-1 fuel loading completed. |
06 Jul 1971 |
Space vehicle countdown demonstration test (wet) completed. |
13 Jul 1971 |
Space vehicle countdown demonstration test (dry) completed. |
14 Jul 1971 |