Part 2 (B)
Developing Hardware Distinctions
October 1963 through December 1963
1963
October
1963
November
1963
December
October 2
At a LEM Mechanical Systems Meeting in Houston, Grumman and
MSC agreed upon a preliminary configuration freeze for the LEM-adapter
arrangement. The adapter would be a truncated cone, 876 centimeters (345 inches)
long. The LEM would be mounted inside the adapter by means of the outrigger
trusses on the spacecraft's landing gear. This configuration provided ample
clearance for the spacecraft, both top and bottom (i.e., between the service
propulsion engine bell and the instrument unit of the S-IVB). (See June 3 and
December 5.)
At this same meeting, Grumman presented a comparison of radially and
laterally folded landing gears (both of 457-centimeter [180-inch] radius). The
radial-fold configuration, MSC reported, promised a weight savings of 22-2
kilograms (49 pounds). MSC approved the concept, with an 876-centimeter
(345-inch) adapter. Further, an adapter of that length would accommodate a
larger, lateral fold gear (508 centimeters [200 inches]), if necessary. During
the next several weeks, Grumman studied a variety of gear arrangements (sizes,
means of deployment, stability, and even a "bending" gear). At a subsequent LEM
Mechanical Systems Meeting, on November 10, Grumman presented data (design,
performance, and weight) on several other four-legged gear arrangements - a
457-centimeter (180-inch), radial fold "tripod" gear (i.e., attached to the
vehicle by three struts), and 406.4-centimeter (160-inch) and 457-centimeter
(180-inch) cantilevered gears. As it turned out, the 406.4-centimeter (160-inch)
cantilevered gear, while still meeting requirements demanded in the work
statement, in several respects was more stable than the larger tripod gear. In
addition to being considerably lighter, the cantilevered design offered several
added advantages:
- A reduced stowed height for the LEM from 336.5 to 313.7 centimeters (132.5
to 123.5 inches).
- A shorter landing stroke (50.8 instead of 101.6 centimeters) (20 instead
of 40 inches).
- Better protection from irregularities (protuberances) on the surface.
- An alleviation of the gear heating problem (caused by the descent engine's
exhaust plume).
- Simpler locking mechanisms.
- A better capability to handle various load patterns on the landing
pads.
Because of these significant (and persuasive) factors, MSC
approved Grumman's change to the 406.4- centimeter (160-inch) cantilevered
arrangement as the design for the LEM's landing gear. By mid- November, MSC
reported to OMSF that Grumman was pursuing the 406.4-centimeter (160-inch)
cantilevered gear. Although analyses would not be completed for some weeks, the
design was "shown . . . to be the lightest gear available to date. . . .
Tentative estimates indicate a gear stowed height reduction of about 9" [22.9
centimeters], which will still accommodate the 180" [45.7 centimeter] cantilever
or 200" [508-centimeter] lateral fold gear as growth potential." Grumman's
effort continued at "firming up" the design, including folding and docking
mechanisms.
GAEC, "Monthly Progress Report No. 9," LPR-10-25, November 10, 1963, pp. 3,
12; MSC, "ASPO Weekly Activity Report, September 26-October 2, 1963," p. 15;
"ASPO Monthly Activity Report, September 19-October 16, 1963," p. 5; MSC,
"Weekly-Activity Report for the Office of the Director, Manned Space Flight,
September 8-14, 1963," pp. 10-II; "Weekly Activity Report for the Office of the
Director, Manned Space Flight, November 17-23, 1963," pp. 9-10; MSC,
"Consolidated Activity Report for the Office of the Director, Manned Space
Flight, October 20-November 16, 1963," p. 36; "Apollo Quarterly Status Report
No. 6,"p. 27; "ASPO Status Report for Period Ending October 16, 1963"; "ASPO
Weekly Status Report, November 12-19, 1963"; "Monthly Progress Report No. 7,"
LPR-10-22, p. 10; "Monthly Progress Report No. 8," LPR-10-24, p. 11; GAEC,
"Monthly Progress Report No. 10," LPR-10-26, December 10, 1963, p. 10; GAEC,
"Monthly Progress Report No. 11," LPR-10-27, January 10, 1964, p. 11.
October 8
NASA announced the appointment of Joseph F. Shea as ASPO
Manager effective October 22. He had been Deputy Director (Systems) in OMSF.
George M. Low, OMSF Deputy Director (Programs), would direct the Systems office
as well as his own. Robert O. Piland, Acting Manager of ASPO since April 3,
resumed his former duties as Deputy Manager.
NASA News Release 63-226, "Shea to Head Apollo Spacecraft Development at
Manned Spacecraft Center," October 8, 1963; MSC News Release 63-163, October 8,
1963; MSC Announcement No. 263, "Manager, Apollo Spacecraft Program Office,"
October 22, 1963.
October 8
Verne C. Fryklund, Jr., of NASA's Office of Space Sciences
(OSS), in a memorandum to MSC Director Robert R. Gilruth, recommended some
general guidelines for Apollo scientific investigations of the moon (which OSS
already was using). "These guidelines," Fryklund told Gilruth, ". . . should be
followed in the preparation of your plans," and thus were "intended to place
some specific constraints on studies. . . . The primary scientific objective of
the Apollo project," Fryklund said, was, of course, the "acquisition of
comprehensive data about the moon." With this as a starting point, he went on,
". . . it follows that the structure of the moon's surface, gross body
properties and large-scale measurements of physical and chemical
characteristics, and observation of whatever phenomena may occur at the actual
surface will be the prime scientific objectives." Basically, OSS's guidelines
spelled out what types of activity were and were not part of Apollo's immediate
goals. These activities were presumed to be mostly reconnaissance, "to acquire
knowledge of as large an area as possible, and by as simple a means as possible,
in the limited time available." The three principal scientific activities
"listed in order of decreasing importance" were: (1) "comprehensive observation
of lunar phenomena," (2) "collection of representative samples," and (3)
"emplacement of monitoring equipment."
These guidelines had been arrived at after extensive consultation within NASA
as a whole as well as with the scientific community.
Memorandum, Verne C. Fryklund, Jr., NASA Office of Space Sciences (OSS), to
Director, MSC, "Scientific Guidelines for the Apollo Project," October 8, 1963;
OSS, "NASA Program Planning in Space Sciences," September 1963, pp. VI-3 through
VI-8.
October 8
At MSC, the Spacecraft Technology Division reported to ASPO
the results of a study on tethered docking of the LEM and CSM. The technology
people found that a cable did not reduce the impact velocities below those that
a pilot could achieve during free flyaround, nor was fuel consumption reduced.
In fact, when direct control of the spacecraft was attempted, the tether proved
a hindrance and actually increased the amount of fuel required.
MSC, "Flight Crew Operations Division, Activity Report, September 16-October
21, 1963," pp. 2-3.
October 9
NASA Administrator James E. Webb announced a major
reorganization of NASA Headquarters, effective November 1, to consolidate
management of major programs and direction of research and development centers
and to realign Headquarters management of agency-wide support functions. On
October 28, NASA Headquarters announced a similar reorganization within OMSF,
also to take effect on November I, to strengthen NASA Headquarters' control of
the agency's manned space flight programs. In effect, these administrative
adjustments "recombined program and institutional management by placing the
field centers under the Headquarters program directors instead of under general
management (i.e., the Associate Administrator)."
NASA News Release 63-225, "NASA Announces Reorganization," October 9, 1963;
NASA News Release 63-241, "NASA Realigns Office of Manned Space Flight," October
28, 1963; Rosholt, Administrative History of NASA, 1958-1963, pp.
289-96.
October 10
LTV announced the results of tests performed by astronauts in
the Manned Space Flight Mission Simulator in Dallas, Tex. (See May 6 and
September 17, 1963, and April 24, 1964.) These indicated that, should the
primary guidance and navigation system fail, LEM pilots could rendezvous with
the CM by using a circular slide rule to process LEM radar data.
Tulsa Daily World, October 11, 1963; The Houston
Post, October 11, 1963.
October 14
Langley Research Center's Lunar Landing Research Facility was
nearing completion. A gantry structure 121.9 meters (400 feet) long and 76.2
meters (250 feet) high would suspend a model of the LEM. It would sustain
five-sixths of the model's weight, simulating lunar gravity, and thus would
enable astronauts to practice lunar landings. (See Volume I, Summer 1961.)
Aviation Week and Space Technology, 79 (October 14, 1963), pp.
83, 86; MSC, Space News Roundup, November 27, 1963, p. 8.
October 14
ASPO established criteria for combustion stability in the
service propulsion engine. The engine had to recover from any instability,
whether induced or spontaneous, within 20 milliseconds during qualification
testing.
MSC, "ASPO Monthly Activity Report, September 19-October 16, 1963," p. 3.
October 15
The Guidance and Performance Sub-Panel, at its first meeting,
began coordinating work at MSC and MSFC. The sub-panel outlined tasks for eac
Center: MSFC would define the dispersions comprising the launch vehicle
performance reserves, prepare a set of typical translunar injection errors for
the Saturn V launch vehicle, and give MSC a typical Saturn V guidance
computation for injection into an earth parking orbit. MSC would identify the
constraints required for free-return trajectories and provide MSFC with details
of the MIT guidance method. Further, the two Centers would exchange data each
month showing current launch vehicle and spacecraft performance capability. (For
operational vehicles, studies of other than performance capability would be
based on control weights and would not reflect the current weight status.)
Memorandum, Secretaries, Guidance and Performance Sub-Panel, MSFC and MSC, to
Distr., "Minutes of First Guidance and Performance Sub-Panel Meeting," October
16, 1963.
October 16-17
MSC discussed commonality of displays and controls with
its two principal spacecraft contractors. A review of panel components suggested
that Grumman might use the same vendors as North American for such items as
switches, potentiometers, and indicators.
MSC, "ASPO Activity Report, October 16-22, 1963," pp. 1-2.
October 16-23
An MSC Spacecraft Technology Division Working Group
reexamined Apollo mission requirements and suggested a number of ways to reduce
spacecraft weight: eliminate the free-return trajectory; design for slower
return times; use the Hohmann descent technique, rather than the equal period
orbit method, yet size the tanks for the equal period mode; eliminate the
CSM/LEM dual rendezvous capability; reduce the orbital contingency time for the
LEM (the period of time during which the LEM could remain in orbit before
rendezvousing with the CSM); reduce the LEM lifetime.
MSC, "ASPO Status Report for Period Ending October 23, 1963."
October 16-November 15
Because of an electrical equipment failure on
Mercury MA-9, North American began a CM humidity study. The company found in the
crew compartment major spacecraft systems which were not designed for operation
in the presence of corrosive moisture. (The environmental control system did not
guarantee complete humidity control.) Investigators also examined in minute
detail all electrical electronic components. North American was considering
design changes that would protect all components from moisture.
"Apollo Monthly Progress Report," SID 62-300-19, p. 25.
October 18
NASA and GD/C negotiated amendments totaling $354,737 to
Little Joe II contract. This sum covered study activity and several relatively
small changes that came out of a Design Engineering Inspection on May 3. More
ground support equipment was authorized, as was fabrication of an additional
breadboard autopilot system for use at MSC. The dummy payload was deleted and
the instrumentation was limited to a control system on the vehicle to be used
for Mission A-002 (BP-23).
Little Joe II Test Launch Vehicle, NASA Project Apollo: Final
Report, Vol. I, p. 4-3.
October 18
NASA Headquarters announced the selection of five
organizations for contract negotiations totaling $60 million for the
development, fabrication, and testing of LEM guidance and navigation equipment:
(1) MIT, overall direction; (2) Raytheon, LEM guidance computer; (3) AC Spark
Plug, inertial measurement unit, gyroscopes, navigation base, power and servo
assembly, coupling display unit, and assembly and testing of the complete
guidance and navigation system; (4) Kollsman Instrument Corporation, scanning
telescope, sextant, and map and data viewer; and (5) Sperry Gyroscope Company,
accelerometers. (All five had responsibility for similar equipment for the CSM
as well. See Vol. I, August 9, 1961, and May 8, 1962.)
MSC News Release 63-175, October 18, 1963.
October 18
NASA announced the selection of 14 astronauts for Projects
Gemini and Apollo, bringing to 30 the total number of American spacemen. They
were Maj. Edwin E. Aldrin, Jr., Capt. William A. Anders, Capt. Charles A.
Bassett II, Capt. Michael Collins, Capt. Donn F. Eisele, Capt. Theodore C.
Freeman, and Capt. David R. Scott of the Air Force; Lt. Cdr. Richard F. Gordon,
Jr., Lt. Alan L. Bean, Lt. Eugene A. Cernan, and Lt. Roger B. Chaffee of the
Navy; Capt. Clifton C. Williams, Jr., of the Marine Corps; R. Walter Cunningham,
research scientist for the Rand Corporation; and Russell L. Schweickart,
research scientist for MIT.
MSC News Release 63-180, October 18, 1963; Space News Roundup,
October 30, 1963.
October 20-November 16
MSC reported that preliminary testing had begun
on the first prototype extravehicular suit telemetry and communications system
and on the portable life support system of which it was an integral part. The
hardware had recently been received from the prime contractor, Hamilton
Standard.
MSC, "Consolidated Activity Report for the Office of the Director, Manned
Space Flight, October 20- November 16, 1963," p. 67.
October 21
The second prototype space suit was received by MSC's Crew
Systems Division. (See August 15-September 21.) Preliminary tests showed little
improvement in mobility over the first suit. On October 24-25, a space suit
mobility demonstration was held at North American. The results showed that the
suit had less shoulder mobility than the earlier version, but more lower limb
mobility. (See September 26-27.) Astronaut John W. Young, wearing the
pressurized suit and a mockup portable life support system (PLSS), attempted an
egress through the CM hatch but encountered considerable difficulty. At the same
time, tests of the suit-couch- restraint system interfaces and control display
layout were begun at the Navy's Aviation Medical Acceleration Laboratory
centrifuge in Johnsville, Pa. Major problems were restriction of downward vision
by the helmet, extension of the suit elbow arm beyond the couch, and awkward
reach patterns to the lower part of the control panel. On October 30-November 1,
lunar task studies with the suit were carried out at Wright-Patterson Air Force
Base in a KC-135 aircraft at simulated lunar gravity. Mobility tests were made
with the suit pressurized and a PLSS attached.
"Apollo Quarterly Status Report No. 6," p. 25; MSC, "Weekly Activity Report
for the Office of the Director, Manned Space Flight, October 27-November 2,
1963," p. 6; MSC, "ASPO Status Report for Week Ending November 6, 1963;" "ASPO
Status Report for Period Ending October 23, 1963;" "ASPO Status Report for
Period October 16-November 12, 1963."
October 22
George E. Mueller, NASA Associate Administrator for Manned
Space Flight, appointed Walter C. Williams Deputy Associate Administrator for
Manned Space Flight in OMSF. Williams would direct operations at MSC, MSFC, and
LOC for all manned space flight missions.
MSC News Release 63-179, October 22, 1963.
October 23
MSC Flight Operations Division defined systems and outlined
ground rules for the lunar landing mission. System definitions were: (1)
primary, most efficient or economic; (2) alternate, either redundant (identical
to but independent of the primary) or backup (not identical but would perform
the same function); (3) critical (failure would jeopardize crew safety); (4)
repairable (for which tools and spares were carried and which the crew could
service in flight); and (5) operational, which must be working to carry out a
mission.
Mission rules established crew safety as the major consideration in all
mission decisions and detailed actions to be taken in the event of a failure in
any system or subsystem.
Memorandum, Eugene L. Duret, MSC, to Chief, Flight Operations Div., "Project
Apollo, operational ground rules for the Lunar Landing Mission," October 23,
1963, with enclosure.
October 23-30
MSC Instrumentation and Electronic Systems Division
awarded a $50,000 contract to the Hughes Aircraft Company for a study of backup
high gain directable antennas for the LEM lunar surface equipment.
MSC," ASPO Status Report for Week Ending October 30, 1963."
October 24
Because OMSF had requested OSSA to provide lunar surface
microrelief and bearing strength data to support LEM landing site selection and
to permit LEM landing-gear design validation, the Ad Hoc Working Group on
Follow-On Surveyor Instrumentation met at NASA Headquarters. Attending were
Chairman Verne C. Fryklund, Clark Goodman, Martin Swetnick, and Paul Brockman of
the NASA Office of Space Sciences and Applications; Harry Hess and George
Derbyshire of the National Acadamy of Sciences; Dennis James of Bellcomm (for
OMSF); and Milton Beilock of the Jet Propulsion Laboratory (JPL). The group
proposed "a fresh look at the problem of instrumenting payloads of Surveyor
spacecraft that may follow the currently approved developmental and operational
flights, so that these spacecraft will be able to determine that a particular
lunar site is suitable for an Apollo landing." The study was assigned to JPL.
Summary Minutes," Ad Hoc Working Group on Follow-On Surveyor Instrumentation,
October 24, 1963," October 28, 1963, pp. 1-2.
October 24
The NASA-Industry Apollo Executives Group, composed of top
managers in OMSF and executives of the major Apollo contractors, met for the
first time. The group met with George E. Mueller, NASA Associate Administrator
for Manned Space Flight, for status briefings and problem discussions. In this
manner, NASA sought to make executives personally aware of major problems in the
program.
Tenth Semiannual Report to Congress of the National Aeronautics and
Space Administration, July 1-December 31, 1963 (1964), p. 43.
October 25
MSC directed Grumman to schedule manned environmental control
system (ECS) development tests, using a welded-shell cabin boilerplate and air
lock. At about the same time, the company was also requested to quote cost and
delivery schedule for a second boilerplate vessel, complete with prototype ECS.
Although this vessel would be used by the MSC Crew Systems Division for in-house
investigation and evaluation of ECS development problems, its major purpose was
to serve as a tool for trouble-shooting during the operational phase.
MSC, "Weekly Activity Report for the Office of the Director, Manned Space
Flight, October 27-November 2, 1963," p. 11; MSC," ASPO Status Report for Period
October 16-November 12, 1963."
October 29
After a program review at an MSF Management Council meeting,
George E. Mueller, head of OMSF, suggested several testing procedures. To meet
schedules, "dead-end" testing, that is, "tests involving components or systems
that [would] not fly operationally without major modification," should be
minimized. Henceforth, Mueller said, NASA would concentrate on "all-up" testing.
[In"all-up" testing, the complete spacecraft and launch vehicle configuration
would be used on each flight. Previously, NASA plans had called for a gradual
buildup of subsystems, systems stages, and modules in successive flight tests.]
To simplify both testing and checkout at Cape Canaveral, complete systems should
be delivered. An instrumentation task force with senior representatives from
each Center, one outside member, and Walter C. Williams of OMSF should be set up
immediately; a second task force, to study storable fuels and small motors,
would include members from Lewis Research Center, MSC, MSFC, as well as
representatives from outside the government.
Memorandum, Clyde Bothmer, MSF Management Council, for Distribution,
"Management Council Meeting, October 29, 1963, in Washington, D.C.," October 31,
1963.
October 30
NASA canceled four manned earth orbital flights with the
Saturn I launch vehicle. Six of a series of 10 unmanned Saturn I development
flights were still scheduled. Development of the Saturn IB for manned flight
would be accelerated and "all-up" testing would be started. (See November 1.)
This action followed Bellcomm's recommendation of a number of changes in the
Apollo spacecraft flight test program. The program should be transferred from
Saturn I to Saturn IB launch vehicles; the Saturn I program should end with
flight SA-10. All Saturn IB flights, beginning with SA-201, should carry
operational spacecraft, including equipment for extensive testing of the
spacecraft systems in earth orbit.
Associate Administrator for Manned Space Flight George E. Mueller had
recommended the changeover from the Saturn I to the Saturn IB to NASA
Administrator James E. Webb on October 26. Webb's concurrence came two days
later.
Memoranda: Mueller to Robert F. Freitag, "Replacement of Scheduled Manned
Flights on Saturn I," October 18, 1963; Mueller to Webb, "Reorientation of
Apollo Plans," October 26, 1963, with handwritten notation signed by Webb,
undated; OMSF, Recommended Changes in the Use of Space Vehicles in the
Apollo Test Program, Technical Memorandum, MD(S) 3100.180 (October 29,
1963), pp. 1-4; NASA News Release 63-246, "NASA Announces Changes in Saturn
Missions," October 30, 1963.
October 31
The Marquardt Corporation received a definitive $9,353,200
contract from North American for development and production of reaction control
engines for the SM. Marquardt, working under a letter contract since April 1962,
had delivered the first engine to North American that November.
MSC News Release 63-22, October 31, 1963; MSC, Space News
Roundup, November 13, 1963, p. 8.
October 31
The first production F-1 engine was flown from Rocketdyne's
Canoga Park, Calif., facility, where it was manufactured, to MSFC aboard Aero
Spacelines' "Pregnant Guppy."
David S. Akens, A. Ruth Jarrell, and Leo L. Jones, History of the
George C. Marshall Space Flight Center From July 1 Through December 31,
1963 (MHM-8, July 1964), Vol. I, p. 129.
Theoretical optimum lunar module descent with thrust-to-weight ration
(initial value in lunar orbit) at 0.3, height at perilune of the transfer orbit
at 15,200 meters (50,000 feet), and using the Hohmann transfer technique. The
diagram showed the velocity change (delta Vc, in feet per second) and approach
flight-path angle (gamma) close to that for an impulsive orbital change (an
instantaneous change, without time value, taken as the ultimate though
unachievable ideal for comparison). (NASA drawing)
During the Month
NASA tentatively approved Project Luster, a program
designed to capture lunar dust deflected from the moon by meteorites and spun
into orbit around the earth. An Aerobee 150 sounding rocket containing
scientific equipment built by Electro-Optical Systems, Inc., was scheduled for
launch in late 1964.
Missiles and Rockets, 13 (October 14, 1963), p. 9.
NASA Associate Administrator for Manned
Space Flight George E. Mueller notified the Directors of MSC, MSFC, and LOC that
he intended to plan a flight schedule which would have a good chance of being
met or exceeded. To this end, he directed that "all-up" spacecraft and launch
vehicle tests be started as soon as possible; all Saturn IB flights would carry
CSM and CSM LEM configurations; and two successful unmanned flights would be
flown before a manned mission on either the Saturn IB or Saturn V.
On November 18, Mueller further defined the flight schedule planning. Early
Saturn IB flights might not be able to include the LEM, but every effort must be
made to phase the LEM into the picture as early as possible. Launch vehicle
payload capability must be reached as quickly as practicable. Subsystems for the
early flights should be the same as those intended for lunar missions. To
conserve funds, the first Saturn V vehicle would be used to obtain reentry data
early in the Saturn test program.
- By December 31 the official schedule showed:
- Final Saturn I flight (SA-10):
- June 1965
- First Saturn IB flight (SA-201):
- first quarter, 1966
- First manned Saturn IB flight:
- either SA-203, third quarter of 1966, or SA-207, third quarter of 1967
- First Saturn V flight (SA-501):
- first quarter, 1967
- First manned Saturn V flight:
- either SA-503, third quarter of 1967, or SA-507, second quarter of
1968.
TWX, Mueller to Dir., MSC, MSFC, and LOC, "Revised Manned Space
Flight Schedule," November 1, 1963; memorandum, Mueller to Dir., MSC, MSFC, and
LOC, "Manned Space Flight Schedule," November 18, 1963; "Apollo Quarterly Status
Report No. 6," fig. 9, 10, 11.
November 1
MSC Flight Operations Division outlined the advantages
inherent in the CSM's capability to use the HF transceiver during earth orbit.
The HF transceiver would allow the CSM to communicate with any one tracking
station at any time during earth orbit, even when the spacecraft had
line-of-sight (LOS) contact with only one or two ground stations in some orbits.
It would give the astronauts an additional communications circuit. Most
important, this HF capability could alert the network about any trouble in the
spacecraft and give the Flight Director more time to make a decision while the
spacecraft was out of LOS communication with the ground stations.
Memorandum, Christopher C. Kraft, Jr., MSC, to Mgr., ASPO, "Apollo HF
communications during earth orbit," November 1, 1963.
November 8
MSC Crew Systems Division, conducting flammability tests on
the constant wear garment material in a 3.5 newtons per square centimeter (5
psi), 100 percent oxygen atmosphere, reported that no fires had been experienced
thus far.
MSC, "Weekly Activity Report for the Office of the Director, Manned Space
Flight, November 3-9, 1963," p. 7.
November 5
MSC Director Robert R. Gilruth announced a reorganization of
MSC to strengthen the management of the Apollo and Gemini programs. Under
Gilruth and Deputy Director James C. Elms, there were now four Assistant
Directors, Managers for both the Gemini and Apollo programs, and a Manager for
MSC's Florida Operations. Assigned to these positions were:
Maxime A. Faget, Assistant Director for Engineering and Development
Christopher C. Kraft, Jr., Assistant Director for Flight Operations Donald K.
Slayton, Assistant Director for Flight Crew Operations Wesley L. Hjornevik,
Assistant Director for Administration Joseph F. Shea, Manager, Apollo Spacecraft
Program Office Charles W. Mathews, Manager, Gemini Program Office and G. Merritt
Preston, Manager, MSC Florida Operations.
MSC News Release 63-277, November 5, 1963; The Houston Post,
November 6, 1963.
November 5
MSC accepted the final items of a $237,000 vibration test
system from the LTV Electronics Division to be used in testing spacecraft parts.
On this same day, MSC awarded a $183,152 contract to Wyle Laboratories to
construct a high-intensity acoustic facility, also for testing spacecraft parts.
The facility would generate noise that might be encountered in space flight.
MSC News Release 63-224, November 5, 1963; MSC News Release 63-225, November
5, 1963.
November 5
North American presented to MSC the results of a three-month
study on radiation instrumentation. Three general areas were covered:
radio-frequency (RF) warning systems, directional instrumentation, and external
environment instrumentation. The company concluded that, with the use of an RE
system, astronauts would receive about two hours' notice of any impending solar
proton event and could take appropriate action. Proper orientation of the
spacecraft could reduce doses by 17 percent, but this could be accomplished only
by using a directional detection instrument. There was a 70 percent chance that
dosages would exceed safe limits unless such an instrument was used.
Consequently North American recommended prompt development.
Despite the contractor's findings, MSC concluded that there was no need for
an RE warning system aboard the spacecraft, believing that radiation warning
could be handled more effectively by ground systems. But MSC did concur in the
recommendation for a combined proton direction and external environment
detection system and authorized North American to proceed with its design and
development.
MSC," ASPO Status Report for Period October 16-November 12, 1963";
memorandum, David M. Hammock and Lee N. McMillion, MSC, to E. E. Sack, NAA,
"Contract NAS 9-150, Radiation Instrumentation for Apollo," November 27, 1963;
"Apollo Monthly Progress Report," SID 62-300-20, pp. 12-13.
November 7
Apollo Pad Abort Mission I (PA-1), the first off-the-pad
abort test of the launch escape system (LES), was conducted at WSMR. PA-1 used
CM boilerplate 6 and an LES for this test.
All sequencing was normal. The tower-jettison motor sent the escape tower
into a proper ballistic trajectory. The drogue parachute deployed as programmed,
followed by the pilot parachute and main parachutes. The test lasted 165.1
seconds. The postflight investigation disclosed only one significant problem:
exhaust impingement that resulted in soot deposits on the CM.
"Postlaunch Memorandum Report for Apollo Pad Abort I," November 13, 1963, pp.
1-1, 1-2, 3-1.
November 8
Grumman issued a go-ahead to RCA to develop the LEM radar.
Negotiations on the $23.461 million cost- plus-fixed-fee contract were completed
on December 10. Areas yet to be negotiated between the two companies were LEM
communications, inflight test, ground support, and parts of the stabilization
and control systems. (See June 28.)
MSC, "Consolidated Activity Report for the Office of the Director, Manned
Space Flight, October 20- November 16, 1963," p. 57; Wall Street
Journal, December 10, 1963.
November 8
MSFC directed Rocketdyne to develop an uprated H-1 engine to
be used in the first stage of the Saturn IB. In August, Rocketdyne had proposed
that the H-1 be uprated from 85,275 to 90,718 kilograms (188,000 to 200,000
pounds) of thrust. The uprated engine promised a 907-kilogram (2,000 pound)
increase in the Saturn IB's orbital payload, yet required no major systems
changes and only minor structural modifications.
Akens et al., History of Marshall . . . July 1-December
31, 1963, Vol. I, pp. 65, 66.
November 8
At El Centro, Calif., a drop test was conducted to evaluate a
dual drogue parachute arrangement for the CM. The two drogues functioned
satisfactorily. The cargo parachute used for recovery, however, failed to fully
inflate, and the vehicle was damaged at impact. This failure was unrelated to
the test objectives.
MSC," ASPO Status Report for Period October 16-November 12, 1963."
November 12
A joint North American-MSC meeting reviewed the tower flap
versus canard concept for the earth landing system (ELS). (See January 18.)
During a low-altitude abort, MSC thought, the ELS could be deployed apex forward
with a very high probability of mission success by using the tower flap
configuration. The parachute system proposed for this mode would be very
reliable, even though this was not the most desirable position for deploying
parachutes. Dynamic stability of the tower flap configuration during high-
altitude aborts required further wind tunnel testing at Ames Research Center.
Two basic unknowns in the canard system were deployment reliability, and the
probability of the crew's being able to establish the flight direction and trim
the CM within its stability limits for a safe reentry. Design areas to be
resolved were a simple deployment scheme and a spacecraft system that would give
the crew a direction reference.
MSC directed North American to proceed with the tower flap as its prime
effort, and attempt to solve the stability problem at the earliest possible
date. MSC's Engineering and Development Directorate resumed its study of both
configurations, with an in-depth analysis of the canard system, in case the
stability problem on the tower flap could not be solved by the end of the year.
(See February 7 and 25, 1964.)
Memorandum, David M. Hammock, MSC, to Asst. Dir. for Engineering and
Development, "Analysis of the abort and earth landing systems if implemented by
a tower flap versus a canard mode," November 18, 1963.
November 12
The Boeing Company and NASA signed a $27.4 million
supplemental agreement to the contract for development, fabrication, and test of
the S-IC (first) stage of the Saturn V launch vehicle.
Aviation Week and Space Technology, 79 (November 25, 1963), p.
67; Akens et al., History of Marshall . . . July 1-December
31, 1963, Vol. I, p. 97.
November 12
NASA awarded a $19.2 million contract to Blount Brothers
Corporation and M. M. Sundt Construction Company for the construction of Pad A,
part of the Saturn V Launch Complex 39 at LOC.
Akens et al., History of Marshall . . . July 1-December
31, 1963, Vol. I, p. 169.
November 12-15
North American representatives reviewed Farrand Optical
Company's subcontract with Link for visual displays in the Apollo Mission
Simulator. MSC officials attended the technical portion of the meeting, which
was held at Link. Farrand and Link had established window fields of view and
optical axis orientations. Designs were to be reviewed to verify accuracy and
currency of window locations and crew eye position parameters.
MSC, "ASPO Status Report for Week Ending November 19, 1963."
November 12-19
ASPO reviewed Grumman's evaluation of series and parallel
propellant feed systems for the LEM ascent stage. Because of the complications
involved in minimizing propellant residuals in a parallel system, a series feed
appeared preferable, despite an increase in LEM structural weight. Further study
of the vehicle showed the feasibility of a two-tank configuration which would be
lighter and have about the same propellant residual as the four-tank series-feed
arrangement. (See December 17.)
"Monthly Progress Report No. 10," LPR-10-26, p. 16; MSC, "ASPO Status Report
for Week Ending November 19, 1963"; "Apollo Quarterly Status Report No. 6," p.
33.
November 13-14
After careful study, Grumman proposed to MSC 15 possible
means for reducing the weight of the LEM. These involved eliminating a number of
hardware items in the spacecraft; two propellant tanks in the vehicle's ascent
stage and consequent changes in the feed system; two rather than three fuel
cells; and reducing reaction control system propellants and, consequently,
velocity budgets for the spacecraft. If all these proposed changes were made,
Grumman advised, the LEM could be lightened significantly, perhaps by as much as
454 kilograms (1000 pounds).
MSC, "ASPO Status Report for Week Ending November 19, 1963."
November 14
ASPO revised the normal and emergency impact limits (20 and
40 g, respectively) to be used as human tolerance criteria for spacecraft
design. [These limits superseded those established in the August 14, 1963, North
American contract and subsequent correspondence.]
Memorandum, David M. Hammock, MSC, to NAA, Attn: E. E. Sack, "Contract 9-150,
Impact Acceleration Limits," November 14, 1963.
November 15
NASA and contractor studies showed that, in the event of an
engine hard-over failure during maximum q, a manual abort was impractical for
the Saturn I and IB, and must be carried out by automatic devices. Studies were
continuing to determine whether, in a similar situation, a manual abort was
possible from a Saturn V.
Memorandum, Maxime A. Faget, MSC, to ASPO, Attn: Calvin H. Perrine, "Apollo
abort mode in event of maximum 'q' engine hard-over malfunction," November 15,
1963.
November 16-December 15
All production drawings for the CM environmental
control system were released. - AiResearch Manufacturing Company reported the
most critical pacing items were the suit heat exchanger, cyclic accumulator
selector valve, and the potable and waste water tanks.
The Garrett Corporation, AiResearch Manufacturing Division, "Monthly Progress
Report, Environmental Control System, NAA/S&ID, Project Apollo, 16 November
1963-15 December 1963," SS-1013-R(19) January 2, 1964, p. 4.
November 16-December 15
North American conducted an eight-day trial of
the prototype Apollo diet. Three test subjects, who continued their normal
activities rather than being confined, were given performance and oxygen
consumption tests and lean body mass and body compartment water evaluations. The
results showed insignificant changes in weight and physiology. "Apollo Monthly
Progress Report," SID 62-300-20, p. 6.
November 17-December 21
As a result of an MSC Crew Systems
Division-Hamilton Standard meeting on the space suit, MSC directed the company
to develop a micrometeoroid protective garment to be worn over the suit. (See
August 13-20, 1964.)
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, November 17-December 21. 1963," p. 54.
November 19-20
At a meeting of the Apollo Docking Interface Panel, North
American recommended and Grumman concurred that the center probe and drogue
docking concept be adopted. (See July 16.) MSC emphasized that docking systems
must not compromise any other subsystem operations nor increase the complexity
of emergency operations. In mid-December, MSC/ASPO notified Grumman and North
American of its agreement. At the same time, ASPO laid down docking interface
ground rules and performance criteria which must be incorporated into the
spacecraft specifications.
There would be two ways for the astronauts to get from one spacecraft to the
other. The primary mode involved docking and passage through the transfer
tunnel. An emergency method entailed crew and payload transfer through free
space. The CSM would take an active part in translunar docking, but both
spacecraft must be able to take the primary role in the lunar orbit docking
maneuver. A single crewman must be able to carry out the docking maneuver and
crew transfer.
MSC," ASPO Status Report for Week Ending December 4, 1963"; "ASPO Status
Report for Week Ending December 17, 1963"; "Apollo Monthly Progress Report," SID
62-300-20, pp. 7, 8, 18; "Apollo Quarterly Status Report No. 6," pp. 3-4.
November 21
MSC approved Grumman's $19,383,822 cost-plus-fixed-fee
subcontract with Rocketdyne for the LEM descent engine development program. (See
January 30, February 13, and May 1.)
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, November 17-December 21, 1963," p. 42.
November 22
MSC's Space Environment Division (SED) recommended (subject
to reconnaissance verification) 10 lunar landing areas for the Apollo program:
- 36 degrees 55' E. 1 degree 45' N.
- 31 degrees E. 0 degrees N.
- 28 degrees 22' E. 1 degree 10' N.
- 24 degrees 10' E. 0 degrees 10' N.
- 12 degrees 50' E. 0 degrees 20' N.
- 1 degree 28'W. 0 degrees 30' S.
- 13 degrees 15' W. 2 degrees 45' N.
- 28 degrees 15' W. 2 degrees 45' N.
- 31 degrees 30' W. 1 degree 05' S.
- 41 degrees 30'W. 1 degree 10' S.
SED chose these sites on the basis
of regional slopes, surface texture and strength, landmarks, isolated features,
and the size, shape, and position of the various areas. The list included
several sites that the Division had designated earlier in the year.
NASA Project Apollo Working Paper No. 1100, "Environmental Factors Involved
in the Choice of Lunar Operational Dates and the Choice of Lunar Landing Sites"
(November 22, 1963), pp. 30-33.
November 22
ASPO developed ground rules and guidelines for the
Spacecraft Development Test Program being conducted by Grumman, North American,
and MIT Instrumentation Laboratory. (See January 3, 1964.)
NAA, "Apollo Spacecraft Development Test Plan," Study Report, SID 64-66-1,
February 3, 1964, Vol. I, pp. v, 26, 53-57.
November 27
At its Santa Susana facility, Rocketdyne conducted the first
long-duration (508 seconds) test firing of a J-2 engine. In May 1962 the J-2's
required firing time was increased from 250 to 500 seconds.
Akens et al., History of Marshall . . . July 1-December
31, 1963, Vol. I, p. 242; Missiles and Rockets, 13 (December
9, 1963), p. 10; interview, telephone, Erika Fry, Rocketdyne, February 24, 1969.
November 27
ASPO Manager Joseph F. Shea asked NASA Headquarters to
revise velocity budgets for the Apollo spacecraft. (Studies had indicated that
those budgets could be reduced without degrading performance.) He proposed that
the 10 percent safety margin applied to the original budget be eliminated in
favor of specific allowances for each identifiable uncertainty and contingency;
but, to provide for maneuvers which might be desired on later Apollo missions,
the LEM's propellant tanks should be oversized. (See December 1963.)
The ASPO Manager's proposal resulted from experience that had arisen because
of unfortunate terminology used to designate the extra fuel. Originally the fuel
budget for various phases of the mission had been analyzed and a 10 percent
allowance had been made to cover - at that time, unspecified - contingencies,
dispersions, and uncertainties. Mistakenly this fuel addition became known as a
"10% reserve"! John P. Mayer and his men in the Mission Planning and Analysis
Division worried because engineers at North American, Grumman, and NASA had
"been freely 'eating' off the so-called 'reserve'" before studies had been
completed to define what some of the contingencies might be and to apportion
some fuel for that specific situation. Mayer wanted the item labeled a "10%
uncertainty."
Shea recommended also that the capacity of the LEM descent tanks be
sufficient to achieve an equiperiod orbit, should this become desirable.
However, the spacecraft should carry only enough propellant for a Hohmann
transfer. This was believed adequate, because the ascent engine was available
for abort maneuvers if the descent engine failed and because a low altitude pass
over the landing site was no longer considered necessary. By restricting lunar
landing sites to the area between ±5 degrees latitude and by limiting the lunar
stay time to less than 48 hours, a one-half-degree, rather than two-degree,
plane change was sufficient.
In the meantime, Shea reported, his office was investigating how much weight
could be saved by these propellant reductions.
Memorandum, Shea to NASA Headquarters, Attn: Mgr., Apollo Program Office,
"Revised Apollo Spacecraft Delta-V Budget," November 27, 1963; memorandum,
Christopher C. Kraft, Jr., MSC, to Mgr., ASPO, "Use of 10% 'reserve' delta-V in
CSM and LEM delta-V Budgets," October 21, 1963.
November 28
In honor of the late President John F. Kennedy, who was
assassinated six days earlier, President Lyndon B. Johnson announced that LOC
and Station No. 1 of the Atlantic Missile Range would be designated the John F.
Kennedy Space Center (KSC), ". . . to honor his memory, and the future of the
works he started . . . ," Johnson said. On the following day, he signed an
executive order making this change official. With the concurrence of Florida
Governor Farris Bryant, he also changed the name of Cape Canaveral to Cape
Kennedy.
Angela C. Gresser, "Historical Aspects Concerning the Redesignation of
Facilities at Cape Canaveral," KHN-1, April 1964, p. 15; The New York
Times, November 29, 1963; The Houston Chronicle, November
30, 1963.
November 28-December 4
MSC reviewed a North American proposal for adding
an active thermal control system to the SM to maintain satisfactory temperatures
in the propulsion and reaction control engines. The company's scheme involved
two water-glycol heat transport loops with appropriate nuclear heaters and
radiators. During December, MSC directed North American to begin preliminary
design of a system for earth orbit only. Approval for spacecraft intended for
lunar missions was deferred pending a comprehensive review of requirements.
MSC, "ASPO Status Report for Week Ending December 4, 1963"; "Apollo Quarterly
Status Report No. 6," p, 15.
November 29
After a meeting with Grumman officials on November 27, ASPO
directed the contractor to begin a Grumman-directed Apollo mission plan
development study. (See January 16, 1964.)
TWX, Owen E. Maynard, MSC, to GAEC, Attn: R. S. Mullaney, November 29, 1963.
During the Month
MSC directed Grumman to halt work on LEM test article
9, pending determination of its status as a tethered flight vehicle. (See August
1963.) As a result, the proposed flight demonstration of the tether coupler,
using an S-64A Skycrane helicopter, was canceled.
"Monthly Progress Report No. 10," LPR-10-26, p. 37.
During the Month
Ames Research Center performed simulated meteoroid
impact tests on the Avco Corporation heatshield structure. Four targets of
ablator bonded to a stainless steel backup structure were tested. The ablator,
in a Fiberglas honeycomb matrix, was 4.369 millimeters (0.172 inch) thick in two
targets and 17.424 millimeters (0.686 inch) thick in the other two. Each ablator
was tested at 116.48 K (-250 degrees F) and at room temperature, with no
apparent difference in damage.
Penetration of the thicker targets was about 13.970 millimeters (0.55 inch).
In the thinner targets, the ablator was pierced. Debris tore through the steel
honeycomb and produced pinholes on the rear steel sheet. Damage to the ablator
was confined to two or three honeycomb cells and there was no cracking or
spalling on the surface.
Tests at Ames of thermal performance of the ablation material under high
shear stress yielded favorable preliminary results. MSC," ASPO Status Report for
Week Ending December 4, 1963."
During the Month
Verne C. Fryklund of NASA's Manned Space Sciences
Division advised Bellcomm of the procedure for determining Apollo landing sites
on the moon. The Manned Space Sciences chief outlined an elimination for the
site selection process. For the first step, extant selenographic material would
be used to pick targets of interest for Lunar Orbiter spacecraft photography.
After study of the Lunar Orbiter photography, a narrower choice of targets then
became the object of Surveyor spacecraft lunar missions, with final choice of
potential landing sites to be made after the Surveyor program. (See December
20.)
The selection criteria at all stages were determined by lunar surface
requirements prepared by OMSF. Fryklund emphasized that a landing at the least
hazardous spot, rather than in the area with the most scientific interest, was
the chief aim of the site selection process.
Memorandum, Verne C. Fryklund, NASA Manned Space Sciences Division, to B. T.
Howard, Bellcomm, "Your memorandum of October 31, 1963 about Apollo Landing
Sites," November 4, 1963.
Grumman selected AiResearch Manufacturing
Company to supply cryogenic storage tanks for the LEM electrical power system.
Final negotiations on the cost-plus-incentive-fee contract were held in June
1964.
On this same date, Grumman concluded negotiations with Allison Division of
General Motors Corporation for design and fabrication of the LEM descent engine
propellant storage tanks (at a cost of $5,479,560).
"Apollo Quarterly Status Report No. 6," pp. 30, 32; MSC, "Project Apollo
Quarterly Status Report No.8 for Period Ending June 30, 1964," p.38; MSC,
"Consolidated Activity Report for the Office of the Associate Administrator,
Manned Space Flight, November 17-December 21, 1963," p. 42.
December 3-5
A design review of the CSM part-task trainer was held at
North American. Briefings included general design criteria and requirements,
physical configuration, simulation models, and scheduling. The trainer was
expected to be operational in December 1964.
"Apollo Monthly Progress Report," SID 62-300-20, pp. 20-21; MSC, "ASPO Status
Report for Week Ending December 10, 1963."
December 5
Primarily to save weight, the length of the adapter was
shortened to 853 centimeters (336 inches), as recommended by Grumman. (See
October 2.)
Letter, Owen E. Maynard, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS
9-1100, Line Items 1 and 6, Implementation of Actions Recommended in Apollo
Program Systems Meetings," December 5, 1963; TWX, David M. Hammock and Maynard,
MSC, to GAEC, Attn: Mullaney, and NAA, Attn: E. E. Sack, December 5, 1963.
December 9
ASPO requested that Grumman make a layout for transmittal to
MSFC showing space required in the S-IVB instrument unit for 406.4- and
457-centimeter (160- and 180-inch) cantilevered gears and for 508-centimeter
(200-inch)-radius lateral fold gears. (See October 2.)
Letter, Owen E, Maynard, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS
9-1100, Implementation of Actions in MSC-MSFC Mechanical Integration Panel,"
December 9, 1963.
December 10-17
As a result of wind tunnel tests, Langley Research Center
researchers found the LEM Little Joe II configuration to be aerodynamically
unstable. To achieve stability, larger booster fins were needed. However, bigger
fins caused more drag, shortening the length of the flight. MSC was
investigating the possibility of using more powerful rocket engines to overcome
this performance degradation. (See February 10, 1964.)
"Monthly Progress Report No. 11," LPR-10-27, p. 42; MSC, "ASPO Status Report
for Week Ending December 17, 1963."
December 10-17
The MSC Operations Planning Division (OPD) reviewed the
operational demands upon the CM from the time of CM-SM separation until
splashdown. OPD concluded that the CM should be designed to operate for 45
minutes during this phase of the mission.
MSC," ASPO Status Report for Week Ending December 17, 1963."
December 11
NASA Headquarters approved a $48,064,658 supplement to the
Douglas Aircraft Company, Inc., contract for 10 additional S-IVB stages, four
for the Saturn IB and six for the Saturn V missions.
Akens et al., History of Marshall . . . July 1-December
31, 1963, Vol. I, p. 69.
December 13
NASA canceled five Ranger flights (numbers 10 through 14)
designed to take high-resolution photographs of the lunar surface before impact.
[Five Rangers had thus far been launched.] OSS Associate Administrator Homer E.
Newell stated that NASA would depend on the remaining four Rangers, the Lunar
Orbiters, and the Surveyors for information about the lunar surface.
Cancellation of the flights promised to save $90 million.
NASA News Release 63-276, "NASA Cancels Five Follow-On Rangers," December 13,
1963.
December 15
The Ad Hoc Working Group on Apollo Experiments submitted its
final recommendations on what should be Apollo's principal scientific
objectives:
- Examination of the physical and geological properties of the moon in the
area surrounding the spacecraft.
- Geological mapping.
- Investigations of the moon's interior.
- Studies of the lunar atmosphere.
- Radio astronomy from the surface.
This group, which had as its
chairman Charles P. Sonett of NASA's Ames Research Center and thus was known as
the Sonett Committee, had been formed wholly within NASA for just this purpose.
Much of the Sonett Committee's report already was contained in the Office of
Space Sciences' guidelines transmitted earlier to MSC (see October 8); their
reception was not what one could call enthusiastic.
"Final Report of the Ad Hoc Working Group on Apollo Experiments and Training
on the Scientific Aspects of the Apollo Program," December 15, 1963, p. 4;
letter, Willis B. Foster, to Associate Administrator for Manned Space Flight,
"Apollo Scientific Guidelines," December 19, 1963.
December 16
MSC and the U.S. Air Force Aerospace Medical Division
completed a joint manned environmental experiment at Brooks Air Force Base, Tex.
After spending a week in a sea-level atmospheric environment, the test subjects
breathed 100 percent oxygen at 3.5 newtons per square centimeter (5 psi) at a
simulated altitude of 8,230 meters (27,000 feet) for 30 days. They then
reentered the test capsule for observation in a sea-level environment for the
next five days. This experiment demonstrated that men could live in a 100
percent oxygen environment under these conditions with no apparent ill effects.
MSC, "Consolidated Activity Report for the Office of the Director, Manned
Space Flight, October 20-November 16, 1963," p. 63; The Houston
Chronicle, November 4, 1963; Missiles and Rockets, 13
(November 11, 1963), p. 31; The Evening Star, Washington, December
17, 1963.
December 16
To ensure MSC's use of its manpower resources to the fullest
extent possible, the Engineering and Development Directorate (EDD) assigned a
subsystem manager to each of the major subsystems in the Apollo program. EDD
provided such support as was needed for him to carry out his assignment
effectively. These subsystem managers were responsible to ASPO for the
development of systems within the cost and schedule constraints of the program.
Primary duties were management of contractor efforts and testing.
MSC, "Apollo Subsystem Management Plan," December 16, 1963.
December 16
General Dynamics Corporation announced the receipt of a
contract (worth about $4 million) from the Philco Corporation for fabrication of
the computer display equipment for the Integrated Mission Control Center at MSC.
Wall Street Journal, December 16, 1963.
December 16
ASPO concurred in Grumman's recommendation to delete the
redundant gimbal actuation system in the LEM's descent engine. A nonredundant
configuration would normally require mission abort in case of actuator failure.
Consequently, in making this change, Grumman must ensure that mission abort and
the associated staging operation would not compromise crew survival and mission
reliability.
Letter, Owen E. Maynard, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS
9-1100, Item 2, Descent Engine Gimbal Drive Actuator," December 16, 1963.
December 16-January 15
Phase I of the Apollo manned centrifuge program
was completed at the U.S. Navy Aerospace Medical Acceleration Laboratory,
Philadelphia, Pa. The tests pointed up interface problems between couch, suit,
and astronaut. For example, pressurizing the suit increased the difficulty of
seeing the lower part of the instrument panel. The test fixture was disassembled
and the couch, framework, and empty instrument panel were shipped to
International Latex Corporation to serve as a mockup for further study.
"Apollo Monthly Progress Report," SID 62-300-21, p. 6.
December 16-January 15
North American completed a study to determine,
for automatic modes of reentry, adequacy of the current CM reaction control
system (RCS) and compatibility of the RCS with other reentry subsystems.
Ibid., p. 8.
December 16-January 15
MSC directed North American to redesign the CM
environmental control system compressor to provide 0.283 cubic meters (10 cubic
feet) of air per minute to each space suit at 1.8 newtons per square centimeter
(3.5 psi), 16.78 kilograms (37 pounds) per hour total.
Ibid., p. 10.
December 17
Grumman proposed a two-tank ascent stage configuration for
the LEM. (See November 12-19.) On January 17, 1964, ASPO formally concurred and
authorized Grumman to go ahead with the design. The change was expected to
reduce spacecraft weight by about 45 kilograms (100 pounds) and would make for a
simpler, more reliable ascent propulsion system. ASPO also concurred in the
selection of titanium for the two propellant tanks.
"Monthly Progress Report No. 11," LPR-10-27, p. 1; letter, William F. Rector
III, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS 9-1100, LEM Program
Review," January 17, 1964.
December 18-January 14
MSC directed North American to assign
bioinstrumentation channels to the CM for early manned flights for monitoring
the crew's pulse rate, blood pressure, respiration, and temperature. These
readings could be obtained simultaneously on any one crew member and by
switching from man to man for monitoring the entire crew.
MSC, "ASPO Status Report for Period December 18-January 14, 1964."
December 18-January 14
The System Engineering Division (SED) examined
the feasibility of performing an unmanned earth orbital mission without the
guidance and navigation system. SED concluded that the stabilization and control
system could be used as an attitude reference for one to two orbits and would
have accuracies at retrofire suitable for recovery. The number of orbits
depended upon the number of maneuvers performed by the vehicle, since the gyros
tended to drift.
Ibid.
December 19
Pratt and Whitney Aircraft delivered the first three
prototype-A fuel cells to North American.
"Apollo Monthly Progress Report," SID 62-300-21, p. 11.
December 20
MSC announced that Grumman and Hamilton Standard had signed
an $8,371,465 definitive contract for the LEM environmental control system. A
go-ahead had been issued to Hamilton Standard on July 23.
MSC News Release 63-257, December 20, 1963; The Houston Post,
December 22, 1963
December 20
NASA selected The Boeing Company to build five Lunar Orbiter
spacecraft. (See August 30.) Beginning in 1966, Lunar Orbiters would take
close-range photographs of the moon and transmit them by telemetry back to
earth. The spacecraft would also detect radiation and micrometeoroid density and
supply tracking data on the gravitational field of the moon. Information derived
from the project (managed by Langley Research Center) would aid in the selection
of lunar landing sites. (See November 1963 and May 8, 1964.)
NASA News Release 63-280, "NASA to Negotiate with Boeing for Lunar Orbiter,"
December 20, 1963.
December 20-January 18
MSC awarded the U.S. Army Corps of Engineers
contracts valued at $4,211,377 (to be subcontracted to W. S. Bellows
Construction Corporation and Peter Kiewit and Sons, Inc.) for the construction
of the MSC Mission and Training Facility and for additions to several existing
facilities at the Center.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, December 22, 1963-January 18, 1964," p. 38;
MSC News Release 64-46, March 5, 1964; The Houston Post, January 9,
1964.
December 21
MSC defined the LEM terminal rendezvous maneuvers. That
phase of the mission would begin at a range of 9.3 kilometers (five nautical
miles) from the CSM and terminate at a range of 152.4 meters (500 feet). Before
rendezvous initiation, closing velocity should be reduced to 61 meters (200
feet) per second by use of the ascent engine. The reaction control system should
be used exclusively thereafter.
Letter, Owen E. Maynard, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS
9-1100, Definition of LEM Terminal Rendezvous Model," December 21, 1963.
December 23
Motorola, Inc., received a follow-on contract from the Jet
Propulsion Laboratory for the manufacture and integration of at least three
S-band receiving subsystems for NASA's Deep Space Network and Manned Space
Flight Network ground stations. Within the unified S-band system adopted by
NASA, receiving equipment of the two networks would be identical except for a
slight difference in operating frequency. This enabled all communications
between ground stations and spacecraft to be on a single frequency. It also
allowed more efficient power transfer between the directive antennas and the
spacecraft and would greatly reduce galactic noise encountered with UHF
frequencies.
NASA News Release 63-284, "Motorola to Make S-Band Radio Receiving Equipment
for NASA Ground Stations," December 23, 1963.
December 29-January 4
Based upon centrifuge test results, MSC directed
Hamilton Standard to modify the space suit helmet. The vomitus port and other
obstructions to the line of sight in the downward direction were deleted.
MSC, "Weekly Activity Report for the Office of the Director, Manned Space
Flight, December 29, 1963-January 4, 1964," p. 4.
December 31
NASA announced the appointment of Air Force Brig. Gen.
Samuel C. Phillips as Deputy Director of the NASA Headquarters Apollo Program
Office. General Phillips assumed management of the manned lunar landing program,
working under George E. Mueller, Associate Administrator of Manned Space Flight
and Director of the Apollo Program Office.
NASA News Release 63-287, "NASA Appoints General Phillips to Assist in Apollo
Program Management," December 31, 1963.
During the Month
MSC decided to supply television cameras for the LEM as
government-furnished items. Grumman was ordered to cease its effort on this
component.
Resizing of the LEM propulsion tanks was completed by Grumman. The
cylindrical section of the descent tank was extended 34.04 millimeters (1.34
inches), for a total of 36.27 centimeters (14.28 inches) between the spherical
end bells. The ascent tanks (two-tank series) were 1240.54 centimeters (48.84
inches) in diameter.
"Monthly Progress Report No. 11," LPR-10-27, pp. 18, 30.
During the Month
RCA, contractor to Grumman for the LEM rendezvous and
landing radars, chose Ryan Aeronautical Company as vendor for the landing radar.
The contract was signed March 16, 1964.
"Apollo Quarterly Status Report No. 6," p. 34.