Part 3 (G)
Man Circles the Moon, the Eagle Lands, and Manned Lunar Exploration
1970
1970
January
1970
February
1970
March
1970
April
1970
June
1970
July
1970
August
1970
September
1970
November
January 4
NASA had canceled the Apollo 20 mission and stretched out the
remaining seven missions to six-month intervals, Deputy Administrator George M.
Low told the press in an interview after dedication of the Lunar Science
Institute (next to MSC in Houston). Budget restrictions had brought the decision
to suspend Saturn V launch vehicle production after vehicle 515 and to use the
Apollo 20 Saturn V to launch the first U.S. space station in 1972. (See also
Jan. 7.)
UPI, "Apollo Missions Extended to '74," New York Times, Jan. 5,
1970, p. 10; NASA Administrator Thomas O. Paine in NASA News Release, "NASA
Future Plans," press conference transcript, Jan. 13, 1970.
January 5-8
Detailed reports on the Apollo 11 sample
analyses were presented at the Lunar Science Conference at MSC. Principal
investigators covered the fields of geology, mineralogy, petrology, radiogenic
isotopes, inorganic and organic chemistry, solar wind and cosmic ray spallation
products, magnetic and electrical properties, physical properties, impact
metamorphism, and micropaleontology. The results added up to the greatest single
advance in the understanding of a planetary-size body attained to date.
Abstract, N. W. Hinners, Bellcomm, Case 340, "Significant Results Reported at
the Apollo 11 Lunar Science Conference," Jan. 30, 1970.
January 6
An MSC Experiments Review Group was established to consider
new or late experiments for the Apollo flights. The group would recommend MSC
policy on changes in experiments and would serve as a management clearing house.
Memo, James A. McDivitt, MSC, to distr., "Apollo Experiments Review Group,"
Jan. 6, 1970.
January 6
North American Rockwell announced a reorganization to
strengthen its operating divisions, streamline channels of communication, and
place more direct responsibility for performance with top division management.
Ltr., J. Leland Atwood, North American Rockwell Corp., to Robert R. Gilruth,
MSC, Jan. 6, 1970.
January 6
North American Rockwell declined to become a member of the
Coordinated Aerospace Supplier Evaluation (CASE) organization. North American
Rockwell stated that its Certified Special Processors system provided greater
effectiveness, that there was no real assurance that a supplier listed in the
CASE Register was capable of performing to all the requirements of the indicated
specifications, and that participants in CASE were prohibited from any exchange
of information concerning supplier inadequacies. Several processors discontinued
by North American Rockwell because of poor performance were still enjoying the
full benefit of listing in the CASE Register, with the implication of system
acceptability and certified-processor status that the listing provided.
Ltr., George W. Jeffs, North American Rockwell Corp., to Kenneth S.
Kleinknecht, MSC, Jan. 6, 1970.
January 7
NASA issued instructions for deletion of the Apollo 20 mission
from the program (see January 4). MSC was directed to take immediate action to:
- Stop work on LM-14 and determine its disposition.
- Delete requirements for the Apollo 20 spacesuits and portable and
secondary life support systems.
- Determine disposition of CSM 115A pending a final decision as to its
possible use in a second workshop mission.
- Reevaluate orbital science experiments and assignments and prepare
proposed revisions.
TWX, Rocco A. Petrone, NASA Hq., to MSC, "Apollo 20
Deletion," Jan. 7, 1970.
January 12
Dale D. Myers' appointment as NASA Associate Administrator
for Manned Space Flight was announced effective January 12, to succeed Dr.
George E. Mueller, who had joined General Dynamics Corp. in New York City as a
Vice President. Before this appointment, Myers was Vice President and General
Manager of the Space Shuttle Program, North American Rockwell Corp.
NASA News Release 70-4, Jan. 8, 1970.
January 14
The scientific debriefing of the Apollo 12
astronauts indicated there were areas of strong interest for which there was no
data and that the data could have been provided by an Apollo lunar surface
closeup stereo camera. These included three distinct kinds of soil noticed by
the astronauts, strangely patterned surface in certain areas, glazings in
craters, and fillets around certain rocks. To assist the Apollo 13 astronauts in
making scientific judgment of targets to be documented, the following
photography list was established: unexpected features, glassy features,
rock-soil junction, undisturbed surface, surface patterns, rock surface, and
craters.
Memos, Anthony J. Calio, MSC, to James A. McDivitt, MSC, "Experiment S184 on
Apollo 13, Apollo Lunar Surface Close-up Photography," Jan. 14, 1970; Richard S.
Johnston, MSC, to Lee R. Scherer, NASA Hq., "Close-up stereo camera utilization
on Apollo 13," Jan. 27, 1970.
January 16
An MSC meeting to realign the Apollo 16-19 lunar orbital
science experiments recommended that the Sounding Radar Experiment, S-167, be
deleted and the Lunar Electromagnetic Sounder, S-168, should be developed and
flown. Scientific-value for the experiments was ranked in the following
descending priorities for the various scientific disciplines: geochemistry,
particles and fields, imagery and geodesy, surface and subsurface profiles, and
atmospheres.
Minutes, Lunar Orbital Experiments Review, Jan. 16, 1970; memo, James A.
McDivitt, MSC, to Rocco A. Petrone, NASA Hq., "Lunar orbital science
experiments," Jan. 21, 1970.
January 29
Ground rules for service module design and integration,
established during recent changes in the lunar orbital science program (see
January 16), were reported. The Apollo LM experiment hardware would be installed
and tested at KSC. A single scientific instrument module configuration was being
proposed for Apollo 16-19 with modification kits developed, as required, to
install Apollo 18 and Apollo 19 experiments. An expanded Apollo LM data system
would be available for Apollo 16 (spacecraft 112).
Memo, James A. McDivitt, MSC, to Rocco A. Petrone, NASA Hq., "Apollo lunar
orbital science program," Jan. 29, 1970.
North American Rockwell completed an
investigation, requested by NASA, of the Apollo 12 flight anomalies
associated with apparent vehicle electrostatic discharges at 36.5 and 52 seconds
into the flight. The investigation indicated the most logical recommendation
consistent with cost and schedule considerations to minimize or eliminate
similar occurrences was for more restrictive launch rules. When atmospheric
conditions exhibited electrostatic gradients in excess of several thousand volts
with severe fluctuations or when heavy cloud conditions associated with frontal
passages existed even in the absence of precipitation or reported spherics
activities, delay of launch should be considered.
Ltr., George W. Jeffs, North American Rockwell Corp., to James A. McDivitt,
MSC, Feb. 5, 1970.
February 6
A statement of agreements was reached between NASA Hq. and
the Centers covering the requirements for a lunar roving vehicle (LRV).
Appropriate portions of the agreements were being incorporated in a revised
Apollo Program Specification and in Apollo Program Directive No. 4.
Memo, Rocco A. Petrone, NASA Hq., to MSFC, MSC, and KSC, "Lunar Roving
Vehicle Requirements," Feb. 6, 1970.
February 17
MSC appointed a panel to investigate a February 13 accident
at the Aerojet-General plant in Fullerton, Calif., that had damaged a lunar
module descent tank beyond repair. Panel findings were reported to a review
board later in the month, which recommended needed safety measures.
Ltr., O. G. Morris, MSC, to R. H. Tripp, Grumman, Feb. 17, 1970; memo for
record, S. H. Simpkinson, MSC, "LM descent tank incident at Aerojet-General
Corporation, California, on February 13, 1970," March 6, 1970.
In a White House release, President Nixon
listed six specific objectives for the space program: continued exploration of
the moon, exploration of the planets and the universe, substantial reductions in
the cost of space operations, extension of man's capability to live and work in
space, rapid expansion of the practical applications of space technology, and
greater international cooperation in space.
Office of the Federal Register, National Archives and Records Service,
Weekly Compilation of Presidential Documents, March 9, 1970, pp.
328-31.
March 13
Wernher von Braun was sworn in as NASA Deputy Associate
Administrator for Planning. He left MSFC on March 1 and was succeeded as MSFC
Director by Eberhard F. M. Rees.
Astronautics and Aeronautics, 1970 (NASA SP-4015, 1972), pp.
88-89.
Astronaut John L. Swigert, Jr., Apollo 13
backup command module pilot, began intensive training as a replacement for
Thomas K. Mattingly II. The Apollo 13 prime crew had undergone a comprehensive
medical examination after German measles had been contracted by Charles M. Duke,
Jr., a member of the Apollo 13 backup crew. Mattingly had not shown immunity to
the rubella virus and it was feared that he might become ill during the Apollo
13 flight.
MSC Apollo 13 Mission Report (MSC-02680), September 1970.
April 11-17
Apollo 13 (AS-508) was launched from Pad A,
Launch Complex 39, KSC, at 2:13 p.m. EST April 11, with astronauts James A.
Lovell, Jr., John L. Swigert, Jr., and Fred W. Haise, Jr., aboard. The
spacecraft and S-IVB stage entered a parking orbit with a 185.5-kilometer apogee
and a 181.5-kilometer perigee. At 3:48 p.m., onboard TV was begun for five and
one-half minutes. At 4:54 p.m., an S-IVB burn placed the spacecraft on a
translunar trajectory, after which the CSM separated from the S-IVB and LM
Aquarius. (The crew had named lunar module 7 Aquarius
and CSM 109 Odyssey.) The CSM then hard-docked with the LM. The
S-IVB auxiliary propulsion system made an evasive maneuver after CSM/LM ejection
from the S-IVB at 6:14 p.m. The docking and ejection maneuvers were televised
during a 72-minute period in which interior and exterior views of the spacecraft
were also shown.
At 8:13 p.m. EST a 217-second S-IVB auxiliary propulsion system burn aimed
the S-IVB for a lunar target point so accurately that another burn was not
required. The S-IVB/IU impacted the lunar surface at 8:10 p.m. EST on April 14
at a speed of 259 meters per second. Impact was 137.1 kilometers from the
Apollo 12 seismometer. The seismic signal generated by the impact
lasted 3 hours 20 minutes and was so strong that a ground command was necessary
to reduce seismometer gain and keep the recording on the scale. The suprathermal
ion detector experiment, also deployed by the Apollo 12 crew,
recorded a jump in the number of ions from zero at the time of impact up to
2,500 shortly thereafter and then back to a zero count. Scientists theorized
that ionization had been produced by 6,300 K to 10,300 K (6,000 degrees C to
10,000 degrees C) temperature generated by the impact or that particles had
reached an altitude of 60 kilometers from the lunar surface and had been ionized
by sunlight.
Meanwhile back in the CSM/LM, the crew had been performing the routine
housekeeping duties associated with the period of the translunar coast. At 30:40
ground elapsed time a midcourse correction maneuver took the spacecraft off a
free-return trajectory in order to control the arrival time at the moon.
Ensuring proper lighting conditions at the landing site. The maneuver placed the
spacecraft on the desired trajectory, on which the closest approach to the moon
would be 114.9 kilometers.
At 10:08 p.m. EST April 13, the crew reported an undervoltage alarm on the
CSM main bus B, rapid loss of pressure in SM oxygen tank No. 2, and dropping
current in fuel cells 1 and 3 to a zero reading. The loss of oxygen and primary
power in the service module required an immediate abort of the mission. The
astronauts powered up the LM, powered down the CSM, and used the LM systems for
power and life support. The first maneuver following the abort decision was made
with the descent propulsion system to place the spacecraft back in a free-return
trajectory around the moon. After the spacecraft swung around the moon, another
maneuver reduced the coast time back to earth and moved the landing point from
the Indian Ocean to the South Pacific.
About four hours before reentry on April 17, the service module was
jettisoned and the crew took photographs and made visual observations of the
damaged area. About one hour before splashdown the command module was powered up
and the lunar module was jettisoned. Parachutes were deployed as planned, and
the Odyssey landed in the mid-Pacific 6.4 kilometers from the
recovery ship U.S.S. Iwo Jima at 1:07 p.m. EST April 17. The
astronauts were picked up by helicopter and transported to the recovery ship
less than an hour after splashdown.
MSC "Apollo 13 Mission Report" (MSC-02680), Sept. 1970; MSC "Apollo 13
(AS-508) Flight Summary," undated; memos, C. M. Lee, NASA Hq., to distr.,
"Mission Director's Summary Report, Apollo 13," April 17, 1970; E. R. Mathews,
KSC, "Apollo 13 (AS-508) Post-Launch Report," April 24, 1970.
April 13
MSC informed NASA Hq. that the Apollo 12 ALSEP
left on the moon in November 1969 was continuing to transmit satisfactory data.
Status of experiments feeding data into the station was as follows:
The operation of the solar wind experiment was satisfactory. During the lunar
days, useful data were being received from the lunar surface magnetometer.
However, during the lunar-night cycle data were not received.
Useful data were being received from the three long-period sensors of the
passive seismometer experiment. The short period sensor was inoperative.
The cold cathode ion gauge power had failed.
Satisfactory data were being received from the suprathermal ion detector.
Ltr., James A. McDivitt, MSC, to Rocco A. Petrone, NASA Hq., "Operational
Status of Apollo 12 ALSEP," April 13, 1970.
April 13-June 15
"Hey, we've got a problem here." The message from the
Apollo 13 spacecraft to Houston ground controllers at 10:08 p.m.
EDT on April 13, initiated an investigation to determine the cause of an oxygen
tank failure that aborted the Apollo 13 mission. The investigation
terminated on June 15, when the Review Board accident report was released by
NASA at a Headquarters press conference.
The Apollo 13 Review Board was established April 17 by George M. Low, NASA
Deputy Administrator, and Thomas O. Paine, NASA Administrator, who appointed the
Director of Langley Research Center, Edgar M. Cortright, as Review Board
Chairman. On April 21 the members of the Board were named. In addition, by
separate memos of April 20, the Aerospace Safety Advisory Panel was requested to
review the procedures and findings of the Board and the Associate Administrator
for Manned Space Flight was directed to provide records, data, and technical
support as requested by the Board. The investigation indicated the accident was
caused by a combination of mistakes and a somewhat deficient design. The
following sequence of events led to the accident:
- After assembly and acceptance testing, the oxygen tank no. 2 that flew on
Apollo 13 was shipped from Beech Aircraft Corp. to North American
Rockwell (NR) in apparently satisfactory condition.
- However, the tank contained two inadequate protective thermostatic
switches on the heater assembly, and they subsequently failed during ground
test operations at Kennedy Space Center (KSC).
- In addition, the tank probably contained a loosely fitting fill tube
assembly. This assembly was probably displaced during subsequent handling,
which included an incident at the prime contractor's plant in which the tank
was jarred.
- In itself, the displaced fill tube assembly was not particularly serious,
but it led to improvised detanking procedures at KSC, which "almost certainly
set the stage for the accident."
- Although Beech had not met any problem in detanking during acceptance
tests, it was not possible to detank oxygen tank no. 2 using normal procedures
at KSC. Tests and analyses indicate that the problem was gas leakage through
the displaced fill tube assembly.
- The special detanking procedures at KSC subjected the tank to an extended
period of heater operation and pressure cycling. "These procedures had not
been used before, and the tank had not been qualified by test for the
conditions experienced. However, the procedures did not violate the
specifications which governed the operation of the heaters at KSC."
- In reviewing these procedures before the flight, officials of NASA, NR,
and Beech did not recognize the possibility of damage from overheating. Many
were not aware of the extended heater operation. In any event, adequate
thermostatic switches might have been expected to protect the tank.
- A number of factors contributed to the presence of inadequate thermostatic
switches in the heater assembly. The original 1962 specifications from NR to
Beech Aircraft Corp. for the tank and heater assembly specified the use of
28-volt, direct-current power, which was used in the spacecraft. In 1965, NR
issued a revised specification that stated the heaters should use a 65-volt dc
power supply for tank pressurization; this was the power supply used at KSC to
reduce pressurization time. Beech ordered switches for the Block II tanks but
did not change the switch specifications to be compatible with 65-volt dc.
- The thermostatic switch discrepancy was not detected by NASA, NR, or Beech
in their review of documentation, nor did tests identify the incompatibility
of the switches with the ground support equipment (GSE) at KSC, "since neither
qualification nor acceptance testing required switch cycling under load as
should have been done. It was a serious oversight in which all parties
shared."
- The thermostatic switches could accommodate the 65-volt dc during tank
pressurization because they normally remained cool and closed. However, they
could not open without damage with 65 volt dc power applied. They were not
required to open until the special detanking. During this procedure, as the
switches started to open when they reached their upper temperature limit, they
were welded permanently closed by the resulting arc and were rendered
inoperative as protective thermostats.
- Failure of the thermostatic switches to open could have been detected at
KSC if switch operation had been checked by observing heater current readings
on the oxygen tank heater control panel. Although not recognized at the time,
the tank temperature readings indicated that the heaters had reached their
temperature limit "and switch opening should have been expected."
- Subsequent tests showed that failure of the thermostatic switches probably
permitted the temperature of the heater tube assembly to reach about 1,000
degrees F [810 K] in spots during the continuous eight-hour period of heater
operation. Such heating had been shown by tests to damage severely the Teflon
insulation on the fan motor wires near the heater assembly. "From that time
on, including pad occupancy , the oxygen tank no. 2 was in a hazardous
condition when filled with oxygen and electrically powered."
- Nearly 56 hours into the mission, the fan motor wiring, possibly moved by
the fan stirring, short-circuited and ignited its insulation. Combustion in
the oxygen tank "probably overheated and failed the wiring conduit where it
entered the tank, and possibly a portion of the tank itself."
- The rapid expulsion of high-pressure oxygen which followed, "possibly
augmented by combustion of insulation in the space surrounding the tank, blew
off the outer panel to bay 4 of the SM, caused a leak in the high-pressure
system of oxygen tank no. 1, damaged the high-gain antenna, caused other
miscellaneous damage, and aborted the mission."
Based on the findings
of the Board, a number of recommendations were made to preclude similar
accidents in future space flights:
- The cryogenic oxygen storage system in the service module should be
modified to:
- Remove from contact with the oxygen all wiring and unsealed motors that
could potentially short-circuit and ignite adjacent materials; or otherwise
ensure against an electrically induced fire in the tank.
- Minimize the use of Teflon, aluminum, and other relatively combustible
materials in the presence of the oxygen and potential ignition sources.
- The modified cryogenic oxygen storage system should be subjected to a
rigorous requalification program, including careful attention to potential
operational problems.
- The warning systems on the Apollo spacecraft and in the Mission Control
Center should be carefully reviewed and modified where appropriate, with
specific attention to:
- Increasing the differential between master alarm trip levels and
expected normal operating ranges to avoid unnecessary alarms.
- Changing the caution and warning system logic to prevent an
out-of-limits alarm from blocking another alarm if a second quantity in the
same subsystem went out of limits.
- Establishing a second level of limit sensing in Mission Control on
critical quantities, with a visual or audible alarm that could not be easily
overlooked.
- Providing independent talk-back indicators for each of the six fuel cell
reactant valves plus a master alarm when any valve closed.
- Consumables and emergency equipment in the LM and the CM should be
reviewed to determine whether steps should be taken to enhance their potential
for use in a 'lifeboat' mode.
- MSC should complete the special tests and analyses under way to understand
more completely the details of the Apollo 13 accident. In
addition, the lunar module power system anomalies should receive careful
attention. Other NASA Centers should continue support to MSC in the areas of
analysis and test.
- Whenever significant anomalies occurred in critical subsystems during
final preparation for launch, standard procedures should require a
presentation of all prior anomalies on that particular piece of equipment,
including those which have previously been corrected or explained. Critical
decisions on flightworthiness should require the full participation of an
expert "intimately familiar with the details of that subsystem."
- NASA should thoroughly reexamine all its spacecraft, launch vehicle, and
ground systems containing high-density oxygen or other strong oxidizers, to
identify and evaluate potential combustion hazards in the light of information
developed in this investigation.
- NASA should conduct additional research on materials compatibility ,
ignition, and combustion in strong oxidizers at various gravity levels and on
the characteristics of supercritical fluids. Where appropriate, new NASA
design standards should be developed.
- MSC should reassess all Apollo spacecraft subsystems, and the engineering
organizations responsible for them at MSC and at its prime contractors, to
ensure adequate understanding and control of the engineering and manufacturing
details at the subcontractor and vendor level. "Where necessary,
organizational elements should be strengthened and in-depth reviews conducted
on selected subsystems with emphasis on soundness of design, quality of
manufacturing, adequacy of test, and operational experience."
Memos,
Low and Paine to Cortright, "Establishment of Apollo 13 Review Board," April 17,
1970; Low and Paine to Cortright, "Membership of Apollo 13 Review Board," April
21, 1970; Low and Paine to Chairman, Aerospace Safety Advisory Panel Charles D.
Harrington, "Review of Procedures and Findings of Apollo 13 Review Board," April
20, 1970; Low and Paine to Dale D. Myers, NASA Hq., "Apollo 13 Review," April
20, 1970; ltr., Cortright to Paine, June 15, 1970; House Committee on Science
and Astronautics, The Apollo 13 Accident: Hearings, 91st Cong., 2nd
sess., June 16, 1970, pp. 234-36, 273-74.
April 19
To support the Apollo 13 Review Board, an MSC Apollo 13
Investigation Team, headed by Scott H. Simpkinson, was established with the
following panels: spacecraft incident investigation, flight crew observations,
flight operations and network ; photograph handling, processing, and cataloging
; corrective action study and implementation for the CSM, LM, and
government-furnished equipment; related system evaluation; reaction processes in
high-pressure fluid systems; high-pressure oxygen system survey; public affairs;
and administration, communications, and procurement.
Memos, James A. McDivitt, MSC, to Apollo 13 Investigation Team, "Apollo 13
Investigation Team organization," April 19, 1970; Owen G. Morris, MSC, to Scott
H. Simpkinson, "Apollo 13 Investigation Team organization," April 20, 1970.
NASA Hq. and Center actions were initiated on
recommendations of the Apollo 13 Review Board. The Associate Administrator for
Space Science and Applications would take specific action on recommendations 6,
7, and 9 of the report as they applied to spacecraft, launch vehicles, aircraft,
ground systems and laboratories under OSSA jurisdiction. Lewis Research Center
was directed to conduct a comprehensive review of oxygen-handling practices in
NASA programs. The Aerospace Safety Research and Data Institute was already
conducting studies on oxygen handling in aerospace programs. Other Centers were
taking action on Board recommendations as applicable. (See July 16 entry.)
Memos, George M. Low, NASA Hq., to Associate Administrator for Space Science
and Applications, "Recommendations of the Apollo 13 Review Board," June 26,
1970; Low to Director, Lewis Research Center, "Expansion of ASRDI Oxygen Systems
Review," June 26, 1970; T. O. Paine, NASA Hq., to Director, Lewis Research
Center, "Review of Oxygen Handling in Aerospace Programs to be Conducted by the
Aerospace Safety Research and Data Institute (ASRDI)," May 19, 1970; Bruce T.
Lundin, Lewis Research Center to Deputy Administrator, "Proposed oxygen handling
program," July 14, 1970; Deputy Associate Administrator for Space Science and
Applications (Engineering) to distr., "Recommendations of the Apollo 13 Review
Board," Aug. 5, 1970.
Efforts of MSC personnel that had been
redirected to support the Apollo 13 investigation would again be
concentrated on the Apollo-experience-reporting project in an effort to attain a
publication date of November 1, 1970.
Memo, Scott H. Simpkinson, MSC, to distr., "Apollo experience reporting,"
July 14, 1970.
July 16
MSC moved to reassess all Apollo spacecraft subsystems and the
engineering organizations responsible for them at MSC and its prime contractors,
in response to Apollo 13 Review Board recommendation 9 (see April 13-June 15).
Memo, James A. McDivitt, MSC, to distr., "Apollo 13 Review Board Report -
Recommendation #9," July 16, 1970; extract from recommendation 9 of the Apollo
13 Review Board Report.
July 17
During the anniversary of Apollo 11, NASA
Administrator Thomas O. Paine said: "The success of Apollo 11 marked the
beginning of a new and important phase of mankind - not just the triumphant end
of a mission. The mission was a voyage of discovery, and an important part of
the discovery was the revelation of the infinite human potential for achievement
as an endless new frontier was opened for future generations.
"Our remarkable progress in the first dozen years of the space age
demonstrates that no dreams are impossible of realization, that the prospects
for progress and human betterment here on earth as well as in space are
limitless. And you may be sure that despite changing program directions, NASA
will continue to play an exciting and vigorous role in the avant-garde of human
progress."
Paine, Message to NASA coworkers, July 17, 1970.
North American Rockwell announced that
William B. Bergen, who had been serving as president of North American's Space
Division, would become a corporate vice president with the title Group Vice
President - Aerospace and Systems. This was one of a number of key
organizational steps taken since January to improve and strengthen the North
American management structure in response to significant changes that had
occurred in the aerospace environment.
Ltr., Robert Anderson, North American Rockwell Corp., to Robert R. Gilruth,
MSC, Aug. 11, 1970.
NASA was canceling Apollo missions 15 and
19 because of congressional cuts in FY 1971 NASA appropriations, Administrator
Thomas O. Paine announced in a Washington news conference. Remaining missions
would be designated Apollo 14 through 17. The Apollo budget would be reduced by
$42.1 million, to $914.4 million - within total NASA $3.27 billion.
"Statement by Dr. Thomas O. Paine," Sept. 2, 1970; Astronauts and
Aeronautics, 1970 (NASA SP-4015, 1972), pp. 248, 257, 284-85.
September 11
Modifications were made in MSFC's lunar roving vehicle
simulator and the static mockup to eliminate extreme arm and hand fatigue felt
by a flight crew member and other test subjects after driving 10 to 15 minutes
in LRV simulator evaluation tests. A T-shaped handle was added to the pistol
grip; a parking-brake release and a reduced brake-travel distance were
incorporated; and a mechanical reverse lockout was added.
Memo, James A. McDivitt, MSC, to Richard G. Smith, MSFC, "Lunar roving
vehicle hand controller," Sept. 11, 1970.
Apollo 13's service module oxygen tank.
Redesigned oxygen tank.
MSC Director Robert R. Gilruth reported MSC actions on the Apollo 13 Review
Board recommendations (see April 13-June 15), including:
- Fan motors had been removed from oxygen storage tanks in the service
modules; the electrical leads had been encased in stainless steel sheaths with
hermetically sealed headers and had been shielded from contact with the
remaining Teflon parts.
- The modified cryogenic oxygen storage system had been subjected to a
comprehensive recertification program developed in close coordination by North
American Rockwell, Beech Aircraft Corp., and NASA. Requirements were founded
on environmental as well as operational factors necessary to prove design
capability.
- No major changes had been made in the caution and warning system.
- The LM and CSM consumables and emergency equipment had been reviewed to
determine any design changes required to provide a safe return from lunar
orbit in the event of a service module cryogenic-oxygen-supply loss. Three
design changes were made in the CSM related to the oxygen tanks, an LM descent
battery, and a water storage system in the CM.
- MSC had made special tests and analyses to understand the Apollo
13 accident better. The testing had reaffirmed the conclusions reached
by the Apollo 13 Review Board.
- Significant anomalies in critical subsystems during final preparation for
launch would be analyzed and resolved with authorized and documented
corrective action in much the same manner as employed during the missions. An
Apollo Program Directive for identification and resolution of significant
failures and anomalies had been issued.
- A thorough reexamination of all spacecraft, launch vehicle, and ground
systems containing high-density oxygen and other strong oxidizers was being
made to identify and evaluate potential combustion hazards.
- Additional research was being conducted on materials compatibility,
ignition, and combustion in strong oxidizers at various gravity levels and on
the characteristics of supercritical fluids. Arc-ignition tests of the Apollo
14 oxygen-storage-system materials in both normal and overstressed modes
indicated a positive margin of safety.
- MSC had organized a system-by-system task team effort and made
comprehensive reassessments of each subsystem. Design and qualification of
each subsystem was reaffirmed as adequate for current ground test and mission
requirements with the exception of a heatshield blowout plug for dumping
reaction-control-subsystem propellant for launch aborts.
Ltr., Gilruth
to Edgar M. Cortright, LaRC, Nov. 24, 1970.
November 25
George M. Low, Acting NASA Administrator, discussed the
significance of unmanned lunar probes Luna XVI and
XVII launched by the U.S.S.R. September 12 and November 10.
Luna XVI had brought lunar samples back to earth and Luna
XVII had landed an unmanned Lunokhod roving vehicle on the moon's
surface. Low stated in a letter to Chairman Clinton P. Anderson of the Senate
Committee on Aeronautical and Space Sciences that while the two launches were
impressive their contributions to science and technology were relatively minor.
Low suggested that the main lesson to be learned from the two launches
specifically and the U.S. and U.S.S.R. space programs in general was that while
the Soviet launch rate was increasing that of the United States was decreasing.
These trends in the two countries' space programs should be a cause of concern
if the United States was interested in maintaining a position of leadership in
space.
Ltr., Dale D. Myers, NASA Hq., to Robert R. Gilruth, MSC, Dec. 16, 1970;
Congressional Record-Senate, Nov. 30, 1970, pp. S19001-02.