AS-509 Prelaunch Operations
Event |
|
. | |
LM Operations |
30 Oct 70 |
Combined System Test |
4 Dec 70 |
Unmanned Altitude Run |
5 May 70 |
Manned Altitude Run |
18 Sep 70 |
LM/SLA Mate |
22 Oct 70 |
CSM Operations |
3 Nov 70 |
Combined System Test |
4 Dec 70 |
Unmanned Altitude Run |
27 Aug 70 |
Manned Altitude Run |
3 Sep 70 |
CSM/SLA Mate |
31 Oct 70 |
Ordnance Installation |
7 Nov 70 |
LV VAB Low Bay Operations |
12 May 70 |
IU Low Bay Checkout |
12 May 70 |
S-IVB Low Bay Checkout |
12 May 70 |
S-II Low Bay Checkout |
11 May 70 |
LV VAB High Bay Operations |
29 Oct 70 |
S-IC Erection |
14 Jan 70 |
LV Erection |
13 May 70 |
LV Electrical System Test |
6 Oct 70 |
LV Malfunction Overall Test |
21 Oct 70 |
LV Service Arm Overall Test |
29 Oct 70 |
Spacecraft Erection |
4 Nov 70 |
Space Vehicle VAB Operations |
8 Nov 70 |
Transfer to Pad |
9 Nov 70 |
Pad Operations |
31 Jan 70 |
LV Power ON |
11 Nov 70 |
Space Vehicle Overall Test |
7 Dec 70 |
LV Flight Systems Test |
11 Dec 70 |
SV Flight Electrical Mating |
11 Dec 70 |
SV Back-up Guidance Test |
14 Dec 70 |
SV Flight Readiness Test |
15 Dec 70 |
SV Hypergolic Loading |
8 Jan 71 |
S-IC RP-I Loading |
9 Jan 71 |
CDDT-Wet/Dry |
18 Jan 71 |
SV Countdown Prep |
25 Jan 72 |
Countdown |
31 Jan 71 |