Part 2 (M)
Recovery, Spacecraft Redefinition, and First Manned Apollo Flight
June through July 1968
1968
June
1968
July
June 3
ASPO Manager George Low advised Apollo program officials at KSC
that, to collect adequate data for evaluating any potential toxicological hazard
inside the spacecraft, collection of gas samples of the cabin atmosphere must be
made for 12 hours during the unmanned altitude chamber test with all systems
operating. Low asked that this requirement be included in the spacecraft test
procedures. (Purpose of a total CSM 101 and LM-3 toxicological evaluation was to
verify that no toxic contaminants were given off by the nonmetallic materials
used in the crew compartments.)
Ltr., Low to R. O. Middleton, KSC, "Toxicological evaluation of CSM 101 and
LM-3," June 3, 1968.
June 3
Apollo Program Director Sam Phillips asked ASPO Manager George
Low to investigate the value of using freon as a fire extinguishing agent inside
the spacecraft. Admittedly, Phillips said, MSC had considered using a freon
extinguisher system shortly after the AS-204 accident, but it had been rejected,
largely because of toxicity factors and because tests had shown the agent
ineffective in extinguishing combustion of polyurethane in a pure oxygen
atmosphere. A number of factors now dictated a reevaluation of such an
extinguisher system, however:
- Additional testing of late had indicated a lower toxicity problem than
earlier believed.
- The addition of oxygen masks to the spacecraft now afforded some
protection against a toxic atmosphere.
- Because of post-accident changes inside the cabin, the flammability
problem had been reduced to a few specific materials (quite different from
polyurethane foam) sited in compartmentalized locations inside the cabin.
- The oxygen-nitrogen mixed gas had been selected as the prelaunch
atmosphere inside the cabin.
In view of these changes, Phillips said, a
freon extinguishing system might be better than the present jelled water
extinguisher (quicker activation and reduced equipment damage). He asked that
Low not overlook this potential improvement in crew safety, which could be of
particular value during the high-risk period of launch, when the crew was
essentially immobilized by the forces of acceleration.
Ltr., Phillips to Low, "CBrF3 (Freon 1301) as a Fire Extinguishing Agent,"
June 3, 1968.
June 5
George E. Mueller, Associate Administrator for Manned Space
Flight, wrote MSC Director Robert R. Gilruth to express his personal interest in
lunar extravehicular activity (EVA) training for the Apollo crews of the F and G
missions (i.e., the initial lunar landing and subsequent flights). Because of
the complexity of the EVA tasks that the astronauts must perform, Mueller said,
crews for those missions should be selected as early as possible. Also,
realistic training - including a realistic run-through of many of the lunar
surface tasks, especially development of the S-band antenna and the Apollo Lunar
Surface Experiments Package and sampling operations - must be conducted to
ensure that the crews competently carried out the various scientific experiments
and other tasks during their brief stays on the moon.
Ltr., Mueller to Gilruth, June 5, 1968.
June 7
ASPO Manager George M. Low and others from MSC met with Grumman's
LM engineering staff, headed by Thomas J. Kelly, to discuss the descent stage
heatshield and thermal blanket problems associated with reduced thrust decay of
the descent engine at lunar touchdown. Several significant decisions were
reached:
- The touchdown probe was lengthened to 1.6 meters.
- Effective on LM-5 and later vehicles, Grumman would "beef up" (both
structurally and thermally) the base heatshield.
- Grumman was to conduct a series of tests on overpressure of the descent
engine.
- Grumman would begin design studies of a jettisonable descent engine skirt.
- Landing stability would be reexamined with the existing thrust tailoff
profile (a study to be made either by Grumman or by Boeing; Low asked Maxime
A. Faget, Director of Engineering and Development at MSC, to review this
proposed test plan and to recommend where it should be conducted, for best
cost, schedule, and technical capabilities).
Memo, Low to C. H.
Bolender, "LM descent stage base heatshield," June 8, 1968.
June 10
In his weekly progress report to the NASA Administrator, Deputy
Administrator for Manned Space Flight George E. Mueller cited several important
Apollo events during the first week of June:
- On June 1, technicians at MSC completed thermal-vacuum testing on LTA-8 to
support LM-3, including 45% hours of manned testing. All spacecraft systems
functioned normally, and preliminary results indicated that all significant
test objectives had been realized.
- Engineers and technicians at KSC completed receiving inspection of CSM 101
on June 3. That inspection revealed fewer discrepancies than had been present
on any other spacecraft delivered to the Cape. Pre-mate inspection of CM 101
also was completed, as were leakage and functional tests on the electrical
power and reaction control systems. SM 101 was in the altitude chamber being
prepared for combined systems testing.
Memo, Mueller to NASA
Administrator, "Manned Space Flight Weekly Report - June 7, 1968," June 10,
1968.
June 10
ASPO Manager George M. Low met with Christopher C. Kraft, Jr.,
and Donald K. Slayton, Directors of MSC Flight and Flight Crew Operations, and
several members of their staffs (including astronaut Walter M. Schirra, Jr.) to
discuss using the flight combustion stability monitor (FCSM) on the Apollo 7
flight. (The FCSM was a safety device to shut down the service propulsion system
[SPS] automatically in the event of rough combustion or instability.) At the
insistence of the Propulsion and Power Division, they agreed to use the FCSM for
all SPS burns on Apollo 7. On all "noncritical" burns, two attempts to start the
engine would be made with the FCSM active. Should the stability monitor shut
down the engine on both those attempts, a detailed review of the situation would
be made before again attempting to start the engine. On "critical" burns (i.e.,
the abort-to-orbit and reentry burns), should the FCSM halt the burn the SPS
engine would be restarted immediately with the FCSM inactive on the assumption
that the shutdown was caused either by an FCSM malfunction or by an engine
instability that would not reoccur on the next start.
Low, Kraft, and the others unanimously wanted to eliminate the FCSM before a
lunar mission, because on this mission lunar orbit and transearth insertion
burns were highly critical and inadvertent shutdowns would cause major
trajectory perturbations. Representatives from the Propulsion and Power Division
(PPD) contended that, because of the relatively small number of bomb tests
carried out on the Block II SPS engine, flight-testing of the engine before the
lunar mission would be inadequate to demonstrate engine stability under all
conditions. Low therefore asked Engineering and Development Director Maxime A.
Faget and PPD Chief Joseph G. Thibodaux, Jr., to plan a ground test program that
would give sufficient confidence in the SPS engine to eliminate the FCSM before
undertaking lunar missions.
Ltr., Low to Thibodaux, "Use of FCSM on Apollo 7," June 11, 1968.
June 11
Dale D. Myers, Apollo CSM Program Manager at North American
Rockwell, advised MSC officials of his company's investigation of two
pilot-chute riser failures during recent drop tests of the Block II
earth-landing system. Should there be any imperfections in either hardware or
assembly techniques, Myers explained, the Block II pilot chute and riser system
could be a marginal-strength item. Investigations had determined that early
manufacturing processes had allowed a differential length between the two plies
of nylon webbing in the pilot-chute riser which caused unequal load distribution
between the two plies and low total riser strength. Because of the earlier test
failures, Myers said, the pilot chute riser had been redesigned. The two-ply
nylon webbing had been replaced by continuous suspension lines (i.e., 12 nylon
cords) and the 5.5-millimeter-diameter cable was changed to 6.3-millimeter
cable. He then cited a series of recent tests that verified the redesigned
pilot-chute riser's strength to meet deployment under worst-case operational
conditions.
Ltr., Myers to K. S. Kleinknecht, MSC, June 11, 1968.
June 17
Apollo Program Director Phillips wrote MSC Director Gilruth
concerning the April 10 proposal for a two-burn lunar orbit insertion (LOI)
maneuver and a spring ejection of the LM from the spacecraft-lunar module
adapter. Phillips agreed to the two-burn LOI in place of the originally planned
one burn if results of an analysis should prove the requirement. He specified
that an analysis be made of the tradeoffs and that the analysis include the risk
of crash, the assumed risks due to lengthening the lunar orbit time (about four
hours), and risks due to an additional spacecraft propulsion system burn, as
well as the effect of the lunar gravitational potential on the ability to target
the LOI maneuver to achieve the desired vector at the time of LM descent. The
proposal for spring ejection of the LM from the SLA was approved with the
provision that a failure analysis be made in order to understand the risks in
the change.
Ltr., Samuel C. Phillips, OMSF, to Robert R. Gilruth, MSC, June 17, 1968.
NASA and contractor technicians successfully
conducted the final parachute drop test to qualify the Apollo CSM earth-landing
system. The Block II ELS thus was considered ready for manned flight after 12
Block I, 4 Block II, and 7 increased-capability Block II Qualification Tests -
that had followed 77 Block I, 6 Block II, and 25 increased-capability Block II
Development Drop Tests.
Memo, George E. Mueller, NASA OMSF, to NASA Administrator and Deputy
Administrator. "Manned Space Flight Weekly Report - July 5, 1968," July 8, 1968;
NASA Technical Note (NASA TN D-7437), "Apollo Experience Report-Earth Landing
System."
July 5
ASPO Manager George M. Low asked Aaron Cohen, one of his chief
technical assistants, to investigate the ability of the Apollo spacecraft to
withstand bending loads imposed by a failure of one or more engines on the
Saturn V launch vehicle (as well as actual loads that would be imposed on the
spacecraft). During the previous week, Low and the Configuration Control Board
had ruled out making any significant design changes to cope with a Saturn V
engine failure. Specifically, Low asked how bending loads on the spacecraft were
derived; what bending loads were imposed on the spacecraft during the
Apollo 6 mission, where two J-2 engines were cut off during the
flight; what was the probability - and criticality - of an S-IC engine's failing
and thereby imposing high bending loads; and whether abort limits should be
established for an engine failure.
Memo, Low to Cohen, "Saturn V single engine out problems," July 5, 1968.
July 10-11
The Apollo Design Certification Review (DCR) Board met in
Houston to examine CSM 101 and the Block II CSM for proof of design and
development maturity and to certify the designs for flightworthiness and manned
flight safety. (Three earlier reviews directly supported this penultimate
scrutiny of the vehicle's development: the CSM 101 Design Certification Review
March 6-7, the Block II environmental control system and spacesuit DCR May 8,
and the DCR covering the CM land and water impact test program June 6.) The
board concluded that design certification on CSM 101 was complete. Action and
open items were subsequently forwarded to the Centers for resolution, to be
closed before the Apollo 7 Flight Readiness Review.
Ltr., Samuel C. Phillips, NASA Hq., to distr., "CSM 101 and Block II CSM
Delta Design Certification Review," Aug. 28, 1968.
July 11
ASPO Manager Low informed Apollo Program Director Phillips of
several changes in the LM vibration testing program. Before beginning the series
of tests, he told Phillips, red line values were established on critical
components that were not to be exceeded. However, because of the most recent
test effort on LM-2, which resulted from the pogo problem experienced during the
flight of Apollo 6, Low was forced to authorize vibration testing
beyond the red line values initially set for the spacecraft. This action, in
turn, forced an inspection and possible refurbishment of LM-2 to make it
available for an unmanned flight, should such a second unmanned LM test mission
be required. He then cited MSC's future plans for LM-2:
- For the planned drop tests with the vehicle, the upper decks would be
inspected and repaired or replaced where necessary.
- Should a LM-2 flight become necessary, all of the descent stage upper
decks would probably be replaced.
Phillips approved Low's action
immediately. He urged Low to "continue to give priority to that work which is
necessary for full and early resolution of the POGO and spacecraft structural
dynamics questions."
Ltr., George M. Low to Samuel C. Phillips, July 11, 1968, with handwritten
notation by Phillips dated July 11, 1968.
July 13
ASPO Manager George M. Low wrote to Grumman President Llewellyn
J. Evans to call his attention to the problem of continued propellant leaks in
the LM. "In spite of all of our efforts, last summer" (i.e., with the extensive
plumbing rework done on LM-1 after its delivery to Florida), Low said,
technicians at KSC found a leak on one of the lines on LM-3, even though no
leaks had been observed during checkout at Bethpage. Investigating the problem,
Low had learned that Grumman had made some propellant-system design changes that
had led to installation of four-bolt flanges with single teflon O-ring seals -
despite the fact that during the preceding summer NASA and Grumman had jointly
agreed not to use this joint on the LM vehicle. This most recent problem, said
Low, again points up the importance of strictest control of all design changes
in the spacecraft. Because of the need for maintaining a lunar-configured LM as
a design baseline, all spacecraft design changes had to be carried through the
Apollo Configuration Control Board before implementation.
Ltr., Low to Evans, July 13, 1968.
July 15
NASA Apollo Program Director Samuel C. Phillips laid down
Headquarters and MSC interfaces with the Atomic Energy Commission (AEC)
regarding the SNAP-27 radioisotope thermoelectric generator for the Apollo Lunar
Surface Experiments Package (ALSEP). The Lunar Surface Program Office at MSC was
the field project office responsible for developing the ALSEP system, and the
radioisotope generator - as part of the ALSEP - had been assigned to that office
for system integration. Thus, the Lunar Surface Program Office served as the
AEC's primary contact on the SNAP-27 both for ALSEP program matters and for data
pertaining to flight safety and documentation for flight approval. Phillips
stressed that all data be fully coordinated with Headquarters before being
submitted to the AEC. (Approval for the flight of any nuclear device rested
ultimately with the President, but formal documentation had to be concurred in
by the NASA Administrator, the AEC Commissioners, the Secretary of Defense, and
the National Aeronautics and Space Council.)
Memo, Phillips to George M. Low, ASPO, MSC, "Atomic Energy Commission
Interfaces," July 15, 1968.
July 17
NASA Associate Administrator George E. Mueller, Apollo Program
Director Samuel C. Phillips, and other high-ranking manned space flight
officials from Headquarters visited Bethpage for an overall review of the LM
program. Greatest emphasis during their review was on schedules, technical
problems, and qualification of the spacecraft's principal subsystems. Mueller
and Phillips cited several areas that most concerned NASA:
- Delivery schedules from subcontractors and vendors had slipped
significantly during the past year, to the point where many components were
only marginally supporting spacecraft deliveries.
- The large number of hardware changes made during the past year was
affecting costs and schedules.
- Costs forecast for Fiscal Year 1969 exceeded the current LM
budget.
Mueller also suggested that Grumman consider eliminating the LM
rendezvous radar to save weight aboard the vehicle. He stated that VHF ranging
would be more accurate and would probably be the preferred mode of operation.
Memo, C. H. Bolender, MSC LM Manager, to Manager, Apollo Spacecraft Program,
MSC, "Dr. Mueller's visit to GAEC on July 17, 1968," July 19, 1968.
July 22
In the continuing effort to reduce costs while still maintaining
a balanced and viable program, ASPO Manager George M. Low recommended to NASA
Hq. that CSM 102 be deleted from the manned flight program. He estimated total
savings at $25.5 million (excluding cost of refurbishment after the current
ground test program). In addition, he said, during the static structural test
program at North American Rockwell, CSM 102 would be subjected to loads that
would compromise structural integrity of the vehicle for manned flight.
Ltr., Low to Samuel C. Phillips, "Deletion of CSM 102 from the manned flight
program," July 22, 1968.
July 23
Prompted by a request from MSC to increase the Saturn V's
performance to 46,070 kilograms for lunar missions, Samuel C. Phillips sought to
strike a balance between spacecraft and launch vehicle weight-performance
demands. He established as a new payload interface definition at translunar
injection a payload of 46,040 kilograms. Should the vehicle per se be incapable
of achieving this figure, said Phillips, he would relax certain flight
constraints to achieve the best possible balance between the space vehicle and
the specific mission to be flown. But he implored both ASPO Manager George M.
Low and Lee B. James, Saturn V Program Manager at MSFC, to work toward this
balance between spacecraft and launch vehicle and to avoid any hardware changes
in the Saturn V solely to meet the new payload interface weight.
Ltr., Phillips to James and Low, "Saturn V Payload Interface Definition,"
July 23, 1968.
July 30
F. A. Speer, Mission Operations Manager at MSFC, advised NASA
Hq. of plans for S-IVB and spacecraft separation and employment of a "slingshot"
trajectory following insertion into the trajectory toward the moon. Residuals in
the S-IVB, said Speer, could be used to place the stage in a trajectory that
would avoid recontact with the spacecraft and impact on either the earth or the
moon - with preclusion of spacecraft-launch vehicle collision as the most
important priority.
Ltr., Speer to William C. Schneider, Apollo Mission Director, NASA, "Lunar
Debris," July 30, 1968.