Part 2 (N)
Recovery, Spacecraft Redefinition, and First Manned Apollo Flight
August through September 1968
1968 
August
1968 
September
August 1
Howard W. Tindall, Jr., Deputy Division Chief, MSC Mission 
Planning and Analysis, wrote ASPO Manager George M. Low: "A rather unbelievable 
proposal has been bouncing around lately. Because it is seriously ascribed to a 
high ranking official, MSC and Grumman are both on the verge of initiating 
activities - feasibility studies, procedures development, etc. - in accord with 
it. . . . The matter to which I refer is the possibility of deleting the 
rendezvous radar from the LM. The first thing that comes to mind, although not 
perhaps the most important, is that the uproar from the astronaut office will be 
fantastic - and I'll join in with my small voice too. Without rendezvous radar 
there is absolutely no observational data going into the LM to support 
rendezvous maneuvers. . . . Please see if you can stop this if it's real and 
save both MSC and GAEC a lot of trouble." On August 9 Low wrote NASA Apollo 
Program Manager Samuel Phillips that, shortly after Associate Administrator for 
Manned Space George Mueller had visited Grumman, Low had calls from both C. H. 
Bolender, MSC, and Joseph Gavin, Grumman, indicating that Mueller had made a 
suggestion "that we should eliminate the LM rendezvous radar as a weight saving 
device." He forwarded Tindall's memorandum as the basis for "why we should not 
consider deleting the radar and why we shouldn't spend any more effort on this 
work." Low added that MSC was discontinuing "any work that we may have started 
as a result of George's comments." In a reply on August 28, Phillips told Low, 
"I am in complete agreement . . . that all work toward deleting the LM 
rendezvous radar should be discouraged and I have written to George Mueller to 
that effect."
Memo, Tindall to Manager, ASPO, "LM rendezvous radar is essential," Aug. 1, 
1968; ltrs., Low to Phillips, Aug. 9, 1968, Phillips to Low, Aug. 28, 1968.
August 2
In an effort to stem the number of hardware changes at KSC, 
Apollo Program Director Samuel C. Phillips instituted a weekly review of all 
changes that produced additional work at KSC in excess of normal checkout flow. 
Phillips stressed the extraordinary importance of change control and the 
requirement that only mandatory changes be approved through the control boards 
at MSC and MSFC. The volume of changes currently under way at KSC constituted a 
major concern. Key program objectives, he said, were in jeopardy.
TWXs, Phillips to distr., Aug. 2 and 19, 1968.
August 7
The Apollo Design Certification Review (DCR) Board convened at 
MSC to examine LM-3 further for proof of design and development maturity and to 
assess and certify the design of the LM-3 as flightworthy and safe for manned 
flight. This Delta review was identified as a requirement at the March 6 LM-3 
DCR. The Board concluded at the close of the Delta DCR that LM-3 was safe to fly 
manned with the completion of open work and action items identified during the 
review.
Ltr., Apollo Program Director to distr., "LM-3 Delta Design Certification 
Review," Sept. 12, 1968.
August 8
ASPO Manager George M. Low and several members of his staff met 
at KSC with Center Director Kurt H. Debus, Launch Operations Director Rocco A. 
Petrone, and KSC Apollo Program Manager R. O. Middleton to discuss test and 
checkout problems for AS-503 and AS-504. They collectively agreed that only 
mandatory changes - i.e., changes for flight safety or to ensure mission success 
- could be made once the spacecraft reached KSC. (Changes that would speed the 
KSC checkout flow also were permitted.) Furthermore, two separate work packages 
would be prepared for each spacecraft customer acceptance readiness review 
board. The first package comprised normal work to be performed at KSC on all 
spacecraft. The second included special work normally done at the factory, but 
which for that specific vehicle was being transferred to the Cape (installation, 
retesting, etc.). The group also reviewed recent Apollo checkout experiences - 
especially test failures and open items - in an effort to improve these areas 
for subsequent missions.
Memo for record, Low, "Report of meeting at KSC," Aug. 10, 1968.
August 9 - November 12
ASPO Manager George M. Low initiated a series of 
actions that led to the eventual decision that AS-503 (Apollo 8) should be a 
lunar orbital mission. Events and the situation during June and July had 
indicated to Low that the only way for the "in this decade" goal to be attained 
was to launch the Saturn 503/CSM 103 LM-3 mission in 1968. During June and July 
the projected launch slipped from November to December, with no assurance of a 
December launch. Later, Low recalled "the possibility of a circumlunar or lunar 
orbit mission during 1968, using AS-503 and CSM 103 first occurred to me as a 
contingency mission."
During the period of July 20-August 5, pogo problems that had arisen on 
Apollo 6 seemed headed toward resolution; work on the CSM slowed, 
but progress was satisfactory; delivery was scheduled at KSC during the second 
week in August and the spacecraft was exceptionally clean. The LM still required 
a lot of work and chances were slim for a 1968 launch.
On August 7, Low asked MSC's Director of Flight Operations Christopher C. 
Kraft, Jr., to look into the feasibility of a lunar orbit mission for Apollo 8 
without carrying the LM. A mission with the LM looked as if it might slip until 
February or March 1969. The following day Low traveled to KSC for an AS-503 
review, and from the work schedule it looked like a January 1969 launch.
August 9 was probably one of the busiest days in George Low's life; the 
activities of that and the following days enabled the United States to meet the 
"in this decade" goal. At 8 :45 a.m. he met with MSC Director Robert R. Gilruth 
and told him he had been considering a lunar orbit mission. Gilruth was highly 
enthusiastic. At 9:00 a.m. Low met with Kraft and was informed that the mission 
was technically feasible from ground control and spacecraft computer standpoint. 
(A decision had been made several months earlier to put a Colossus onboard 
computer program on the 103 spacecraft.)
At 9:30 a.m. Low met with Gilruth, Kraft, and Director of Flight Crew 
Operations Donald K. Slayton, and they unanimously decided to seek support from 
MSFC Director Wernher von Braun and Apollo Program Director Samuel C. Phillips. 
Gilruth called von Braun and, after briefly outlining the plan, asked if they 
could meet in Huntsville that afternoon. Low called Phillips, who was at KSC, 
and asked whether he and KSC Director Kurt Debus could participate and a meeting 
was set up for 2:30.
Present at the 2:30 p.m. meeting at MSFC were von Braun, Eberhard Rees, Lee 
James, and Ludie Richard, all of MSFC: Phillips and George Hage, both of OMSF; 
Debus and Rocco Petrone, MSFC; and Gilruth, Low, Kraft, and Slayton of MSC. Low 
outlined the hardware situation and told the group it was technically feasible 
to fly the lunar orbit mission in December 1968, with the qualification that 
Apollo 7 would have to be a very successful mission. If not successful, Apollo 8 
would be another earth-orbital mission. Kraft made a strong point that to gain 
lunar landing benefits Apollo 8 would have to be a lunar orbital rather than a 
circumlunar mission. All were enthusiastic. Phillips began outlining necessary 
events: KSC said it would be ready to support such a launch by December 1; MSFC 
felt it would have no difficulties; MSC needed to look at the differences 
between spacecraft 103 and 106 (the first spacecraft scheduled to leave earth's 
atmosphere) and had to find a substitute for the LM. The meeting was concluded 
at 5:00 p.m. with an agreement to meet in Washington August 14. This would be 
decision day and, if "GO," Phillips planned to go to Vienna and discuss the plan 
with Associate Administrator for Manned Space Flight George E. Mueller and NASA 
Administrator James E. Webb (who were attending a United Nations Conference). 
Preliminary planning would be secret, but if and when adopted by the agency the 
plan would be made public immediately.
Still on August 9, in another meeting at MSC at 8:30 p.m., Low met with 
Kenneth S. Kleinknecht, George Abbey, and C. H. Bolender of MSC, and Dale Myers, 
North American Rockwell. Bolender left immediately for Bethpage, N.Y., to find a 
substitute for the LM; and Myers left for Downey, Calif., to get the CM going.
On the following day there were still no obvious insurmountable problems that 
might block the plan. Kleinknecht was studying the differences between 
spacecraft 103 and 106, where the high-gain antenna might be a problem. It 
seemed possible to use LM-2 to support the flight, but Joseph Kotanchik, MSC, 
suggested flying a simple crossbeam instead of a LM in the event the pogo 
oscillation problem remained and pointed out that even if pogo was solved the LM 
would not be needed. Low called Richard and Hage, who agreed with Kotanchik but 
still wanted mass representation to avoid possible dynamic problems. Low then 
called William Bergen, of North American, who was not too receptive to the plan.
On August 12 Kraft informed Low that December 20 was the day if they wanted 
to launch in daylight. With everyone agreeing to a daylight launch, the launch 
was planned for December 1 with a "built-in hold" until the 20th, which would 
have the effect of giving assurance of meeting the schedule. LTA (LM test 
article)-B was considered as a substitute; it had been through a dynamic test 
vehicle program, and all except Kotanchik agreed this would be a good 
substitute. Grumman suggested LTA-4 but Low decided on LTA-B.
Kleinknecht had concluded his CSM 103-106 configuration study by August 13 
and determined the high-gain antenna was the most critical item. Kraft was still 
"GO" and said December 20-26 (except December 25) offered best launch times; he 
had also looked at January launch possibilities. Slayton had decided to assign 
the 104 crew to the mission. He had talked to crew commander Frank Borman and 
Borman was interested.
Participants in the August 14 meeting in Washington were Low, Gilruth, Kraft, 
and Slayton from MSC; von Braun, James, and Richard from MSFC; Debus and Petrone 
from KSC; and Deputy Administrator Thomas Paine, William Schneider, Julian 
Bowman, Phillips, and Hage from NASA Hq. Low reviewed the spacecraft aspects; 
Kraft, flight operations; and Slayton, flight crew support. MSFC had agreed on 
the LTA-B as the substitute and were still ready to go; and KSC said they would 
be ready by December 6.
While the meeting was in progress, Mueller called from Vienna to talk to 
Phillips. He was cool to the proposed idea, especially since it preceded Apollo 
7, and urged Phillips not to come to Vienna, adding that he could not meet with 
the group before August 22. The group agreed they could not wait until August 22 
for a decision and agreed to keep going, urging again that Phillips go to Vienna 
and present their case.
At this point Paine reminded them that not too long before they were making a 
decision whether to man 503, and now they were proposing a bold mission. He then 
asked for comments by those around the table and received the following 
responses:
von Braun - Once you decided to man 503 it did not matter how far you 
went.
Hage - There were a number of places in the mission where the decision 
could be made, minimizing the risk.
Slayton - Only chance to get to the moon before the end of 1969.
Debus - I have no technical reservations.
Petrone - I have no reservations.
Bowman - A shot in the arm for manned space flight.
James - Manned safety in this and following flights enhanced.
Richard - Our lunar capability will be enhanced by flying this 
mission.
Schneider - My wholehearted endorsement.
Gilruth - Although this may not be the only way to meet our goal, it 
enhances our possibility. There is always risk, but this is in path of less 
risk. In fact, the minimum risk of all Apollo plans.
Kraft - Flight operations has a difficult job here. We need all kind 
of priorities; it will not be easy to do, but I have confidence. It should be 
lunar orbit and not circumlunar.
Low - Assuming Apollo 7 is a success there is no other choice.
After receiving this response, Paine congratulated them on not being 
prisoners of previous plans and said he personally felt it was the right thing 
to do. Phillips then said the plan did not represent shortcuts and planned to 
meet with Mueller on August 22. He reiterated Mueller's reservations, and then 
agreed to move out on a limited basis, since time was critical.
On August 15 Phillips and Paine discussed the plan with Webb. Webb wanted to 
think about it, and requested further information by diplomatic carrier. That 
same day Phillips called Low and informed him that Mueller had agreed to the 
plan with the provisions that no full announcement would be made until after the 
Apollo 7 flight; that it could be announced that 503 would be manned and 
possible missions were being studied; and that an internal document could be 
prepared for a planned lunar orbit for December.
Phillips and Hage visited MSC August 17, bringing the news that Webb had 
given clear-cut authority to prepare for a December 6 launch, but that they 
could not proceed with clearance for lunar orbit until after the Apollo 7 
flight, which would be an earth-orbital mission with basic objectives of proving 
the CSM and Saturn V systems. Phillips said that Webb had been "shocked and 
fairly negative" when he talked to him about the plan on August 15. 
Subsequently, Paine and Phillips sent Webb a lengthy discourse on why the 
mission should be changed, and it was felt he would change his mind with a 
successful Apollo 7 mission.
Apollo 7 - flown October 11-22 - far exceeded Low's expectations 
in results and left no doubts that they should go for lunar orbit on Apollo 8. 
At the November 10 Apollo Executive meeting Phillips presented a summary of the 
activities; James gave the launch vehicle status; Low reported on the spacecraft 
status and said he was impressed with the way KSC had handled its tight checkout 
schedule; Slayton reported on the flight plan; and Petrone on checkout 
readiness. Petrone said KSC could launch as early as December 10 or 12. Phillips 
said he would recommend to the Management Council the next day for Apollo 8 to 
go lunar orbit. Following are the reactions of the Committee members:
Walter Burke, McDonnell Douglas - the S-IVB was ready but McDonnell 
Douglas favored circumlunar rather than lunar orbit;
Hilliard Paige, GE - favored lunar orbit;
Paul Blasingame, AC - guidance and navigation hardware was ready, 
lunar orbit;
C. Stark Draper, Massachusetts Institute of Technology - we should go 
ahead;
Bob Evans, IBM - go;
George Bunker of Martin, T. A. Wilson of Boeing, Lee Atwood of North 
American, Bob Hunter of Philco-Ford, and Tom Morrow of Chrysler - lunar 
orbit.
At the Manned Space Flight Management Council Meeting on November 11 Mueller 
reported that the proposal had been discussed with the Apollo Executive 
Committee, Department of Defense, the Scientific and Technical Advisory 
Committee (STAC), and the President's Science Advisory Committee (PSAC). STAC 
had made a penetrating review and reacted positively and PSAC was favorably 
disposed toward the plan but made no firm recommendation.
After a series of meetings, on November 11 Paine said Apollo 8 was to go 
lunar orbit. The decision was announced publicly the following day. Low's 
initiative had paid off; the final decision to go to the moon in 1968 was made 
with the blessings of all of NASA's decision-makers, the Apollo Executive 
Committee, STAC, and PSAC.
ASPO Manager George M. Low, "Special Notes for August 9, 1968, and 
Subsequent."
August 10
Capping off a considerable exchange of views between MSC and 
NASA Headquarters, ASPO Manager George Low advised Apollo Program Director Sam 
Phillips that Houston was going ahead with mission planning that employed a 
two-burn orbit insertion maneuver. He forwarded to Phillips a lengthy memorandum 
from one of his staff, Howard W. Tindall, Jr., that explained in detail MSC's 
rationale for this two-stage orbital maneuver, the most important of which 
derived from crew safety and simplified orbital mission procedures. The 
overriding factor, Tindall explained, was a "concern for the consequences of the 
many things we will not have thought about but will encounter on the first lunar 
flight. Anything that can be done to keep the dispersions small and the 
procedures simple provides that much more tolerance for the unexpected. . . . 
The cost of the two-stage LOI is a small price to pay for these intangible but 
important benefits."
Ltr., George M. Low to Samuel C. Phillips, Aug. 10, 1968, with encl., memo, 
Tindall to ASPO Manager, "Recommendation to retain the Two-Stage Lunar Orbit 
Insertion (LOI) Maneuver," Aug. 5, 1968.
August 12
Dieter Grau, Director of Quality and Reliability Assurance at 
MSFC, sent his Houston counterpart Martin Raines a memorandum of understanding 
covering exchanges of quality surveillance responsibility in support of pogo 
structural testing under way both in Huntsville, Ala., and at MSC. Testing was 
being conducted simultaneously at the Wyle Laboratories in Huntsville (under 
contract to North American Rockwell, primarily static loading and referred to as 
shell stability tests); and dynamic load testing at MSC (called the "short 
stack" dynamic tests). In effect, each Center assumed the task of overseeing the 
complete test article (spacecraft, instrument unit, and S-IVB forward skirt) 
being tested at its own location.
Ltr., Grau to Raines, Aug. 12, 1968, with encl., memorandum of agreement, 
"Quality Coverage of POGO Structural Testing," Aug. 12, 1968.
August 13
George M. Low, MSC, in a letter to Samuel C. Phillips, OMSF, 
said that the Design Certification Review (DCR) for spacecraft 101 had been 
completed; that assigned action items had been resolved; and most of the open 
items had been closed. Several open issues would be closed at the 101 Flight 
Readiness Review. Low said: "The MSC subsystem managers have reviewed all the 
documentation supporting the DCR. I have reviewed the statements of 
certification by the North American and MSC subsystem managers. I have 
personally watched the design of Spacecraft 101 develop to a stage of maturity. 
As a result, I am taking this opportunity to certify that Spacecraft 101 is 
ready to perform the Apollo 7 mission once the open items are closed."
Ltr., Low to Phillips, "Design Certification of Apollo 7," Aug. 13, 1968.
August 16
NASA Associate Administrator for Manned Space Flight George E. 
Mueller reported to his superiors that launch preparations for the Apollo 7 
mission were running ahead of schedule. Spacecraft 101 had been erected and 
mated with the launch vehicle on August 9. Integrated systems testing had begun 
on August 15. Preparation for the next mission, Apollo 8, were not proceeding as 
well. Checkout of the launch vehicle and CSM 103 were on schedule, but work on 
LM-3 was some seven days behind schedule. Though LM-3's problems were under 
intensive investigation, they were directly holding up the simulated mission run 
and transfer to the altitude test chamber.
Memo, Mueller to Administrator, "Manned Space Flight Weekly Report - August 
16, 1968."
August 17
ASPO Manager George M. Low wrote Program Director Samuel C. 
Phillips seeking to halt further development of a pogo sensor for the CSM. (MSC 
had undertaken development of the device shortly after the Apollo 6 
flight as "insurance" should the sensor prove necessary.) No requirement for a 
pogo sensor had been identified, said Low. In fact, it was by no means certain 
how the sensor could be used in flight. Because MSFC was highly confident that 
the pogo problem encountered on Apollo 6 had been solved, and 
because no abort criteria could be based on pogo alone, Low argued against the 
sensor. Even in the unlikely event that pogo occurred on the next Saturn V 
flight, he argued against an abort unless there was a catastrophic effect on the 
launch vehicle, in which case abort would be effected using normal abort 
criteria. For these reasons, no pogo sensor was to be installed on the CSM. A 
week later, Phillips approved Low's recommendation to halt the pogo sensor 
development.
Ltrs., Low to Phillips, Aug. 17, 1968; Phillips to Low, Aug. 24, 1968.
August 19
In a Mission Preparation Directive sent to the three manned 
space flight Centers, NASA Apollo Program Director Samuel C. Phillips stated 
that the following changes would be effected in planning and preparation for 
Apollo flights:
  - Apollo-Saturn 503 
  
 - 
  
    - Assignment of Saturn V 503, CSM 103, and LM-3 to Mission D was canceled.
    
    
 - Saturn V 503 would be prepared to carry CSM 103 and LTA (LM test 
    article)-B on a manned CSM-only mission to be designated the C prime 
mission.
    
    
 - The objectives and profile of the C prime mission would be developed to 
    provide maximum gain consistent with standing flight safety requirements. 
    Studies would be carried out and plans prepared so as to provide reasonable 
    flexibility in establishing final mission objectives.
    
    
 - All planning and preparations for the C prime mission would proceed 
    toward launch readiness on December 6, 1968.
 
   - Apollo-Saturn 504 
  
 - Saturn V 504, CSM 104, and LM-3 were assigned to the D mission, scheduled 
  for launch readiness no earlier than February 20, 1969. The crew assigned to 
  the D mission would remain assigned to that mission. The crew assigned to the 
  E mission (Frank Borman, James A. Lovell, Jr., and William Anders) would be 
  reassigned to the C prime mission. Training and equipping the C prime crews 
  and operational preparations would proceed as required to meet mission 
  requirements and to meet the newly established flight readiness date.
 
A 
memorandum from the ASPO Manager on September 3 summarized the basic and 
alternate missions for which detailed planning and preparation would be 
performed. In the basic earth-orbital C prime mission the vehicle configuration 
would consist of the Saturn V 503 with a payload of 39,780 kilograms (CSM 103 
and LTA-B with the service propulsion subsystem fully loaded). Insertion would 
be into low circular orbit of the earth. The earth-parking-orbit activities 
would include crew and ground support exercises related to spacecraft system 
checkout and preparation for translunar injection (TLI; i.e., transfer into a 
trajectory toward the moon). CSM separation maneuver would occur before TLI.
Alternate earth-orbital missions would include a manned TLI burn to a 6440-km 
apogee or an SPS burn to achieve a 6,440-km apogee. An alternate lunar orbit 
mission would include mission planning, crew training, spacecraft hardware, and 
software to support the mission. In providing support, top priority would be 
assigned to the lunar orbit mission. The memo indicated that following TLI, 
simulated transposition and docking maneuvers would be conducted; midcourse 
corrections and star horizon/ star landmark sightings would be performed during 
the translunar coast; lunar orbit insertion would be accomplished and a lunar 
parking orbit established for 20 hours.
On September 13, MSC Director of Flight Operations Christopher C. Kraft 
affirmed that the impact of supporting the described mission plan had been 
assessed and no constraints were seen to prevent meeting the launch readiness 
date. He added that the lunar parking orbit would be established during the 
course of two elliptic orbits and would be of 16 hours duration, thus giving a 
total lunar vicinity time of 20 hours.
Ltr., Phillips to Directors, KSC, MSFC, and MSC, "Apollo Mission Preparation 
Directive," Aug. 19, 1968; memos, Manager, ASPO, to distr., "C Prime Mission," 
Sept. 3, 1968; MSC Director of Flight Operations to Manager, ASPO, "C Prime 
Mission," Sept. 13, 1968.
August 26
ASPO Manager George M. Low asked Joseph N. Kotanchik, head of 
the Structures and Mechanics Division, to verify that all spacecraft load 
analyses and safety factors were compatible with the recently agreed-on payload 
weight of 39,780 kilograms for the AS-503 mission. Low passed along the concern 
voiced by Lee B. James, Saturn V Program Manager at MSFC, that the problem of an 
S-IC engine failure in the Saturn launch vehicle might be more severe for the 
503 mission than for a heavier payload. Had adequate stress analysis been done 
on the high-gain antenna attachments and its support inside the adapter? When 
would pogo dynamic analysis of the actual 503 payload be completed? And finally, 
what was the situation regarding loads on LTA-B, the LM test article to be 
substituted in place of an actual lunar lander aboard the flight?
Memo, Low to Kotanchik,"AS-503 Loads," Aug. 26, 1968.
August 27
George M. Low, ASPO Manager, set forth the rationale for using 
LTA-B (as opposed to some other LM test article or even a full-blown LM) as 
payload ballast on the AS-503 mission. That decision had been a joint one by 
Headquarters, MSFC, and MSC. Perhaps the chief reason for the decision was 
Marshall's position that the Saturn V's control system was extremely sensitive 
to payload weight. Numerous tests had been made for payloads of around 38,555 
kilograms but none for those in the 29,435- to 31,750-kilogram range. MSFC had 
therefore asked that the minimum payload for AS-503 be set at 38,555 kilograms. 
Because LTA-B brought the total payload weight to 39,780 kilograms, that vehicle 
had been selected for the Apollo 8 mission. All dynamic analyses in connection 
with the pogo problem had to be verified, but MSFC engineers were not concerned 
that the established weight would affect pogo performance. Because NASA had been 
prepared to fly AS-503 with a heavier payload - i.e., originally including LM-3 
- Low saw "no reason to be concerned about the decision made to fly the somewhat 
lighter and more symmetrical LTA-B."
Memo, Low to Joseph N. Kotanchik, MSC, "Use of LTA-B for AS-503," Aug. 27, 
1968.
August 28
NASA asked Grumman to make a detailed study of LM-4 to 
determine any constraints that might prevent accomplishment of a lunar orbit 
mission. All such constraints were to be defined in sufficient detail to 
facilitate a NASA review, and NASA expected Grumman-recommended action in each 
case. The information was requested before the LM-4 Customer Acceptance 
Readiness Review. Grumman was further asked to study LM-5 to determine 
constraints that might prevent accomplishment of the lunar landing mission. 
Again, all constraints were to include recommended action.
Ltr., Frank X. Battersby, RASPO, to Joseph Gavin, LM Program Director, 
Grumman, Aug. 28, 1968.
August 30
Eberhard Rees, Director of the Apollo Special Task Team at 
North American Rockwell, notified the contractor that facilities the team had 
used at Downey, Calif., were relinquished to the company. Thus ended the mission 
of the group formed some nine months earlier to oversee the contractor's 
preparations during the period of adjustment following the Apollo 1 accident.
Ltr., Rees to C. F. Wetter, Aug. 30, 1968.
Apollo Program Director Samuel C. Phillips 
notified the three manned space flight Centers that the Apollo 8 launch 
readiness working-schedule date had been changed to December 13, 1968.
TWX, Phillips to MSC, KSC, MSFC, "Apollo 8 (AS-503) Launch Readiness Working 
Schedule," Sept. 3, 1968.
September 6
In response to a letter from Apollo Program Director Samuel 
C. Phillips concerning proposed revisions of the first lunar landing mission 
plan, MSC Director Robert R. Gilruth presented MSC's position on the three major 
topics:
  - deletion of the lunar geology investigation (LGI) and the Apollo Lunar 
  Surface Experiments Package (ALSEP), 
  
 - television coverage, and 
  
 - extravehicular excursion.
 
Concerning the first item, Gilruth said, 
"Our lunar surface exploration and scientific activities should be progressive 
as we extend our knowledge and obtain a better understanding of operational 
limitations and capabilities in a 1/6g environment. . . . By embarking on too 
ambitious an effort on our first mission, we may well jeopardize our capability 
to accomplish manned . . . activities on subsequent flights. . . ." It was 
"recommended that the LGI (with the exception of the contingency sample and 
preliminary sample portion) and the ALSEP be deleted from the first lunar 
landing mission."
With reference to television coverage, Gilruth cited Houston's position that 
"it would be extremely desirable to provide adequate television coverage during 
the extravehicular excursion. Coverage can be obtained through the LM steerable 
antenna and the Goldstone 210-foot [64-meter] antenna while in view of 
Goldstone." MSC proposed to provide "the capability to transmit the television 
signal directly through the high gain antenna; but we would also like to 
maintain the capability to carry the erectable antenna, in the event that it 
will not be feasible to adjust the timeline to provide Goldstone coverage for 
all planned extravehicular activities. . . ."
On the subject of extravehicular excursion, he said, ". . . we strongly 
believe that, on the first lunar landing mission, only a single extravehicular 
activity should be carried out. You have stated that the simplest and safest 
excursion should be conducted by one man alone. However, it is clear that we 
have to maintain the basic capability for a two-man excursion so that the second 
man can assist the first in the event of trouble or difficulties. Also, further 
studies and simulations in this area might identify new reasons why a planned 
two-man excursion is more desirable than a one-man excursion. . . ."
Gilruth said that MSC officials Charles A. Berry, Maxime A. Faget, 
Christopher C. Kraft, Jr., George M. Low, and Donald K. Slayton were in full 
accord with all of these recommendations. He added, however, that Wilmot N. Hess 
felt that "these changes represent a serious compromise to the scientific 
program." Hess felt that the EVA period should be open ended and that it would 
be worthwhile to carry ALSEP and attempt its deployment. Hess also recommended 
that if a decision were made not to carry ALSEP, some easily deployed 
contingency experiments might be added, such as: Solar Wind Composition 
experiment, High-Z Cosmic Ray experiment, and a simplified Corner Reflector for 
Laser Ranging experiment.
Gilruth said that he himself believed, "that it is essential that EVA on the 
first lunar landing mission be limited to a single excursion and that ALSEP and 
LGI be eliminated as experiments from that flight. . . . I believe that the 
maximum scientific gains on this and future missions will be achieved if we 
limit our objectives as proposed. . . . I am sure that all will agree that if we 
successfully land on the moon and return to earth, bring back samples of lunar 
soil, transmit television directly from the moon, and return with detailed 
photographic coverage, our achievement will have been tremendous by both 
scientific and technological standards."
Ltr., Gilruth to Phillips, "Proposed revisions to the first lunar landing 
mission plan," Sept. 6, 1968.
September 10
ASPO Manager George M. Low advised Headquarters of the 
status of MSC's work on action items assigned as a result of the Apollo Crew 
Safety Review Board presentation on June 17. Among those items were:
  - Switching procedures for the emergency detection system - the crew would 
  manually disable the automatic abort device at 1 minute 40 seconds after 
  liftoff. 
  
 - High-altitude abort procedures - these procedures were being reevaluated 
  by the CSM 101 crew on the spacecraft simulator; following completion 
  (scheduled for September 23), a decision would be made whether to retain the 
  procedure for optional tower jettison. 
  
 - Rescue of an incapacitated crew - emergency access procedures were being 
  demonstrated at Downey using CSM 008. Any procedural revisions required would 
  be made accordingly.
 
Completion of these actions, said Low, fulfilled 
the recommendations of the Crew Safety Review Board.
Ltr., Low to Samuel C. Phillips, "Actions from Apollo Crew Safety Review 
Board and Presentation," Sept. 10, 1968.
September 10-11
The Apollo Crew Safety Review Board, headed by William 
C. Schneider, met for the third time at MSFC, a meeting devoted primarily to 
safety factors for the Saturn V launch vehicle. Of particular concern was the 
capability to shut down the vehicle during the period between ignition and 
liftoff should some problem arise (it could be shut down by several methods, 
including both manual and automatic engine shutdown). The Board also reviewed in 
detail Saturn V modifications that had eliminated more than 50 engine and 
electrical circuitry potential single-point failures (primarily through 
increased redundancy and circuitry checkout). Similarly the Board examined the 
reliability of guidance failure indicators and checkout of the emergency 
detection system during the final portion of the countdown. No additional action 
was needed, members concluded, because all functions in the launch vehicle were 
checked during the terminal count and tank pressure gauges were checked out by 
disconnecting the transducers and testing them individually several days before 
launch.
At the end of the meeting, Board members attended the POGO Management Review, 
where they were favorably impressed by the optimism among Saturn V program 
officials that the pogo problem had been solved (although contingency planning 
for a pogo occurrence should continue through AS-503).
Ltr., Schneider to distr., "Minutes of Third Meeting on September 10-11, 
1968, at Marshall Space Flight Center," Sept. 16, 1968.
September 11
At a meeting of the MSF Management Council, Apollo Program 
Director Samuel C. Phillips put forth a number of recommendations regarding 
planning for extravehicular and scientific activities during the first lunar 
landing missions:
  - During the first mission, extravehicular activities (EVA) should be 
  limited to three hours, with the spacecraft manned by one of the two crewmen 
  at all times. 
  
 - The Apollo Lunar Surface Experiments Package should be deleted from the 
  earliest missions (although the present preliminary sample must be improved 
  scientifically). 
  
 - Television must be carried aboard the LM, for benefits both for 
  operational and public information. 
  
 - To realize the maximum scientific return on the second and subsequent 
  flights, MSC must, during the first landing mission, assess the astronauts' 
  capabilities to conduct lunar surface activities. Also, MSC should study and 
  recommend changes in LM hardware that would lengthen EVA time available for 
  scientific investigations during future Apollo missions.
 
The Management 
Council approved Phillips' recommendations and carried them to Administrator 
James E. Webb for final approval. In Houston, ASPO Manager George M. Low ordered 
his organization to begin planning for the first landing mission in accordance 
with these recommendations.
Memo, Low to O. E. Maynard, "G Mission Planning," Sept. 13, 1968.
September 12
Dale D. Myers, North American Rockwell's Apollo CSM Program 
Manager, wrote George M. Low: "With the recent shipment of CSM 101 to KSC and 
preparations for the first manned Apollo flight, attention is centered on the 
various aspects of crew safety. In this regard, I recently instructed our system 
safety people to review the action items that resulted from the S/C 012 fire 
[January 27, 1967], identify those with safety content or implications, 
determine what corrective action had been accomplished, and assess the adequacy 
of the closeout actions." Myers went on to say that out of a total of 137 North 
American action items, 70 were related to safety; and combining similar and 
identical items resulted in identification of 41 specific safety-oriented action 
items. An exhaustive study by safety personnel had indicated that all items had 
been closed out and that corrective actions were adequate.
Ltr., Myers to Low, ASPO, MSC, Sept. 12, 1968.
September 16
Apollo Program Director Samuel C. Phillips formally 
notified ASPO Manager George M. Low at MSC and Saturn V Program Manager Lee B. 
James at MSFC of changes in the Apollo Program Specification. As agreed on 
during the MSF Management Council meeting on August 6, the Apollo payload 
interface was set at 46,040 kilograms (with a flight geometry reserve of 137 
kilometers per hour). Also, the present spacecraft loading philosophy allowed a 
total spacecraft weight of 46,266 kilograms for lunar missions having less than 
maximum flight geometry requirements. Phillips repeated his earlier statement 
that he was prepared to relax some flight constraints to achieve the best 
possible balance on each space vehicle. (Although with recent changes in Saturn 
V loading, residuals, and J-2 engine thrust, apparently few if any of these 
constraints would have to be relaxed.)
Ltr., Phillips to James and Low, "Apollo Program Specification Changes," 
Sept. 16, 1968.
September 17
Ernest B. Nathan, MSFC Cochairman of the Saturn-Apollo 
Flight Evaluation Panel, sent to MSC Marshall's requirements for the flight crew 
debriefing for the AS-205 mission. Generally, these requirements called for the 
crew's visual and sensory evaluation of the launch vehicle's performance and 
behavior.
Ltr., Nathan to Helmut A. Kuehnel, MSC, Sept. 17, 1968, with encl., "MSFC 
Flight Crew Debriefing Requirements, AS-205/SC-101 Mission."
September 18
Dale D. Myers, Apollo CSM Program Manager at North American 
Rockwell, wrote to CSM Manager Kenneth S. Kleinknecht at MSC to apprise him of 
the company's response to an earlier review of the CSM subsystems development 
program. During February a small task team from MSFC, headed by William A. 
Mrazek, had surveyed the design, manufacture, and checkout of several of the 
spacecraft's subsystems. Findings of the team had been reviewed with Eberhard F. 
M. Rees, then at Downey as head of the Apollo Special Task Team. Myers sent 
Kleinknecht briefing notes of a presentation to Rees and others of the special 
team describing North American's responses to specific issues raised by Mrazek's 
group. These issues, Myers reported, had been resolved to the satisfaction of 
both contractor and customer.
Ltr., Myers to Kleinknecht, Sept. 18, 1968.
September 18
ASPO officials headed by Manager George M. Low met with 
spacecraft managers from North American Rockwell and Grumman to discuss 
configuration management for the remainder of the Apollo program and to set 
forth clear ground rules regarding kinds of changes (described as Class I and 
Class II) and the requisite level of authority for such changes. The outcome of 
this meeting, as Low told Apollo Program Director Samuel C. Phillips, was that 
MSC would pass judgment on all Class I changes and that "nearly every change 
[would] fall in this category." Minor design changes might still be approved at 
the contractor or subcontractor levels, said Low, but MSC would judge whether 
those changes were indeed Class II changes. The overall result of this policy, 
he told Phillips, would be a better awareness by NASA of all changes made by 
spacecraft subcontractors and a firm understanding that only NASA could approve 
Class I design modifications.
Ltr., Low to Phillips, Sept. 19, 1968.
September 23
The Apollo Guidance Software Task Force, which NASA 
Associate Administrator for Manned Space Flight George E. Mueller had convened 
in December 1967, submitted its final report. Purpose of the task force, as 
Mueller had stated at the time, was to determine whether "additional actions . . 
. could be taken to improve the software development and verification process 
and control of it." Between December and July 1968, the group met 14 times at 
NASA and contractor locations to review the historical evolution of software 
programs within the Apollo project. Because of the great complexity of this 
entire field, the task force members recommended that it continue to receive 
attention by top management levels at both MSC and MSFC. And drawing upon 
experience learned in the Apollo program, the task force recommended that 
software not be slighted during any advanced manned programs and that adequate 
resources and experienced personnel be assigned early in the program to this 
vital and easily underestimated area.
Ltr., Mueller to Harold T. Luskin, Apollo Applications Program Director, 
NASA, Sept. 23, 1968, with encl., "Final Report: Apollo Guidance Software Task 
Force," Sept. 23, 1968.
September 24
Samuel C. Phillips announced membership of the OMSF Apollo 
Site Selection Board, which was to meet September 26: Phillips, chairman; Lee R. 
Scherer, OMSF, secretary; John D. Stevenson and Harold D. Luskin, both of OMSF; 
Oran W. Nicks, NASA Hq., John D. Hodge, Owen E. Maynard, and Wilmot N. Hess, all 
of MSC; Ernst Stuhlinger, MSFC: and Roderick O. Middleton, KSC. J. H. Turnock 
and Charles W. Mathews had been deleted from the previous membership list and 
Hodge, Luskin, and Scherer added.
Memo, Apollo Program Director to distr., "Membership of the OMSF Apollo Site 
Selection Board," Sept. 24, 1968.
September 24
Apollo Program Director Samuel C. Phillips wrote to his two 
principal counterparts at MSFC and MSC, Lee B. James and George M. Low, to 
express his concern that the launch-release wind constraint for the Saturn IB, 
currently 45 kilometers, was perhaps the most restrictive of all such 
constraints. Phillips emphasized his need for a complete understanding of all 
tradeoffs associated with this figure, to allow a real-time estimate of the 
requirement to hold. He asked James and Low to summarize for him several such 
tradeoffs before the Apollo 7 flight readiness review: wind versus safety, 
velocity versus direction, and conservative assumption versus technical 
accuracy. Also, he asked for criticality and failure mode for each of the above 
tradeoffs to allow a technical evaluation of increasing the 45-kilometer 
constraint. At the same time, he asked that a similar effort be initiated for 
the Saturn V.
TWX, Phillips to Low and James, "Apollo Saturn Release Wind Constraints," 
Sept. 24, 1968.
September 25
NASA Resident ASPO Manager Wilbur H. Gray at Downey told 
Dale D. Myers, North American Rockwell CSM Manager, that NR quality coverage of 
spacecraft testing no longer provided NASA with confidence in test results and 
that NASA Quality Control would return to monitoring test activities in and from 
the ACE (acceptance checkout equipment) control room. Gray charged that North 
American had progressively backed away from contractually agreed steps of the 
November 30, 1967, Quality Program Plan, and that these actions had affected 
test readiness, testing, and trouble shooting to the point that test acceptance 
could not be accepted with any reasonable assurance. Gray said that - unless 
North American responded by immediate reinstatement of the procedures which, as 
a minimum, were those that worked satisfactorily on CSMs 103 and 104 - NASA 
formal acceptance of operational checkout procedures would be discontinued and 
contractual action initiated. An annotation to George Low from Kenneth S. 
Kleinknecht, MSC's CSM Manager, indicated the letter had been written with the 
concurrence and at the suggestion of Kleinknecht.
Myers replied: "I regret that NASA feels any lack of confidence in current 
test results. . . . For the past year, there has been a constant improvement 
program carried out in Test Quality Assurance to (1) perform quality evaluation 
and acceptance of test results in real time and (2) upgrade the test discipline 
to be consistent with good quality practice. I believe that this improvement 
program has been effective and is evidenced by the current efficiency of test 
and expedient manner in which test paper work is being closed out. While there 
is naturally some cost benefit experienced from the successful improvements, 
cost never has been placed as a criteria above quality. . . .
"Again, I want to emphasize that the CSM Program has not nor will not 
intentionally place cost ahead of quality. . . . The procedures which worked 
satisfactorily on CSM 103 and 104 are being improved to provide better test 
discipline and more effective Quality Assurance coverage. Test progress on CSM 
106 to date indicates a greater test effectiveness and a greater confidence in 
test results than any previous CSM's."
Ltr., Gray to Myers, Sept. 25, 1968; annotation, Kleinknecht to Low, Sept. 
26, 1968; ltr., Myers to Gray, Oct. 17, 1968.
September 25
The LM ascent engine to be flown in LM-3 and subsequent 
missions would incorporate the Rocketdyne injector, Apollo Program Director 
Phillips informed ASPO Manager Low. The engine would be assembled and delivered 
by Rocketdyne under subcontract to Grumman. MSC was authorized to inform those 
concerned of these decisions but would not issue contractual direction until an 
agreed course of contractual action had been approved by NASA Hq. Two days 
later, on September 27, Phillips advised Low that MSC was authorized to take all 
proper contract actions to implement the decision to contract with Grumman for 
ascent-stage engines assembled by Rocketdyne with the latter's injector.
TWXs, NASA Headquarters to MSC, Attn: George Low, "LM Ascent Engine Program 
Decision," Sept. 25, 1968; and "LM Ascent Engine Program," Sept. 27, 1968.
September 26
MSC Director Robert R. Gilruth sent Eberhard F. M. Rees, 
MSFC Deputy Director, his "personal commendation" and appreciation for Rees's 
leadership of the Apollo Special Task Team and its efforts to bring the CSM 
program out of the difficult period early in 1967. The work of Rees and his 
group, said Gilruth, had made an outstanding contribution to the Apollo program 
and had given NASA management "a significantly higher level of technical 
confidence" that the Block II spacecraft could safely perform its mission. In 
addition, Gilruth noted, Rees's "diplomacy in interfacing with North American 
management also created a much better NASA-contractor relationship and mutual 
understanding of program technical requirements."
Ltr., Gilruth to Rees, Sept. 26, 1968.
Week Ending September 27
The Allison descent-stage propellant tank, 
being redesigned at Airite Division of Sargent Industries to a "lidless" 
configuration, blew up during qualification test at Airite. The crew noticed 
loss of pressure and therefore tightened fittings and repressurized. As the 
pressure went up, the tank blew into several pieces. Grumman dispatched a team 
to Airite to determine the cause and the necessary corrective action.
Memo, Frank X. Battersby, RASPO, Bethpage, to Chief, Apollo Procurement Br., 
Procurement and Contracts Div., MSC, "Weekly Activities Report, BMR, Bethpage, 
Week Ending September 27," Oct. 3, 1968.
September 28
Results of a joint MSFC-MSC review of functional interfaces 
between the launch vehicle and spacecraft for Apollo 7 were forwarded to NASA 
Hq. (The review had originally been requested by the Apollo 7 Crew Safety Review 
Board, headed by John D. Hodge.) The two Centers had tackled the task by 
identifying all electrical wiring between payload and booster, the requirement 
for each wire, a verification that the circuits indeed satisfied requirements, 
and an evaluation of the adequacy of test and checkout procedures. Several 
months of investigation, reported Teir and Low, had uncovered no areas of 
concern. Definition and function of the CSM instrument unit were both accurate 
and valid and ensured flight readiness.
Ltr., Saturn IB Manager William Teir, MSFC, and ASPO Manager George M. Low, 
MSC, to Samuel C. Phillips, NASA Hq., "Apollo 7 Launch Vehicle to Spacecraft 
Functional Interface Review," Sept. 28, 1968, with encl.,"AS-205 Launch 
Vehicle/Spacecraft (LV/SC) Electrical Interface Review."
September 30
NASA Associate Administrator for Manned Space Flight George 
E. Mueller summarized for his superiors launch preparation for the near-term 
missions Apollo 7 and Apollo 8:
  - Apollo 7 - Space vehicle testing was on schedule (despite a delay in start 
  of the flight readiness test caused by a liquid hydrogen leak due to a faulty 
  pneumatic valve). The flight readiness test began on September 25 and went 
  smoothly through T minus 0 two days later. Countdown for launch would begin as 
  scheduled on October 6, leading to launch readiness on October 11. 
  
 - Apollo 8 - Both launch vehicle (503) and spacecraft (103) were several 
  days behind schedule. CSM 103 was tested in the altitude chamber while manned 
  by the prime and backup crews on September 20 and 22. The spacecraft was 
  undergoing several modifications and equipment installations (including the 
  high-gain antenna, which was delivered to KSC on September 23); KSC and 
  contractor technicians also were making leak and functional checks on the S-II 
  stage and subsystem checks on the S-IVB stage of the launch vehicle. Rollout 
  of the space vehicle from the assembly building to the pad was planned for 
  October 10.
 
Memo, Mueller to Administrator and Deputy Administrator, 
"Manned Space Flight Weekly Report - September 30, 1968," Sept. 30, 1968.
September 30
Apollo Program Director Samuel C. Phillips asked ASPO 
Manager George M. Low to investigate the feasibility of using data from the D 
and G missions to increase NASA's knowledge of and confidence in the operational 
capabilities of the extravehicular mobility unit (EMU). Phillips included in his 
request specific recommendations for additional instrumentation to obtain the 
necessary data. His action stemmed from a general concern about the extent and 
complexity of surface operations on the first lunar landing flight (which might 
substantially reduce chances for successful completion). For this reason, he and 
other program officials had stringently limited the number of objectives and the 
extent of those surface activities. But to plan confidently for surface EVA 
during follow-on Apollo landing missions, Phillips said, as much information as 
possible had to be gathered about the operational capability of the crew and the 
EMU.
Ltr., Phillips to Low, "Data for an EVA Capability Assessment," Sept. 30, 
1968.