Apollo 17 Spacecraft History
Event |
Date |
Saturn S-II stage #12 delivered to KSC. |
27 Oct 1970 |
Saturn S-IVB stage #512 delivered to KSC. |
21 Dec 1970 |
Individual and combined CM and SM systems test completed at factory. |
08 May 1971 |
LM #12 final engineering evaluation acceptance test at factory. |
23 May 1971 |
LM #12 integrated test at factory. |
23 May 1971 |
LM ascent stage #12 ready to ship from factory to KSC. |
14 Jun 1971 |
LM descent stage #12 ready to ship from factory to KSC. |
14 Jun 1971 |
LM ascent stage #12 delivered to KSC. |
16 Jun 1971 |
LM descent stage #12 delivered to KSC. |
17 Jun 1971 |
Integrated CM and SM systems test completed at factory. |
02 Aug 1971 |
CM #114 and SM #114 ready to ship from factory to KSC. |
17 Mar 1972 |
CM #114 and SM #114 delivered to KSC. |
24 Mar 1972 |
Spacecraft/LM adapter #21 delivered to KSC. |
24 Mar 1972 |
CM #114 and SM #114 mated. |
28 Mar 1972 |
CSM #114 combined systems test completed. |
09 May 1972 |
Saturn S-IC stage #12 delivered to KSC. |
11 May 1972 |
Saturn S-IC stage #12 erected on MLP #3. |
15 May 1972 |
LM ascent stage #12 and descent stage #12 mated. |
18 May 1972 |
Saturn S-II stage #12 erected. |
19 May 1972 |
LRV #3 delivered to KSC. |
02 Jun 1972 |
LM #12 combined systems test completed. |
07 Jun 1972 |
Saturn S-IVB instrument unit #512 delivered to KSC. |
07 Jun 1972 |
CSM #114 altitude tests completed. |
19 Jun 1972 |
Saturn S-IVB instrument unit #512 erected. |
20 Jun 1972 |
Saturn S-IVB stage #512 erected. |
23 Jun 1972 |
Launch vehicle electrical systems test completed. |
12 Jul 1972 |
LM #12 altitude tests completed. |
25 Jul 1972 |
Launch vehicle propellant dispersion/malfunction overall test completed. |
01 Aug 1972 |
Launch vehicle service arm overall test completed. |
11 Aug 1972 |
LRV #3 installed. |
13 Aug 1972 |
CSM #114 moved to VAB |
22 Aug 1972 |
Spacecraft erected. |
23 Aug 1972 |
Spacecraft moved to VAB. |
24 Aug 1972 |
Space vehicle and MLP #3 transferred to launch complex 39A. |
28 Aug 1972 |
LM #12 combined systems test completed. |
06 Sep 1972 |
CSM #114 integrated systems test completed. |
11 Sep 1972 |
LM #10 flight readiness test completed. |
04 Oct 1972 |
CSM #114 electrically mated to launch vehicle. |
11 Oct 1972 |
Space vehicle overall test #1 (plugs in) completed. |
12 Oct 1972 |
Space vehicle overall test completed. |
17 Oct 1972 |
Space vehicle flight readiness test completed. |
20 Oct 1972 |
Saturn S-IC stage #12 RP-1 loading completed. |
10 Nov 1972 |
Space vehicle countdown demonstration test (wet) completed. |
20 Nov 1972 |
Space vehicle countdown demonstration test (dry) completed. |
21 Nov 1972 |